12951 W AETNA ST 91401
Certificate Information: 12951 W AETNA ST 91401
- Application / Permit
- 22010-20000-00592
- Plan Check / Job No.
- B22VN01996
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2-STORY DETACHED ADU (40'-0"x23'-9"), 1157 SQFT W/DECK ABOVE PER LAMC 12.22 A.33(c)(d) The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 10/3/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | PETER MOSESIAN |
| Corrections Issued | 3/8/2022 | PETER MOSESIAN |
| Quality Review Completed | 3/14/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/14/2022 | APPLICANT |
| Plan Check Approved | 10/3/2022 | PETER MOSESIAN |
| Issued | 10/3/2022 | APPLICANT |
| CofO in Progress | 10/7/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 10/18/2024 | DANIEL ORRANTE |
| CofO Issued | 10/18/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/18/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 3/15/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/15/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 3/24/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 4/11/2022 | LAURINDA MEADE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/7/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Pre-Inspection | 3/13/2023 | Corrections Issued | KIRK SANDERS |
| Excavation/Setback/Form/Re-Bar | 6/16/2023 | Partial Approval | KIRK SANDERS |
| PLUMBING-Rough | 6/21/2023 | Partial Approval | JUAN VALENZUELA |
| Sewer | 6/21/2023 | Approved | JUAN VALENZUELA |
| Underground Mechanical | 6/21/2023 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/3/2023 | Approved | KIRK SANDERS |
| Grounding or Bonding | 7/3/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2023 | Partial Approval | KIRK SANDERS |
| Green Building Rough | 7/24/2023 | Not Ready for Inspection | KIRK SANDERS |
| Verify Sprinkler Sign Off | 7/24/2023 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/17/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 10/17/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 10/17/2023 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 10/17/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 10/26/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 10/26/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Rough | 10/26/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Rough | 10/26/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/26/2023 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 10/26/2023 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/30/2023 | Conditional Approval | KIRK SANDERS |
| Green Building Rough | 11/30/2023 | Approved | KIRK SANDERS |
| Shower Pan | 11/30/2023 | Approved | KIRK SANDERS |
| Verify Sprinkler Sign Off | 11/30/2023 | Approved | KIRK SANDERS |
| Insulation | 12/6/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Drywall Nailing | 12/8/2023 | Approved | JUAN VALENZUELA |
| Insulation | 12/8/2023 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 1/9/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 9/6/2024 | No Access for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/4/2024 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 10/4/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 10/4/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 10/4/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 10/4/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 10/4/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/4/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 10/4/2024 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 10/4/2024 | Approved | OGANES TARAKHCHYAN |