5864 N HILLVIEW PARK AVE 91401
Certificate Information: 5864 N HILLVIEW PARK AVE 91401
- Application / Permit
- 22010-20000-00674
- Plan Check / Job No.
- B22VN02218
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 1-STORY ADU PER CA Govt. Code 65852.2(e)(1)(B) and LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 4/14/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | KHEDER ALRAZAA |
| Corrections Issued | 2/27/2022 | KHEDER ALRAZAA |
| Quality Review Completed | 3/8/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 3/15/2022 | APPLICANT |
| Applicant returned to address corrections | 3/22/2023 | KHEDER ALRAZAA |
| Plan Check Approved | 4/11/2023 | KHEDER ALRAZAA |
| Issued | 4/14/2023 | APPLICANT |
| CofO in Progress | 4/22/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 4/25/2025 | RUBEN SALAS |
| CofO Issued | 4/25/2025 | RUBEN SALAS |
| Permit Finaled | 4/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/27/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2022 | ROMAN GUTIERREZ |
| Low Impact Development | Cleared | 11/14/2022 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 11/17/2022 | ROMAN GUTIERREZ |
| Hydrant and Access approval | Cleared | 2/22/2023 | LAVEON RIDER |
| Construction near power lines | Cleared | 3/10/2023 | WALTER RAMIREZ |
| Abandoned oil well | Cleared | 3/16/2023 | LAVEON RIDER |
| Sewer availability | Cleared | 3/20/2023 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/8/2023 | Corrections Issued | JUAN VALENZUELA |
| METHANE-Barrier | 6/8/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| METHANE-Subgrade | 6/8/2023 | Corrections Issued | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 6/29/2023 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/29/2023 | Approved | JUAN VALENZUELA |
| METHANE-Barrier | 6/29/2023 | Approved | JUAN VALENZUELA |
| METHANE-Subgrade | 6/29/2023 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 7/27/2023 | Approved | KIRK SANDERS |
| Wood Frame | 7/27/2023 | Partial Approval | KIRK SANDERS |
| Insulation | 8/1/2023 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2023 | Corrections Issued | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Partial Approval | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2024 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 1/9/2024 | Approved | JOSE AVILA |
| HVAC-Rough | 1/16/2024 | Approved | CRAIG DAVIS |
| Interior/Exterior Lathing | 1/16/2024 | Approved | CRAIG DAVIS |
| HVAC-Rough | 1/22/2024 | Approved | JOSE AVILA |
| Sewer | 1/26/2024 | Approved | JOSE AVILA |
| Underground Mechanical | 1/26/2024 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 2/7/2024 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 2/15/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 2/20/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 2/20/2024 | Approved | MISAEL ESPARZA |
| METHANE-Rough | 2/20/2024 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 2/20/2024 | Approved | MISAEL ESPARZA |
| Insulation | 3/11/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 3/13/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 3/20/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 3/20/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 3/27/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 5/22/2024 | Approved | SALVADOR MARTINEZ |
| Shower Pan | 5/22/2024 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 2/10/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Final | 2/10/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 2/19/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 3/3/2025 | Corrections Issued | JOSE AVILA |
| Green Building Final | 3/3/2025 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 3/3/2025 | SGSOV Not Ready | JOSE AVILA |
| Service/Power Release | 3/3/2025 | Not Ready for Inspection | JOSE AVILA |
| Smoke Detectors | 3/3/2025 | Approved | JOSE AVILA |
| Final | 3/11/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 3/11/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 3/13/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Green Building Final | 3/13/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 3/13/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 3/13/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Final | 3/18/2025 | Partial Inspection | RAUL OLAGI |
| Service/Power Release | 4/11/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 4/14/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Final | 4/22/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Service/Power Release | 4/22/2025 | Approved | GAREN HAYRAPETYAN |