5522 E BUCHANAN ST 90042

Certificate Information: 5522 E BUCHANAN ST 90042

Application / Permit
22010-20000-00641
Plan Check / Job No.
B22VN02111
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 24' X 20' DETACHED ACCESSORY DWELLING UNIT (480 SQ FT) PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 3/31/2022
Issuing Office
Current Status
CofO Issued on 8/2/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2022 APPLICANT
Assigned to Plan Check Engineer 2/18/2022 JEROME MAGAT PALMA
Corrections Issued 2/19/2022 JEROME MAGAT PALMA
Plan Check Approved 3/31/2022 JEROME MAGAT PALMA
Issued 3/31/2022 APPLICANT
Building Plans Picked Up 4/1/2022 APPLICANT
CofO in Progress 7/28/2022 CRAIG VAUGHAN
CofO in Progress 7/28/2022 CRAIG VAUGHAN
Permit Finaled 8/2/2022 DEROLD HAUFF
CofO Issued 8/2/2022 DEROLD HAUFF
Permit Finaled 8/2/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 3/1/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 3/1/2022 CELINA MORENO
Sewer availability Cleared 3/11/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 3/25/2022 CELINA MORENO
Grading Pre-Inspection Cleared 3/29/2022 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/14/2022 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 4/14/2022 Approved CRAIG VAUGHAN
Gas Test 4/14/2022 Partial Approval CRAIG VAUGHAN
Sewer 4/14/2022 Approved CRAIG VAUGHAN
Underground Mechanical 4/14/2022 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 4/29/2022 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 4/29/2022 Approved KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 4/29/2022 Approved KATHRYN BUTTERWORTH
Green Building Rough 4/29/2022 Approved KATHRYN BUTTERWORTH
HVAC-Rough 4/29/2022 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 4/29/2022 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 4/29/2022 Approved KATHRYN BUTTERWORTH
Insulation 5/6/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/6/2022 Partial Approval HAMIK HARTOUNIAN
Drywall Nailing 5/10/2022 Approved CRAIG VAUGHAN
Shower Pan 5/10/2022 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 5/13/2022 Approved CRAIG VAUGHAN
Final 6/24/2022 Corrections Issued OSVALDO PARAMO
Green Building Final 6/24/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 6/24/2022 SGSOV Approved OSVALDO PARAMO
Service/Power Release 6/24/2022 Approved OSVALDO PARAMO
Smoke Detectors 6/24/2022 Approved OSVALDO PARAMO
Underground Mechanical 6/24/2022 Approved OSVALDO PARAMO
Final 7/5/2022 Corrections Issued HAMIK HARTOUNIAN
Gas Test 7/5/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 7/27/2022 Approved CRAIG VAUGHAN
Final 7/27/2022 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 7/27/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 7/27/2022 Approved CRAIG VAUGHAN