6620 N TYRONE AVE 91405
Certificate Information: 6620 N TYRONE AVE 91405
- Application / Permit
- 22010-20000-00696
- Plan Check / Job No.
- B22VN02251
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 42'-6" X 23'-0" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 12/1/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/25/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 2/26/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 3/1/2022 | APPLICANT |
| Issued | 12/1/2022 | APPLICANT |
| CofO in Progress | 9/8/2023 | RYAN SALAZAR |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
| CofO Issued | 10/13/2023 | RUBEN SALAS |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/1/2022 | CARLOS AGUILERA |
| CPC | Cleared | 3/2/2022 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/3/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/24/2022 | LAURINDA MEADE |
| Low Impact Development | Cleared | 5/12/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 5/12/2022 | CARLOS AGUILERA |
| HPOZ | Cleared | 11/22/2022 | SUKI GERSHENHORN |
| ZI | Cleared | 11/22/2022 | SUKI GERSHENHORN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/3/2023 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 1/3/2023 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 1/12/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 3/8/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 3/8/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 3/8/2023 | Approved | RYAN SALAZAR |
| Sewer | 3/8/2023 | Approved | RYAN SALAZAR |
| Underground Mechanical | 3/8/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/11/2023 | Partial Approval | RYAN SALAZAR |
| Wood Frame | 4/11/2023 | Approved | RYAN SALAZAR |
| Insulation | 4/17/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 4/24/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 4/24/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 4/24/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 9/6/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 9/6/2023 | Approved | RYAN SALAZAR |
| Final | 9/6/2023 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 9/6/2023 | Approved | RYAN SALAZAR |
| HVAC-Final | 9/6/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 9/6/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 9/6/2023 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 9/6/2023 | Approved | RYAN SALAZAR |
| Smoke Detectors | 9/6/2023 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 9/6/2023 | Approved | RYAN SALAZAR |