1103 W 29TH ST 90007

Certificate Information: 1103 W 29TH ST 90007

Application / Permit
22010-20000-00580
Plan Check / Job No.
B22VN01949
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan PROPOSED DETACHED ADU PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g). ATTACHED GARAGE ON 1ST STORY. The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 1/18/2023
Issuing Office
Current Status
CofO Issued on 4/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/8/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 MARCELA FRANQUEZ
Corrections Issued 3/4/2022 MICHAEL LOPEZ
Quality Review Completed 3/7/2022 HERNAN ARREOLA
Applicant returned to address corrections 7/26/2022 MICHAEL LOPEZ
Applicant returned to address corrections 9/22/2022 MICHAEL LOPEZ
Applicant returned to address corrections 11/4/2022 MARCELA FRANQUEZ
Applicant returned to address corrections 12/7/2022 MARCELA FRANQUEZ
Applicant returned to address corrections 12/16/2022 MARCELA FRANQUEZ
Plan Check Approved 1/18/2023 MARCELA FRANQUEZ
Issued 1/18/2023 APPLICANT
CofO in Progress 2/13/2024 ARTHUR NEGRETE
Permit Finaled 4/2/2024 DEROLD HAUFF
CofO Issued 4/2/2024 DEROLD HAUFF
Permit Finaled 4/2/2024 DEROLD HAUFF

Permit Application Clearance Information

Miscellaneous Cleared 3/8/2022 DANIEL MATA
Miscellaneous Cleared 3/8/2022 DANIEL MATA
Miscellaneous Cleared 3/8/2022 DANIEL MATA
Specific Plan Cleared 3/8/2022 DANIEL MATA
Address approval Cleared 3/9/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/10/2022 WALLIE JONG
Sewer availability Cleared 3/10/2022 WALLIE JONG
ZA Case Cleared 3/25/2022 MAXFIELD VERMY
ZA Case Cleared 3/25/2022 MAXFIELD VERMY
Hydrant and Access approval Cleared 3/28/2022 LAURINDA MEADE
Frnt yard landscape/Water mgmt Cleared 4/28/2022 MAXFIELD VERMY
Highway dedication Cleared 6/30/2022 THAN WIN
Roof/Waste drainage to street Cleared 7/11/2022 WALLIE JONG

Contact Information

Architect Zbikowski,, Jeffrey; Lic. No.: C35389 4043 IRVING PL SUITE B      CULVER CITY, CA 90232
Contractor Owner-Builder       ,
Engineer Lotfi,, Fariborz Frank; Lic. No.: C49359 1328 DUENDE LANE      PACIFIC PALISADES, CA 90272

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/2/2023 Partial Approval JOSE AVILA
METHANE-Barrier 5/2/2023 Partial Approval JOSE AVILA
METHANE-Subgrade 5/2/2023 Approved JOSE AVILA
Sewer 5/2/2023 Partial Approval JOSE AVILA
Deputy Reinf. Concrete 5/5/2023 Conditional Approval KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 5/5/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 5/5/2023 Partial Approval KATHRYN BUTTERWORTH
Deputy Reinf. Concrete 5/9/2023 Conditional Approval KATHRYN BUTTERWORTH
Deputy Steel/Welding 5/9/2023 Conditional Approval KATHRYN BUTTERWORTH
Footing/Foundation/Slab 5/10/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Barrier 5/10/2023 Approved KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 5/11/2023 Conditional Approval SCOTT FINNILA
Deputy Reinf. Concrete 5/12/2023 Conditional Approval FREDDIE RIVERA
Deputy Steel/Welding 5/12/2023 Conditional Approval FREDDIE RIVERA
Deputy Steel/Welding 5/25/2023 Conditional Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/31/2023 Partial Approval SCOTT FINNILA
Deputy Wood Construction 6/28/2023 Conditional Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 7/5/2023 Corrections Issued LILIANA PORTILLO
HVAC-Rough 7/5/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 7/5/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 7/21/2023 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 7/21/2023 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 7/21/2023 Approved KATHRYN BUTTERWORTH
METHANE-Rough 7/21/2023 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 7/21/2023 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 8/9/2023 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Rough 8/9/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 8/9/2023 Partial Approval KATHRYN BUTTERWORTH
Insulation 8/14/2023 Corrections Issued KATHRYN BUTTERWORTH
Drywall Nailing 8/21/2023 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 8/21/2023 Partial Approval KATHRYN BUTTERWORTH
Gas Test 10/3/2023 Partial Approval KATHRYN BUTTERWORTH
Sewer 10/3/2023 Corrections Issued KATHRYN BUTTERWORTH
Underground Mechanical 10/3/2023 Partial Approval KATHRYN BUTTERWORTH
Insulation 10/24/2023 Approved KATHRYN BUTTERWORTH
Sewer 10/24/2023 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 11/15/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Final 11/15/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Final 11/15/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Final 2/12/2024 Approved ARTHUR NEGRETE
Final 2/12/2024 OK to Issue CofO ARTHUR NEGRETE
Footing/Foundation/Slab 2/12/2024 Approved ARTHUR NEGRETE
Green Building Final 2/12/2024 Approved ARTHUR NEGRETE
HVAC-Final 2/12/2024 Approved ARTHUR NEGRETE
PLUMBING-Final 2/12/2024 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 2/12/2024 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 2/12/2024 Approved ARTHUR NEGRETE
Smoke Detectors 2/12/2024 Approved ARTHUR NEGRETE