9108 S WADSWORTH AVE 90002
Certificate Information: 9108 S WADSWORTH AVE 90002
- Application / Permit
- 22010-20000-00665
- Plan Check / Job No.
- B22VN02186
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN* (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g)
- Permit Issued
- Issued on 7/14/2022
- Issuing Office
- Current Status
- CofO Issued on 1/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | LAMAR DAVIS |
| Corrections Issued | 3/7/2022 | LAMAR DAVIS |
| Quality Review Completed | 3/17/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 4/8/2022 | LAMAR DAVIS |
| Applicant returned to address corrections | 6/28/2022 | LAMAR DAVIS |
| Plan Check Approved | 7/1/2022 | LAMAR DAVIS |
| Issued | 7/14/2022 | APPLICANT |
| CofO in Progress | 1/19/2023 | LILIANA PORTILLO |
| CofO in Progress | 1/20/2023 | LILIANA PORTILLO |
| Permit Finaled | 1/25/2023 | DEROLD HAUFF |
| CofO Issued | 1/25/2023 | DEROLD HAUFF |
| Permit Finaled | 1/25/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/29/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 5/3/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 5/3/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 6/29/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 6/30/2022 | AMAAN MALIK |
Contact Information
| Contractor | Habitat For Humanity Of Greater Los Angeles; Lic. No.: 907613-B | 8739 ARTESIA BLVD BELLFLOWER, CA 90706 |
| Engineer | Dwelle,, Robert Kennedy; Lic. No.: C73395 | 1090 MOLINO AVE LONG BEACH, CA 90804 |
| Engineer | Ibrahim,, Mark Khalil; Lic. No.: S4223 | 3436 E LONGRIDGE DR ORANGE, CA 92867 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/12/2022 | Partial Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 8/19/2022 | Conditional Approval | LILIANA PORTILLO |
| Sewer | 8/19/2022 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 9/6/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 9/9/2022 | Approved | HORACE FULTZ |
| Deputy Reinf. Concrete | 9/12/2022 | Conditional Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 10/7/2022 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 10/11/2022 | Approved | LILIANA PORTILLO |
| Deputy Wood Construction | 10/12/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/12/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/13/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 10/13/2022 | Corrections Issued | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/13/2022 | Partial Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/17/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 10/17/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 10/17/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 10/17/2022 | Approved | LILIANA PORTILLO |
| Insulation | 10/19/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 10/21/2022 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 10/21/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 12/21/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/21/2022 | Corrections Issued | LILIANA PORTILLO |
| Final | 12/21/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 12/21/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 12/21/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 12/21/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 12/21/2022 | SGSOV Not Required | LILIANA PORTILLO |
| Service/Power Release | 12/21/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 12/21/2022 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 12/21/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 1/11/2023 | Approved | LILIANA PORTILLO |
| Final | 1/11/2023 | Conditional Approval | LILIANA PORTILLO |
| Green Building Final | 1/11/2023 | Approved | LILIANA PORTILLO |
| Service/Power Release | 1/11/2023 | Approved | LILIANA PORTILLO |
| Final | 1/19/2023 | OK to Issue CofO | LILIANA PORTILLO |