10620 N AQUEDUCT AVE 91344
Certificate Information: 10620 N AQUEDUCT AVE 91344
- Application / Permit
- 22010-20000-00649
- Plan Check / Job No.
- B22VN02138
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2-STORY 1098 SQFT ADU W/ NEW 388 SQFT ATTACHED STORAGE PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 1/12/2024
- Issuing Office
- Current Status
- CofO Issued on 11/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | PETER MOSESIAN |
| Corrections Issued | 3/10/2022 | PETER MOSESIAN |
| Quality Review Completed | 3/14/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/15/2022 | APPLICANT |
| Plan Check Approved | 10/26/2023 | PETER MOSESIAN |
| No Progress | 10/26/2023 | PETER MOSESIAN |
| Plan Check Approved | 1/3/2024 | PETER MOSESIAN |
| Issued | 1/12/2024 | APPLICANT |
| CofO in Progress | 10/18/2024 | ROBERT GOLD |
| CofO in Progress | 10/18/2024 | ROBERT GOLD |
| CofO in Progress | 11/12/2024 | JAVIER RAMOS JR |
| Permit Finaled | 11/15/2024 | DANIEL ORRANTE |
| CofO Issued | 11/15/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/15/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/17/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/17/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/17/2022 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 4/25/2022 | CINDY JOSSELYN |
| Low Impact Development | Cleared | 6/9/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/19/2023 | NIKKI ZULUETA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/29/2024 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 3/11/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 3/11/2024 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2024 | Conditional Approval | JOHN COLEMAN |
| Underground Mechanical | 3/19/2024 | Partial Approval | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/4/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/11/2024 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 4/11/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 4/11/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/13/2024 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 4/13/2024 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 4/13/2024 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 4/13/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 4/13/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 4/13/2024 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 4/13/2024 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 4/15/2024 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 4/19/2024 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 4/19/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Drywall Nailing | 4/23/2024 | Approved | JAVIER RAMOS JR |
| Shower Pan | 5/7/2024 | Approved | ROBERT GOLD |
| ELECTRICAL-Final | 7/18/2024 | Approved | JAVIER RAMOS JR |
| Final | 7/18/2024 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 7/18/2024 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 7/18/2024 | Approved | JAVIER RAMOS JR |
| MERV13>=Final | 7/18/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 7/18/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/18/2024 | SGSOV Not Required | JAVIER RAMOS JR |
| Service/Power Release | 7/18/2024 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 7/18/2024 | Approved | JAVIER RAMOS JR |
| Final | 10/18/2024 | Conditional Approval | ROBERT GOLD |
| Final | 11/12/2024 | OK to Issue CofO | JAVIER RAMOS JR |