3064 S FIELD AVE 90016
Certificate Information: 3064 S FIELD AVE 90016
- Application / Permit
- 22010-20000-00670
- Plan Check / Job No.
- B22VN02207
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED DETACHED ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 7/15/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | MICHAEL LOPEZ |
| Corrections Issued | 3/3/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 3/4/2022 | SEAN DANG |
| Building Plans Picked Up | 3/8/2022 | APPLICANT |
| Plan Check Approved | 7/7/2022 | MICHAEL LOPEZ |
| Issued | 7/15/2022 | APPLICANT |
| CofO in Progress | 2/2/2024 | JUSTIN HAWLEY |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
| CofO Issued | 2/7/2024 | DEROLD HAUFF |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/8/2022 | CINDY QI |
| CPC | Cleared | 3/8/2022 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2022 | CINDY QI |
| Sewer availability | Cleared | 3/10/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 4/11/2022 | LAURINDA MEADE |
| Low Impact Development | Cleared | 5/3/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 5/5/2022 | CINDY QI |
| Construction near power lines | Cleared | 6/1/2022 | RIDWAN HARDY |
| Flood clearance | Cleared | 6/30/2022 | BRYAN GATHUKA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 9/27/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/30/2022 | Partial Approval | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 9/30/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 9/30/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 9/30/2022 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/11/2022 | Partial Approval | STUART CHAPMAN |
| Deputy Wood Construction | 10/11/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 10/11/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 10/11/2022 | Approved | STUART CHAPMAN |
| Wood Frame | 10/11/2022 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/20/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Rough | 10/20/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 10/20/2022 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 11/23/2022 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 11/23/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Rough | 11/23/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 11/23/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 11/23/2022 | Approved | STUART CHAPMAN |
| Wood Frame | 11/23/2022 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 12/2/2022 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 12/12/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Rough | 12/12/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 12/12/2022 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/20/2022 | Corrections Issued | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2022 | Corrections Issued | CALEB MEISTER |
| Green Building Rough | 12/20/2022 | Corrections Issued | CALEB MEISTER |
| Wood Frame | 12/20/2022 | Not Ready for Inspection | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2023 | Partial Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 4/10/2023 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 4/10/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 4/10/2023 | Approved | CALEB MEISTER |
| HVAC-Rough | 4/10/2023 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 4/10/2023 | Approved | CALEB MEISTER |
| Wood Frame | 4/10/2023 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2023 | Not Ready for Inspection | CALEB MEISTER |
| Insulation | 4/25/2023 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 4/25/2023 | Partial Approval | CALEB MEISTER |
| Shower Pan | 5/12/2023 | Approved | CALEB MEISTER |
| Insulation | 5/17/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 5/23/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 6/13/2023 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 6/16/2023 | Partial Approval | STUART CHAPMAN |
| Underground Mechanical | 7/21/2023 | Not Ready for Inspection | CALEB MEISTER |
| Gas Test | 8/7/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 8/7/2023 | Not Ready for Inspection | CALEB MEISTER |
| Service/Power Release | 8/7/2023 | Not Ready for Inspection | CALEB MEISTER |
| Sewer | 8/7/2023 | Approved | CALEB MEISTER |
| Underground Mechanical | 8/7/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Final | 10/2/2023 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Final | 10/2/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Final | 10/2/2023 | Not Ready for Inspection | CALEB MEISTER |
| FLOOD-Elevation Certificate | 11/21/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 11/21/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 11/21/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Final | 11/21/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Pre-Inspection | 11/21/2023 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Service/Power Release | 11/21/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 11/21/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Pre-Inspection | 11/29/2023 | No Access for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 12/4/2023 | SGSOV Not Ready | JUSTIN HAWLEY |
| Final | 12/5/2023 | Corrections Issued | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 12/5/2023 | SGSOV Approved | JUSTIN HAWLEY |
| FLOOD-Elevation Certificate | 12/14/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 12/14/2023 | Corrections Issued | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 12/14/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Gas Test | 12/14/2023 | Approved | JUSTIN HAWLEY |
| Green Building Final | 12/14/2023 | Approved | JUSTIN HAWLEY |
| Pre-Inspection | 12/14/2023 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 12/14/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Smoke Detectors | 12/14/2023 | Approved | JUSTIN HAWLEY |
| FLOOD-Elevation Certificate | 12/22/2023 | Approved | JUSTIN HAWLEY |
| Final | 12/22/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 12/22/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| Service/Power Release | 12/22/2023 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Final | 2/2/2024 | Approved | JUSTIN HAWLEY |
| Final | 2/2/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 2/2/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 2/2/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 2/2/2024 | Approved | JUSTIN HAWLEY |