4113 N WOODMAN AVE 91423

Certificate Information: 4113 N WOODMAN AVE 91423

Application / Permit
22010-20000-00723
Plan Check / Job No.
B22VN02335
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 72'-9" X 48' TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NPFA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 12/20/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/17/2022 SELLA BENYAMIN
Corrections Issued 3/22/2022 SELLA BENYAMIN
Quality Review Completed 3/30/2022 STEVEN KIM
Building Plans Picked Up 3/30/2022 APPLICANT
Plan Check Approved 10/7/2022 SELLA BENYAMIN
Issued 12/20/2022 APPLICANT
CofO in Progress 10/10/2025 MISAEL ESPARZA
Permit Finaled 11/6/2025 RUBEN SALAS
CofO Issued 11/6/2025 RUBEN SALAS
Permit Finaled 11/6/2025 RUBEN SALAS

Permit Application Clearance Information

Permit Cleared 4/21/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/25/2022 CARLOS AGUILERA
Sewer availability Cleared 4/25/2022 CARLOS AGUILERA
Trees in Parkway Cleared 6/6/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 7/3/2022 RUEL COLE
Low Impact Development Cleared 7/26/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 7/26/2022 CARLOS AGUILERA
GPI Written Notices Cleared 10/7/2022 SELLA BENYAMIN
Grading Pre-Inspection Cleared 10/7/2022 SELLA BENYAMIN

Contact Information

Contractor Owner-Builder       ,
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 1792 PEREGRINE CT      SIMI VALLEY, CA 93065

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/12/2023 Corrections Issued JOHN COLEMAN
Footing/Foundation/Slab 6/12/2023 Partial Approval JOHN COLEMAN
Underground Mechanical 6/26/2023 Partial Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 6/28/2023 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 6/29/2023 Not Ready for Inspection JOHN COLEMAN
Footing/Foundation/Slab 7/28/2023 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 9/7/2023 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 9/7/2023 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 10/12/2023 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/12/2023 Corrections Issued MISAEL ESPARZA
Green Building Rough 10/12/2023 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 10/12/2023 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 10/12/2023 Not Ready for Inspection MISAEL ESPARZA
Deputy Wood Construction 10/13/2023 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/27/2023 Corrections Issued MISAEL ESPARZA
Gas Test 12/11/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 12/11/2023 Not Ready for Inspection MISAEL ESPARZA
Sewer 12/11/2023 Approved MISAEL ESPARZA
Underground Mechanical 12/11/2023 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/15/2024 Corrections Issued MISAEL ESPARZA
BUILDING-Rough-Frame 4/11/2024 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Corrections Issued MISAEL ESPARZA
Green Building Rough 4/11/2024 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 4/11/2024 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 5/20/2024 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 5/20/2024 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 6/18/2024 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/18/2024 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 6/18/2024 Approved MISAEL ESPARZA
Green Building Rough 6/18/2024 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 6/18/2024 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 6/18/2024 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/26/2024 Not Ready for Inspection JOHN COLEMAN
Wood Frame 6/26/2024 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 6/27/2024 Corrections Issued JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 6/27/2024 Partial Approval JOHN COLEMAN
HVAC-Rough 6/27/2024 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Rough 6/27/2024 Partial Approval JOHN COLEMAN
ELECTRICAL-Rough 7/2/2024 Approved SALVADOR MARTINEZ
HVAC-Rough 7/2/2024 Approved SALVADOR MARTINEZ
PLUMBING-Rough 7/2/2024 Partial Approval SALVADOR MARTINEZ
BUILDING-Rough-Frame 7/3/2024 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Approved JACK KARGODORIAN
Green Building Rough 7/3/2024 Approved JACK KARGODORIAN
Verify Sprinkler Sign Off 7/3/2024 Approved JACK KARGODORIAN
Wood Frame 7/3/2024 Approved JACK KARGODORIAN
Insulation 7/17/2024 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 7/26/2024 Approved MICHAEL CORTEZ
Shower Pan 7/26/2024 Approved MICHAEL CORTEZ
Drywall Nailing 7/31/2024 Partial Inspection MISAEL ESPARZA
Deputy Drilled-In Anchors 4/10/2025 Conditional Approval JUAN VALENZUELA
Deputy Reinf. Concrete 4/10/2025 Conditional Approval JUAN VALENZUELA
Pre-Inspection 5/13/2025 Partial Inspection MISAEL ESPARZA
Service/Power Release 5/13/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 8/19/2025 Corrections Issued JAVIER RAMOS JR
Final 8/19/2025 Corrections Issued JAVIER RAMOS JR
HVAC-Final 8/19/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Final 8/19/2025 Corrections Issued JAVIER RAMOS JR
Smoke Detectors 8/19/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 8/29/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 8/29/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 8/29/2025 No Access for Inspection MISAEL ESPARZA
ELECTRICAL-Final 9/3/2025 Not Ready for Inspection MISAEL ESPARZA
Final 9/3/2025 Corrections Issued MISAEL ESPARZA
Green Building Final 9/3/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 9/3/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 9/3/2025 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/3/2025 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 9/3/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 9/23/2025 Approved MISAEL ESPARZA
Final 9/23/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 9/23/2025 Approved MISAEL ESPARZA
HVAC-Final 9/23/2025 Approved MISAEL ESPARZA
PLUMBING-Final 9/23/2025 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/23/2025 SGSOV Approved MISAEL ESPARZA
Service/Power Release 9/23/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 9/26/2025 Partial Approval MISAEL ESPARZA
HVAC-Final 9/26/2025 Partial Approval MISAEL ESPARZA
PLUMBING-Final 9/26/2025 Partial Approval MISAEL ESPARZA
Service/Power Release 9/26/2025 Not Ready for Inspection MISAEL ESPARZA
Final 10/2/2025 OK to Issue CofO MISAEL ESPARZA
Service/Power Release 10/2/2025 Approved MISAEL ESPARZA