Pre-Inspection
|
8/23/2023
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
10/25/2024
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
10/30/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
11/1/2024
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
11/12/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
11/18/2024
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
11/19/2024
|
Approved
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
11/19/2024
|
Partial Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
11/20/2024
|
Approved
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
11/25/2024
|
Approved
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
11/25/2024
|
Partial Approval
|
JOHN KITCKO
|
|
Reinforced Concrete Frame
|
11/25/2024
|
Partial Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
11/25/2024
|
Partial Inspection
|
BRIAN KELLY
|
|
Footing/Foundation/Slab
|
12/16/2024
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
12/20/2024
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
12/23/2024
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
1/2/2025
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
1/2/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
1/3/2025
|
Approved
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
1/6/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
1/7/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
1/9/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
1/10/2025
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
1/16/2025
|
Approved
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
1/16/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
1/21/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Reinforced Concrete Frame
|
1/27/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
1/29/2025
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
1/30/2025
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
1/31/2025
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
2/4/2025
|
Approved
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
2/4/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
2/4/2025
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
2/5/2025
|
No Access for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
2/6/2025
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
2/10/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
2/12/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
2/21/2025
|
Approved
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
2/21/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
2/26/2025
|
Approved
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
2/26/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
2/27/2025
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
2/28/2025
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
3/18/2025
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
3/18/2025
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
3/19/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
3/21/2025
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
4/18/2025
|
Approved
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
4/18/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
4/24/2025
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
4/24/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
4/25/2025
|
Conditional Approval
|
JOHN KITCKO
|
|
Reinforced Concrete Frame
|
4/29/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
5/2/2025
|
Approved
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
5/5/2025
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Reinforced Concrete Frame
|
5/7/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
5/8/2025
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Steel/Welding
|
5/15/2025
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
5/16/2025
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Steel/Welding
|
5/16/2025
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Deputy Steel/Welding
|
5/19/2025
|
Conditional Approval
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
5/19/2025
|
Partial Approval
|
DANNY RODRIGUEZ
|
|
Deputy Reinf. Concrete
|
5/20/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Steel/Welding
|
5/21/2025
|
Approved
|
DANNY RODRIGUEZ
|
|
Footing/Foundation/Slab
|
5/22/2025
|
Partial Approval
|
ROBERT DAVIS
|
|
Special/Order Compliance
|
5/22/2025
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Deputy Reinf. Concrete
|
5/23/2025
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
5/23/2025
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
5/27/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
5/27/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
5/28/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
5/29/2025
|
Approved
|
JOHN KITCKO
|
|
Deputy Steel/Welding
|
5/29/2025
|
Approved
|
JOHN KITCKO
|
|
Deputy Steel/Welding
|
5/30/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
6/2/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
6/2/2025
|
No Access for Inspection
|
GREGORY POMISH
|
|
Deputy Steel/Welding
|
6/3/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
6/5/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Steel/Welding
|
6/5/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Footing/Foundation/Slab
|
6/6/2025
|
Partial Inspection
|
ANDREW DORSO
|
|
Deputy Reinf. Concrete
|
6/11/2025
|
Approved
|
JOHN KITCKO
|
|
Deputy Steel/Welding
|
6/17/2025
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
6/20/2025
|
Approved
|
JOHN KITCKO
|
|
Deputy Steel/Welding
|
6/20/2025
|
Approved
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
6/20/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Excavation/Setback/Form/Re-Bar
|
6/23/2025
|
Partial Approval
|
JOHN KITCKO
|
|
Deputy Reinf. Concrete
|
6/24/2025
|
Approved
|
JOHN KITCKO
|
|
Deputy Steel/Welding
|
6/24/2025
|
Approved
|
JOHN KITCKO
|
|
Special/Order Compliance
|
6/24/2025
|
Partial Inspection
|
JOHN KITCKO
|
|
Deputy Steel/Welding
|
6/26/2025
|
Approved
|
JOHN KITCKO
|
|
Deputy Wood Construction
|
6/26/2025
|
Approved
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/26/2025
|
Partial Inspection
|
JOHN KITCKO
|
|
Deputy Steel/Welding
|
6/30/2025
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Steel/Welding
|
7/2/2025
|
Approved
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/2/2025
|
Partial Inspection
|
JOHN KITCKO
|
|
Deputy Steel/Welding
|
7/3/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
7/10/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Steel/Welding
|
7/14/2025
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Drilled-In Anchors
|
7/15/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
7/16/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
7/17/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Deputy Steel/Welding
|
7/17/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Special/Order Compliance
|
7/17/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/21/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Special/Order Compliance
|
7/21/2025
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Special/Order Compliance
|
7/21/2025
|
Partial Inspection
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
7/22/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Special/Order Compliance
|
7/22/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Special/Order Compliance
|
7/22/2025
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Deputy Steel/Welding
|
7/28/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Pre-Inspection
|
7/28/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Deputy Reinf. Concrete
|
7/29/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Special/Order Compliance
|
7/29/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Special/Order Compliance
|
7/29/2025
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Footing/Foundation/Slab
|
7/30/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
7/31/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Special/Order Compliance
|
7/31/2025
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Footing/Foundation/Slab
|
8/5/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Special/Order Compliance
|
8/5/2025
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Special/Order Compliance
|
8/5/2025
|
Partial Inspection
|
GREGORY POMISH
|
|
Special/Order Compliance
|
8/7/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Drilled-In Anchors
|
8/8/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Deputy Reinf. Concrete
|
8/12/2025
|
Conditional Approval
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
8/12/2025
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Deputy Drilled-In Anchors
|
8/13/2025
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Reinf. Concrete
|
8/14/2025
|
Conditional Approval
|
DEANDRE HOFFMAN
|
|
Footing/Foundation/Slab
|
8/14/2025
|
Partial Inspection
|
ROBERT DAVIS
|
|
Special/Order Compliance
|
8/14/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Deputy Reinf. Concrete
|
8/15/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
8/20/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
8/25/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
9/25/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
9/25/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Other (see comments)
|
10/14/2025
|
Conditional Approval
|
DEANDRE HOFFMAN
|
|
Deputy Reinf. Concrete
|
10/14/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
10/15/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Special/Order Compliance
|
10/16/2025
|
Partial Inspection
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
10/23/2025
|
Conditional Approval
|
JEFFREY DURAN
|
|
Footing/Foundation/Slab
|
10/23/2025
|
Partial Inspection
|
ANDREW DORSO
|
|
Drywall Nailing
|
10/29/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
10/30/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
11/4/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Footing/Foundation/Slab
|
11/5/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Deputy Reinf. Concrete
|
12/3/2025
|
Conditional Approval
|
GREGORY POMISH
|
|
Special/Order Compliance
|
12/8/2025
|
Partial Approval
|
SCOTT SOBEL
|
|
Special/Order Compliance
|
12/8/2025
|
Partial Inspection
|
GREGORY POMISH
|
|
Structural Steel Frame
|
2/17/2026
|
No Access for Inspection
|
JOHN KITCKO
|
|
Pre-Inspection
|
3/2/2026
|
Partial Inspection
|
BRIAN KELLY
|
|
Special/Order Compliance
|
3/2/2026
|
Partial Approval
|
JOHN KITCKO
|
|
Piling/Pier/Caisson
|
3/3/2026
|
Corrections Issued
|
JOHN KITCKO
|
|
Special/Order Compliance
|
3/3/2026
|
Partial Inspection
|
BRIAN KELLY
|
|
Structural Steel Frame
|
3/3/2026
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Piling/Pier/Caisson
|
3/5/2026
|
Partial Approval
|
JOHN KITCKO
|
|
Structural Steel Frame
|
3/5/2026
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Piling/Pier/Caisson
|
3/6/2026
|
No Access for Inspection
|
JOHN KITCKO
|
|
Special/Order Compliance
|
3/6/2026
|
Partial Inspection
|
BRIAN KELLY
|
|
Structural Steel Frame
|
3/6/2026
|
No Access for Inspection
|
JOHN KITCKO
|
|
Deputy Wood Construction
|
3/10/2026
|
Approved
|
JOHN KITCKO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/12/2026
|
Conditional Approval
|
JOHN KITCKO
|
|
Special/Order Compliance
|
3/12/2026
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Piling/Pier/Caisson
|
3/16/2026
|
No Access for Inspection
|
JOHN KITCKO
|
|
Reinforced Concrete Frame
|
3/16/2026
|
No Access for Inspection
|
JOHN KITCKO
|
|
Piling/Pier/Caisson
|
3/18/2026
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Piling/Pier/Caisson
|
3/26/2026
|
Partial Approval
|
JOHN KITCKO
|
|
Pre-Inspection
|
3/26/2026
|
Partial Inspection
|
DEANDRE HOFFMAN
|
|
Special/Order Compliance
|
3/26/2026
|
Partial Inspection
|
BRIAN KELLY
|
|
Final
|
4/21/2026
|
Partial Inspection
|
JOHN KITCKO
|
|
Footing/Foundation/Slab
|
4/21/2026
|
Approved
|
JOHN KITCKO
|
|
Green Building Final
|
4/21/2026
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Green Building Rough
|
4/21/2026
|
Approved
|
JOHN KITCKO
|
|
Reinforced Masonry Frame
|
4/21/2026
|
Approved
|
JOHN KITCKO
|
|
SGSOV-Seismic Gas S/O Valve
|
4/21/2026
|
SGSOV Not Ready
|
JOHN KITCKO
|
|
Smoke Detectors
|
4/21/2026
|
Not Ready for Inspection
|
JOHN KITCKO
|
|
Verify Sprinkler Sign Off
|
4/21/2026
|
Approved
|
JOHN KITCKO
|