5269 N SHOSHONE AVE 91316

Certificate Information: 5269 N SHOSHONE AVE 91316

Application / Permit
22010-20000-00645
Plan Check / Job No.
B22VN02127
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33(c)-(d), (g)
Permit Issued
Issued on 5/9/2022
Issuing Office
Current Status
CofO Issued on 3/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 DANIEL YIP
Corrections Issued 3/1/2022 DANIEL YIP
Quality Review Completed 3/2/2022 KEN GILL
Building Plans Picked Up 3/4/2022 APPLICANT
Plan Check Approved 5/9/2022 DANIEL YIP
Issued 5/9/2022 APPLICANT
CofO in Progress 3/10/2023 SEAN HAUPT
CofO Issued 3/23/2023 JOHN JANSON
Permit Finaled 3/23/2023 JOHN JANSON

Permit Application Clearance Information

ZA Case Cleared 3/15/2022 LAUREN PADICK
Address approval Cleared 3/21/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/21/2022 CARLOS AGUILERA
Sewer availability Cleared 3/22/2022 CARLOS AGUILERA
Low Impact Development Cleared 4/15/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 4/18/2022 CARLOS AGUILERA
Miscellaneous Cleared 4/28/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Kazemi,, Milad; Lic. No.: C92143 21126 MERRIDY STREET      CHATSWORTH, CA 91311

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/5/2022 Approved SEAN HAUPT
Deputy Reinf. Concrete 7/13/2022 Partial Approval SEAN HAUPT
Excavation/Setback/Form/Re-Bar 7/13/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 7/13/2022 Approved SEAN HAUPT
Deputy Reinf. Concrete 7/14/2022 Partial Approval SEAN HAUPT
Deputy Drilled-In Anchors 7/19/2022 Partial Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 8/19/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 9/2/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 9/23/2022 Partial Approval SEAN HAUPT
ELECTRICAL-Rough 9/23/2022 Approved SEAN HAUPT
Shower Pan 9/28/2022 Approved KRISTEN CAUSEY
PLUMBING-Rough 10/5/2022 Approved SEAN HAUPT
HVAC-Rough 10/7/2022 Approved SEAN HAUPT
HVAC-Rough 10/14/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 10/14/2022 Approved SEAN HAUPT
BUILDING-Rough-Frame 10/20/2022 Not Ready for Inspection SEAN HAUPT
Green Building Rough 10/20/2022 Not Ready for Inspection SEAN HAUPT
Insulation 10/20/2022 Not Ready for Inspection SEAN HAUPT
Verify Sprinkler Sign Off 10/20/2022 Not Ready for Inspection SEAN HAUPT
Drywall Nailing 11/8/2022 No Access for Inspection DAVID SANDOVAL
Green Building Rough 11/8/2022 No Access for Inspection DAVID SANDOVAL
Drywall Nailing 11/18/2022 Approved SEAN HAUPT
Green Building Rough 11/18/2022 Approved SEAN HAUPT
Deck 12/22/2022 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 2/14/2023 Approved SEAN HAUPT
ELECTRICAL-Final 2/14/2023 Approved SEAN HAUPT
Final 2/14/2023 Corrections Issued SEAN HAUPT
Green Building Final 2/14/2023 Approved SEAN HAUPT
HVAC-Final 2/14/2023 Approved SEAN HAUPT
PLUMBING-Final 2/14/2023 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 2/14/2023 SGSOV Approved SEAN HAUPT
Service/Power Release 2/14/2023 Not Required SEAN HAUPT
Smoke Detectors 2/14/2023 Approved SEAN HAUPT
Verify Sprinkler Sign Off 2/14/2023 Approved SEAN HAUPT
Final 3/9/2023 OK to Issue CofO SEAN HAUPT