333 N ALFRED ST 90048

Certificate Information: 333 N ALFRED ST 90048

Application / Permit
22010-20000-00594
Plan Check / Job No.
B22VN02014
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 3-STORY SINGLE FAMILY DWELLING WITH 2-CAR ATTACHED GARAGE
Permit Issued
Issued on 10/18/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 PRANITA SHAH
Corrections Issued 3/1/2022 PRANITA SHAH
Quality Review Completed 3/8/2022 KEN GILL
Applicant returned to address corrections 8/10/2022 PRANITA SHAH
Applicant returned to address corrections 8/22/2022 PRANITA SHAH
Applicant returned to address corrections 8/30/2022 PRANITA SHAH
Plan Check Approved 10/17/2022 PRANITA SHAH
Issued 10/18/2022 APPLICANT
CofO in Progress 9/8/2023 ROBERT CHAVEZ
CofO in Progress 9/8/2023 ROBERT CHAVEZ
Permit Finaled 9/18/2023 DANIEL SANCHEZ
CofO Issued 9/18/2023 DANIEL SANCHEZ
Permit Finaled 9/18/2023 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 3/24/2022 JEANIE LAM
Permit Cleared 3/24/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/25/2022 JEANIE LAM
Sewer availability Cleared 3/25/2022 JEANIE LAM
Trees in Parkway Cleared 4/8/2022 ADALBERTO VERA
Low Impact Development Cleared 5/6/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 5/11/2022 JEANIE LAM
Hydrant and Access approval Cleared 5/28/2022 GILBERT URREA

Contact Information

Architect Gemigniani,, Richard Louis; Lic. No.: C18783 4069 WOODCLIFF RD      SHERMAN OAKS, CA 91403
Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/20/2022 Partial Inspection MICHAEL LEWIS
METHANE-Barrier 10/20/2022 Partial Inspection MICHAEL LEWIS
METHANE-Subgrade 10/20/2022 Partial Inspection MICHAEL LEWIS
Underground Mechanical 10/20/2022 Partial Inspection MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 10/21/2022 Corrections Issued JOHN TCHANG
Footing/Foundation/Slab 10/26/2022 Not Ready for Inspection JOHN TCHANG
METHANE-Barrier 10/26/2022 Not Ready for Inspection JOHN TCHANG
METHANE-Subgrade 10/26/2022 Not Ready for Inspection JOHN TCHANG
Excavation/Setback/Form/Re-Bar 10/31/2022 Partial Approval JOHN TCHANG
Deputy Reinf. Concrete 11/1/2022 Conditional Approval JOEL WILLIAMS
METHANE-Rough 11/4/2022 Not Ready for Inspection JOHN TCHANG
METHANE-Barrier 11/9/2022 Not Ready for Inspection JOHN TCHANG
METHANE-Rough 11/9/2022 Partial Approval JOHN TCHANG
Footing/Foundation/Slab 11/14/2022 Approved JOHN TCHANG
METHANE-Barrier 11/14/2022 Approved JOHN TCHANG
METHANE-Final 11/14/2022 Not Ready for Inspection JOHN TCHANG
METHANE-Subgrade 11/14/2022 Approved JOHN TCHANG
Pre-Inspection 11/14/2022 Not Ready for Inspection JOHN TCHANG
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Partial Approval JOHN TCHANG
Floor/Roof Diaphrgm/Shear Wall 12/19/2022 Partial Approval HAGOP BADOSSIAN
Floor/Roof Diaphrgm/Shear Wall 12/27/2022 Partial Approval ROBERT CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 1/6/2023 Approved JOHN TCHANG
PLUMBING-Rough 1/13/2023 Not Ready for Inspection JOHN TCHANG
Sewer 1/13/2023 Approved COREY HUPP
METHANE-Rough 1/17/2023 Not Ready for Inspection JOHN TCHANG
PLUMBING-Rough 1/17/2023 Corrections Issued JOHN TCHANG
BUILDING-Rough-Frame 1/25/2023 Not Ready for Inspection JOHN TCHANG
Green Building Rough 1/25/2023 Not Ready for Inspection JOHN TCHANG
PLUMBING-Rough 1/25/2023 Approved JOHN TCHANG
Verify Sprinkler Sign Off 1/25/2023 Not Ready for Inspection JOHN TCHANG
Wood Frame 1/25/2023 Not Ready for Inspection JOHN TCHANG
ELECTRICAL-Rough 2/2/2023 Approved JOHN TCHANG
HVAC-Rough 2/2/2023 Partial Approval JOHN TCHANG
BUILDING-Rough-Frame 2/7/2023 Corrections Issued JOHN TCHANG
Green Building Rough 2/7/2023 Not Ready for Inspection JOHN TCHANG
METHANE-Rough 2/7/2023 Not Ready for Inspection JOHN TCHANG
Verify Sprinkler Sign Off 2/7/2023 Not Ready for Inspection JOHN TCHANG
HVAC-Rough 2/15/2023 Approved JOHN TCHANG
PLUMBING-Rough 2/15/2023 Not Ready for Inspection JOHN TCHANG
Shower Pan 2/15/2023 Not Ready for Inspection JOHN TCHANG
Wood Frame 2/15/2023 Corrections Issued JOHN TCHANG
BUILDING-Rough-Frame 2/22/2023 Corrections Issued JOHN TCHANG
Deputy Steel/Welding 2/23/2023 Conditional Approval ROBERT CHAVEZ
Insulation 3/16/2023 Approved ROBERT CHAVEZ
Shower Pan 3/16/2023 Not Ready for Inspection ROBERT CHAVEZ
Drywall Nailing 3/22/2023 Approved ROBERT CHAVEZ
Green Building Rough 3/22/2023 Approved ROBERT CHAVEZ
Interior/Exterior Lathing 3/22/2023 Partial Approval ROBERT CHAVEZ
Interior/Exterior Lathing 3/30/2023 Approved ROBERT CHAVEZ
Enclosure/Fence 6/8/2023 Not Ready for Inspection RUBEN PEREZ
ELECTRICAL-Final 6/16/2023 Approved ROBERT CHAVEZ
HVAC-Final 6/16/2023 Not Ready for Inspection ROBERT CHAVEZ
HVAC-Final 6/21/2023 Not Ready for Inspection ROBERT CHAVEZ
PLUMBING-Final 6/21/2023 Corrections Issued ROBERT CHAVEZ
ELECTRICAL-Final 7/6/2023 Corrections Issued ROBERT CHAVEZ
Green Building Final 7/6/2023 Corrections Issued ROBERT CHAVEZ
HVAC-Final 7/6/2023 Corrections Issued ROBERT CHAVEZ
PLUMBING-Final 7/6/2023 Approved ROBERT CHAVEZ
BUILDING-Rough-Frame 7/18/2023 Approved ROBERT CHAVEZ
Final 7/18/2023 OK to Issue CofO ROBERT CHAVEZ
Green Building Final 7/18/2023 Approved ROBERT CHAVEZ
METHANE-Final 7/18/2023 Approved ROBERT CHAVEZ
METHANE-Rough 7/18/2023 Approved ROBERT CHAVEZ
SGSOV-Seismic Gas S/O Valve 7/18/2023 SGSOV Approved ROBERT CHAVEZ
Service/Power Release 7/18/2023 Approved ROBERT CHAVEZ
Smoke Detectors 7/18/2023 Approved ROBERT CHAVEZ
Verify Sprinkler Sign Off 7/18/2023 Approved ROBERT CHAVEZ