6620 N TYRONE AVE 91405

Certificate Information: 6620 N TYRONE AVE 91405

Application / Permit
22010-20000-00696
Plan Check / Job No.
B22VN02251
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 42'-6" X 23'-0" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
Permit Issued
Issued on 12/1/2022
Issuing Office
Valley
Current Status
CofO Issued on 10/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/18/2022 APPLICANT
Assigned to Plan Check Engineer 2/25/2022 ARTIN ZARUKIAN
Corrections Issued 2/26/2022 ARTIN ZARUKIAN
Building Plans Picked Up 3/1/2022 APPLICANT
Issued 12/1/2022 APPLICANT
CofO in Progress 9/8/2023 RYAN SALAZAR
Permit Finaled 10/13/2023 RUBEN SALAS
CofO Issued 10/13/2023 RUBEN SALAS
Permit Finaled 10/13/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/1/2022 CARLOS AGUILERA
CPC Cleared 3/2/2022 LAUREN PADICK
Eng Process Fee Ord 176,300 Cleared 3/3/2022 CARLOS AGUILERA
Sewer availability Cleared 3/3/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 3/24/2022 LAURINDA MEADE
Low Impact Development Cleared 5/12/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 5/12/2022 CARLOS AGUILERA
HPOZ Cleared 11/22/2022 SUKI GERSHENHORN
ZI Cleared 11/22/2022 SUKI GERSHENHORN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/3/2023 Partial Approval RYAN SALAZAR
PLUMBING-Rough 1/3/2023 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 1/12/2023 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 3/8/2023 Approved RYAN SALAZAR
HVAC-Rough 3/8/2023 Approved RYAN SALAZAR
PLUMBING-Rough 3/8/2023 Approved RYAN SALAZAR
Sewer 3/8/2023 Approved RYAN SALAZAR
Underground Mechanical 3/8/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/11/2023 Partial Approval RYAN SALAZAR
Wood Frame 4/11/2023 Approved RYAN SALAZAR
Insulation 4/17/2023 Approved RYAN SALAZAR
Drywall Nailing 4/24/2023 Approved RYAN SALAZAR
Green Building Rough 4/24/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/24/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 9/6/2023 Approved RYAN SALAZAR
ELECTRICAL-Final 9/6/2023 Approved RYAN SALAZAR
Final 9/6/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 9/6/2023 Approved RYAN SALAZAR
HVAC-Final 9/6/2023 Approved RYAN SALAZAR
PLUMBING-Final 9/6/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 9/6/2023 SGSOV Approved RYAN SALAZAR
Service/Power Release 9/6/2023 Approved RYAN SALAZAR
Smoke Detectors 9/6/2023 Approved RYAN SALAZAR
Verify Sprinkler Sign Off 9/6/2023 Approved RYAN SALAZAR