6949-6951 N CEDROS AVE 91405
Certificate Information: 6949-6951 N CEDROS AVE 91405
- Application / Permit
- 22010-20000-00711
- Plan Check / Job No.
- B22VN02304
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* CONVERT (E) ATTACHED 2-CAR GARAGE (ZC: 371 SF) INTO ADU PER CA GC 65852.2(e)(1)(A). ALL CONSTRUCTION PER WFPP.
- Permit Issued
- Issued on 8/25/2022
- Issuing Office
- Current Status
- CofO Issued on 10/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/8/2022 | VIVIAN LAO |
| Corrections Issued | 3/8/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 5/19/2022 | VIVIAN LAO |
| Plan Check Approved | 8/9/2022 | VIVIAN LAO |
| Issued | 8/25/2022 | APPLICANT |
| CofO in Progress | 10/29/2024 | RYAN SALAZAR |
| Permit Finaled | 10/29/2024 | DANIEL ORRANTE |
| CofO Issued | 10/29/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/29/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/5/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/5/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/5/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/27/2022 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 11/7/2022 | Approved | RICHARD DOCKUS |
| Underground Mechanical | 11/17/2022 | Corrections Issued | RICHARD DOCKUS |
| Underground Mechanical | 11/21/2022 | Corrections Issued | WILLIAM WREN |
| Wood Frame | 11/21/2022 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 11/23/2022 | Not Ready for Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 12/1/2022 | Approved | RYAN SALAZAR |
| HVAC-Rough | 12/1/2022 | Corrections Issued | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/1/2022 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 12/1/2022 | Approved | RYAN SALAZAR |
| Insulation | 3/15/2023 | Approved | RYAN SALAZAR |
| Pre-Inspection | 3/15/2023 | Partial Inspection | RYAN SALAZAR |
| Underground Mechanical | 7/6/2023 | No Access for Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/3/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 9/3/2024 | Approved | RYAN SALAZAR |
| Final | 9/3/2024 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 9/3/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 9/3/2024 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 9/3/2024 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 9/3/2024 | Approved | RYAN SALAZAR |
| Final | 10/22/2024 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 10/22/2024 | Approved | RYAN SALAZAR |