11213 N LOUISE AVE 91344

Certificate Information: 11213 N LOUISE AVE 91344

Application / Permit
22010-20000-00623
Plan Check / Job No.
B22VN02072
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 26'-2" X 70'-3" IRREG SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) WITH ATTACHED 2-CAR GARAGE AND 8'-3" X 21' TRELLIS. ALL WORK DONE PER ENGINEERING. SEE COMMENTS
Permit Issued
Issued on 8/26/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/10/2022 APPLICANT
Assigned to Plan Check Engineer 2/18/2022 GURUNATH NESARAJAH
Corrections Issued 3/29/2022 GURUNATH NESARAJAH
Applicant returned to address corrections 6/30/2022 GURUNATH NESARAJAH
Building Plans Picked Up 6/30/2022 APPLICANT
Applicant returned to address corrections 8/12/2022 HAYATO TSUCHIYA
Plan Check Approved 8/25/2022 JEROME MAGAT PALMA
Issued 8/26/2022 APPLICANT
CofO in Progress 8/18/2023 STEVEN BACK
CofO in Progress 8/21/2023 STEVEN BACK
CofO in Progress 8/31/2023 STEVEN BACK
CofO Issued 9/1/2023 JOHN JANSON
Permit Finaled 9/1/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/25/2022 CARLOS AGUILERA
Sewer availability Cleared 2/25/2022 CARLOS AGUILERA
ZI Cleared 3/18/2022 PABLO ESTRADA
Eng Process Fee Ord 176,300 Cleared 3/21/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 3/30/2022 CINDY JOSSELYN
Construction near power lines Cleared 4/15/2022 RIDWAN HARDY
Grading Pre-Inspection Cleared 5/11/2022 KIRK LINKLATER
Low Impact Development Cleared 5/26/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 6/2/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 6/2/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 6/2/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 6/2/2022 MEGAN GODINEZ
GPI Written Notices Cleared 8/12/2022 GURUNATH NESARAJAH

Contact Information

Contractor Owner-Builder       ,
Engineer Grigoryan,, Souren; Lic. No.: C93320 6506 TEESDALE AVE      NORTH HOLLYWOOD, CA 91606

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/19/2022 Partial Approval DAVID SCANTLIN
Underground Mechanical 9/19/2022 Approved DAVID SCANTLIN
Deputy Reinf. Concrete 9/21/2022 Conditional Approval DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 9/23/2022 Approved DAVID SCANTLIN
Footing/Foundation/Slab 9/23/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 11/1/2022 Approved JEFFREY PARD
HVAC-Rough 11/1/2022 Approved JEFFREY PARD
PLUMBING-Rough 11/1/2022 Approved JEFFREY PARD
Wood Frame 11/1/2022 Approved JEFFREY PARD
ELECTRICAL-Rough 11/7/2022 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 11/7/2022 Approved JEFFREY PARD
Interior/Exterior Lathing 11/7/2022 Approved JEFFREY PARD
BUILDING-Rough-Frame 12/19/2022 Approved STEVEN BACK
Green Building Rough 12/19/2022 Approved STEVEN BACK
Insulation 12/19/2022 Corrections Issued STEVEN BACK
Interior/Exterior Lathing 12/19/2022 Not Ready for Inspection STEVEN BACK
Drywall Nailing 1/4/2023 Approved STEVEN BACK
Insulation 1/4/2023 Approved STEVEN BACK
Shower Pan 1/4/2023 Approved STEVEN BACK
Gas Test 5/22/2023 Approved STEVEN BACK
Final 6/2/2023 No Access for Inspection DAVID SCANTLIN
Green Building Final 6/2/2023 No Access for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 6/2/2023 SGSOV Not Ready DAVID SCANTLIN
Service/Power Release 6/2/2023 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 6/2/2023 No Access for Inspection DAVID SCANTLIN
Final 6/7/2023 Corrections Issued JEFFREY PARD
Green Building Final 6/7/2023 Corrections Issued JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 6/7/2023 SGSOV Not Ready JEFFREY PARD
Smoke Detectors 6/7/2023 Approved JEFFREY PARD
Final 6/13/2023 Corrections Issued STEVEN BACK
Green Building Final 6/13/2023 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/13/2023 SGSOV Not Ready STEVEN BACK
Special/Order Compliance 6/29/2023 Corrections Issued STEVEN BACK
Final 8/18/2023 Corrections Issued STEVEN BACK
Green Building Final 8/18/2023 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 8/18/2023 SGSOV Approved STEVEN BACK
Service/Power Release 8/18/2023 Approved STEVEN BACK
Final 8/21/2023 Corrections Issued STEVEN BACK
Final 8/31/2023 OK to Issue CofO STEVEN BACK