7511 N VASSAR AVE 91303
Certificate Information: 7511 N VASSAR AVE 91303
- Application / Permit
- 22010-20000-00664
- Plan Check / Job No.
- B22VN02185
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan new ADU. New 1-story detached Accessory dwelling Unit per LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 1/12/2023
- Issuing Office
- Current Status
- CofO Issued on 8/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | HERNAN ARREOLA |
| Corrections Issued | 2/17/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 10/31/2022 | HANS SANTIAGO |
| Plan Check Approved | 11/2/2022 | ANDREW SANTIAGO |
| Issued | 1/12/2023 | APPLICANT |
| CofO in Progress | 3/20/2024 | ALEXANDER HANDY |
| Permit Finaled | 8/26/2024 | JOHN JANSON |
| CofO Issued | 8/26/2024 | JOHN JANSON |
| Permit Finaled | 8/26/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2022 | DAGOVERTO GUERRERO |
| "Q" conditions | Cleared | 5/9/2022 | LAUREN PADICK |
| Low Impact Development | Cleared | 9/8/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/8/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 10/25/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Richard C C; Lic. No.: S1371 | 19321 VANOWEN ST RESEDA, CA 91335 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/10/2023 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 9/29/2023 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 9/29/2023 | Partial Approval | ALEXANDER HANDY |
| Excavation/Setback/Form/Re-Bar | 10/2/2023 | Approved | JEFFREY PARD |
| BUILDING-Rough-Frame | 10/26/2023 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 10/26/2023 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 10/26/2023 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 10/26/2023 | Approved | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 10/26/2023 | Approved | ALEXANDER HANDY |
| Insulation | 11/8/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 11/8/2023 | Partial Approval | ALEXANDER HANDY |
| Shower Pan | 11/8/2023 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 11/16/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 11/16/2023 | Approved | ALEXANDER HANDY |
| Sewer | 1/11/2024 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 1/11/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 3/19/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 3/19/2024 | Approved | ALEXANDER HANDY |
| Final | 3/19/2024 | OK to Issue CofO | ALEXANDER HANDY |
| Footing/Foundation/Slab | 3/19/2024 | Approved | ALEXANDER HANDY |
| HVAC-Final | 3/19/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 3/19/2024 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 3/19/2024 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 3/19/2024 | Approved | ALEXANDER HANDY |
| Smoke Detectors | 3/19/2024 | Approved | ALEXANDER HANDY |
| Special/Order Compliance | 5/23/2024 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Final | 6/11/2024 | Corrections Issued | ALEXANDER HANDY |
| Service/Power Release | 8/23/2024 | Approved | ALEXANDER HANDY |