4113 N WOODMAN AVE 91423
Certificate Information: 4113 N WOODMAN AVE 91423
- Application / Permit
- 22010-20000-00723
- Plan Check / Job No.
- B22VN02335
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 72'-9" X 48' TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NPFA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 12/20/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/17/2022 | SELLA BENYAMIN |
| Corrections Issued | 3/22/2022 | SELLA BENYAMIN |
| Quality Review Completed | 3/30/2022 | STEVEN KIM |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Plan Check Approved | 10/7/2022 | SELLA BENYAMIN |
| Issued | 12/20/2022 | APPLICANT |
| CofO in Progress | 10/10/2025 | MISAEL ESPARZA |
| Permit Finaled | 11/6/2025 | RUBEN SALAS |
| CofO Issued | 11/6/2025 | RUBEN SALAS |
| Permit Finaled | 11/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Permit | Cleared | 4/21/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/25/2022 | CARLOS AGUILERA |
| Trees in Parkway | Cleared | 6/6/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 7/3/2022 | RUEL COLE |
| Low Impact Development | Cleared | 7/26/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 7/26/2022 | CARLOS AGUILERA |
| GPI Written Notices | Cleared | 10/7/2022 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 10/7/2022 | SELLA BENYAMIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Warling,, Jeffrey Paul; Lic. No.: C43743 | 1792 PEREGRINE CT SIMI VALLEY, CA 93065 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/12/2023 | Corrections Issued | JOHN COLEMAN |
| Footing/Foundation/Slab | 6/12/2023 | Partial Approval | JOHN COLEMAN |
| Underground Mechanical | 6/26/2023 | Partial Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/28/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 6/29/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Footing/Foundation/Slab | 7/28/2023 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 9/7/2023 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/7/2023 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/12/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 10/12/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 10/12/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 10/12/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Deputy Wood Construction | 10/13/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2023 | Corrections Issued | MISAEL ESPARZA |
| Gas Test | 12/11/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 12/11/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Sewer | 12/11/2023 | Approved | MISAEL ESPARZA |
| Underground Mechanical | 12/11/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/11/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 4/11/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 4/11/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 5/20/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 5/20/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/18/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/18/2024 | Approved | MISAEL ESPARZA |
| Green Building Rough | 6/18/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 6/18/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 6/18/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Not Ready for Inspection | JOHN COLEMAN |
| Wood Frame | 6/26/2024 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Rough | 6/27/2024 | Corrections Issued | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2024 | Partial Approval | JOHN COLEMAN |
| HVAC-Rough | 6/27/2024 | Not Ready for Inspection | JOHN COLEMAN |
| PLUMBING-Rough | 6/27/2024 | Partial Approval | JOHN COLEMAN |
| ELECTRICAL-Rough | 7/2/2024 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 7/2/2024 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 7/2/2024 | Partial Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 7/3/2024 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2024 | Approved | JACK KARGODORIAN |
| Green Building Rough | 7/3/2024 | Approved | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 7/3/2024 | Approved | JACK KARGODORIAN |
| Wood Frame | 7/3/2024 | Approved | JACK KARGODORIAN |
| Insulation | 7/17/2024 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/26/2024 | Approved | MICHAEL CORTEZ |
| Shower Pan | 7/26/2024 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 7/31/2024 | Partial Inspection | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 4/10/2025 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 4/10/2025 | Conditional Approval | JUAN VALENZUELA |
| Pre-Inspection | 5/13/2025 | Partial Inspection | MISAEL ESPARZA |
| Service/Power Release | 5/13/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/19/2025 | Corrections Issued | JAVIER RAMOS JR |
| Final | 8/19/2025 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 8/19/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Final | 8/19/2025 | Corrections Issued | JAVIER RAMOS JR |
| Smoke Detectors | 8/19/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 8/29/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 8/29/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 8/29/2025 | No Access for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 9/3/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 9/3/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 9/3/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 9/3/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 9/3/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 9/3/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 9/3/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 9/23/2025 | Approved | MISAEL ESPARZA |
| Final | 9/23/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 9/23/2025 | Approved | MISAEL ESPARZA |
| HVAC-Final | 9/23/2025 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 9/23/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 9/23/2025 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 9/23/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 9/26/2025 | Partial Approval | MISAEL ESPARZA |
| HVAC-Final | 9/26/2025 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Final | 9/26/2025 | Partial Approval | MISAEL ESPARZA |
| Service/Power Release | 9/26/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 10/2/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 10/2/2025 | Approved | MISAEL ESPARZA |