13115 W OTSEGO ST 91423
Certificate Information: 13115 W OTSEGO ST 91423
- Application / Permit
- 22010-20000-00628
- Plan Check / Job No.
- B22VN02081
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 6/17/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | ERIC WONG |
| Corrections Issued | 2/26/2022 | ERIC WONG |
| Quality Review Completed | 3/8/2022 | KEN GILL |
| Applicant returned to address corrections | 5/18/2022 | ERIC WONG |
| Plan Check Approved | 6/17/2022 | ERIC WONG |
| Issued | 6/17/2022 | APPLICANT |
| CofO in Progress | 5/22/2023 | KIRK SANDERS |
| CofO Issued | 8/28/2023 | RUBEN SALAS |
| Permit Finaled | 8/28/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/14/2022 | WALTER RAMIREZ |
| Address approval | Cleared | 3/15/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/15/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/16/2022 | CINDY JOSSELYN |
| Low Impact Development | Cleared | 5/6/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 5/6/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/29/2022 | Approved | RAFAEL CORTES |
| Footing/Foundation/Slab | 7/29/2022 | Approved | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 8/3/2022 | Approved | RAFAEL CORTES |
| PLUMBING-Rough | 8/3/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Underground Mechanical | 8/3/2022 | Approved | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2022 | Corrections Issued | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2022 | Partial Approval | RAFAEL CORTES |
| PLUMBING-Rough | 10/4/2022 | Corrections Issued | RAFAEL CORTES |
| Shower Pan | 10/4/2022 | Corrections Issued | RAFAEL CORTES |
| PLUMBING-Rough | 10/5/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Shower Pan | 10/5/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Final | 10/11/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Rough | 10/11/2022 | Partial Approval | RAFAEL CORTES |
| Shower Pan | 10/11/2022 | Approved | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Approved | CALEB MEISTER |
| PLUMBING-Rough | 10/18/2022 | Approved | CALEB MEISTER |
| HVAC-Rough | 11/3/2022 | Corrections Issued | WILLIAM WREN |
| Insulation | 11/3/2022 | Partial Approval | WILLIAM WREN |
| HVAC-Rough | 11/10/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 11/10/2022 | Partial Approval | CALEB MEISTER |
| ELECTRICAL-Rough | 11/14/2022 | Approved | CALEB MEISTER |
| Wood Frame | 11/17/2022 | Corrections Issued | CALEB MEISTER |
| Insulation | 11/29/2022 | Not Ready for Inspection | KIRK SANDERS |
| Interior/Exterior Lathing | 11/29/2022 | Approved | KIRK SANDERS |
| Wood Frame | 11/29/2022 | Approved | KIRK SANDERS |
| Insulation | 12/13/2022 | Corrections Issued | KIRK SANDERS |
| Drywall Nailing | 12/23/2022 | Approved | KIRK SANDERS |
| Drywall Nailing | 12/27/2022 | Approved | KIRK SANDERS |
| Gas Test | 2/27/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Gas Test | 4/4/2023 | Approved | MISAEL ESPARZA |
| Gas Test | 4/6/2023 | Approved | JOHN COLEMAN |
| ELECTRICAL-Final | 4/26/2023 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 4/26/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 4/26/2023 | Not Ready for Inspection | KIRK SANDERS |
| Service/Power Release | 4/26/2023 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 4/26/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/10/2023 | Conditional Approval | KIRK SANDERS |
| ELECTRICAL-Final | 5/10/2023 | Approved | KIRK SANDERS |
| Final | 5/10/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 5/10/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 5/10/2023 | Approved | KIRK SANDERS |
| HVAC-Final | 5/10/2023 | Approved | KIRK SANDERS |
| PLUMBING-Final | 5/10/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/10/2023 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 5/10/2023 | Not Ready for Inspection | KIRK SANDERS |
| Verify Sprinkler Sign Off | 5/10/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/19/2023 | Approved | KIRK SANDERS |
| Final | 5/19/2023 | OK to Issue CofO | KIRK SANDERS |
| Service/Power Release | 5/19/2023 | Approved | KIRK SANDERS |