5864 N HILLVIEW PARK AVE 91401

Certificate Information: 5864 N HILLVIEW PARK AVE 91401

Application / Permit
22010-20000-00674
Plan Check / Job No.
B22VN02218
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY ADU PER CA Govt. Code 65852.2(e)(1)(B) and LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 4/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 4/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/14/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 KHEDER ALRAZAA
Corrections Issued 2/27/2022 KHEDER ALRAZAA
Quality Review Completed 3/8/2022 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 3/15/2022 APPLICANT
Applicant returned to address corrections 3/22/2023 KHEDER ALRAZAA
Plan Check Approved 4/11/2023 KHEDER ALRAZAA
Issued 4/14/2023 APPLICANT
CofO in Progress 4/22/2025 GAREN HAYRAPETYAN
Permit Finaled 4/25/2025 RUBEN SALAS
CofO Issued 4/25/2025 RUBEN SALAS
Permit Finaled 4/25/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/27/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 4/28/2022 ROMAN GUTIERREZ
Low Impact Development Cleared 11/14/2022 LUIS LUVANO
Roof/Waste drainage to street Cleared 11/17/2022 ROMAN GUTIERREZ
Hydrant and Access approval Cleared 2/22/2023 LAVEON RIDER
Construction near power lines Cleared 3/10/2023 WALTER RAMIREZ
Abandoned oil well Cleared 3/16/2023 LAVEON RIDER
Sewer availability Cleared 3/20/2023 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/8/2023 Corrections Issued JUAN VALENZUELA
METHANE-Barrier 6/8/2023 Not Ready for Inspection JUAN VALENZUELA
METHANE-Subgrade 6/8/2023 Corrections Issued JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 6/29/2023 Approved JUAN VALENZUELA
Footing/Foundation/Slab 6/29/2023 Approved JUAN VALENZUELA
METHANE-Barrier 6/29/2023 Approved JUAN VALENZUELA
METHANE-Subgrade 6/29/2023 Approved JUAN VALENZUELA
Underground Mechanical 7/27/2023 Approved KIRK SANDERS
Wood Frame 7/27/2023 Partial Approval KIRK SANDERS
Insulation 8/1/2023 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/16/2023 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/5/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/9/2024 Approved JOSE AVILA
PLUMBING-Rough 1/9/2024 Approved JOSE AVILA
HVAC-Rough 1/16/2024 Approved CRAIG DAVIS
Interior/Exterior Lathing 1/16/2024 Approved CRAIG DAVIS
HVAC-Rough 1/22/2024 Approved JOSE AVILA
Sewer 1/26/2024 Approved JOSE AVILA
Underground Mechanical 1/26/2024 Partial Approval JOSE AVILA
ELECTRICAL-Rough 2/7/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 2/15/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 2/20/2024 Corrections Issued MISAEL ESPARZA
Green Building Rough 2/20/2024 Approved MISAEL ESPARZA
METHANE-Rough 2/20/2024 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 2/20/2024 Approved MISAEL ESPARZA
Insulation 3/11/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Insulation 3/13/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 3/20/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 3/20/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 3/27/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 5/22/2024 Approved SALVADOR MARTINEZ
Shower Pan 5/22/2024 Approved SALVADOR MARTINEZ
HVAC-Final 2/10/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Final 2/10/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 2/19/2025 Approved GAREN HAYRAPETYAN
Final 3/3/2025 Corrections Issued JOSE AVILA
Green Building Final 3/3/2025 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 3/3/2025 SGSOV Not Ready JOSE AVILA
Service/Power Release 3/3/2025 Not Ready for Inspection JOSE AVILA
Smoke Detectors 3/3/2025 Approved JOSE AVILA
Final 3/11/2025 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/11/2025 SGSOV Not Ready OGANES TARAKHCHYAN
Final 3/13/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Green Building Final 3/13/2025 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 3/13/2025 SGSOV Approved GAREN HAYRAPETYAN
Service/Power Release 3/13/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Final 3/18/2025 Partial Inspection RAUL OLAGI
Service/Power Release 4/11/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Final 4/14/2025 Corrections Issued OGANES TARAKHCHYAN
Final 4/22/2025 OK to Issue CofO GAREN HAYRAPETYAN
Service/Power Release 4/22/2025 Approved GAREN HAYRAPETYAN