10911 N NESTLE AVE 91326

Certificate Information: 10911 N NESTLE AVE 91326

Application / Permit
22010-20000-00677
Plan Check / Job No.
B22VN02234
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 43'-0" X 18'-4" TWO STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 1/9/2023
Issuing Office
Current Status
CofO Issued on 9/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/3/2022 APPLICANT
Assigned to Plan Check Engineer 3/11/2022 ARTIN ZARUKIAN
Corrections Issued 3/13/2022 ARTIN ZARUKIAN
Building Plans Picked Up 3/18/2022 APPLICANT
Plan Check Approved 11/3/2022 MIROOSH KHACHATOORIAN
Issued 1/9/2023 APPLICANT
CofO in Progress 9/1/2023 DAVID SCANTLIN
Permit Finaled 9/11/2023 JOHN JANSON
CofO Issued 9/11/2023 JOHN JANSON
Permit Finaled 9/11/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/14/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/15/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 6/15/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 7/1/2022 KURT CORRAL
Construction near power lines Cleared 7/6/2022 TINA MIRANDA
Low Impact Development Cleared 8/1/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/16/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/3/2023 Approved DAVID SCANTLIN
PLUMBING-Rough 3/3/2023 Approved DAVID SCANTLIN
Pre-Inspection 3/3/2023 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 4/4/2023 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 4/13/2023 Partial Approval JEFFREY BULL
Green Building Rough 4/13/2023 Not Ready for Inspection JEFFREY BULL
Verify Sprinkler Sign Off 4/13/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 4/25/2023 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 4/25/2023 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 4/25/2023 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 4/25/2023 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 4/25/2023 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 5/3/2023 Approved DAVID SCANTLIN
HVAC-Rough 5/3/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 5/3/2023 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 5/3/2023 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 5/10/2023 Approved DAVID SCANTLIN
ELECTRICAL-Rough 5/10/2023 Approved DAVID SCANTLIN
Green Building Rough 5/10/2023 Approved DAVID SCANTLIN
HVAC-Rough 5/10/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 5/10/2023 Partial Approval DAVID SCANTLIN
PLUMBING-Rough 5/10/2023 Approved DAVID SCANTLIN
Wood Frame 5/10/2023 Approved DAVID SCANTLIN
Gas Test 5/16/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 5/16/2023 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 5/16/2023 SGSOV Approved DAVID SCANTLIN
Insulation 5/30/2023 Corrections Issued JUSTIN HAWLEY
Shower Pan 5/30/2023 Approved JUSTIN HAWLEY
Drywall Nailing 6/1/2023 Approved DAVID SCANTLIN
Drywall Nailing 6/1/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 6/1/2023 Approved DAVID SCANTLIN
ELECTRICAL-Rough 6/21/2023 Not Ready for Inspection DAVID SCANTLIN
Final 8/31/2023 OK to Issue CofO DAVID SCANTLIN
Green Building Final 8/31/2023 Approved DAVID SCANTLIN
Service/Power Release 8/31/2023 Approved DAVID SCANTLIN
Smoke Detectors 8/31/2023 Approved DAVID SCANTLIN