1103 W 29TH ST 90007
Certificate Information: 1103 W 29TH ST 90007
- Application / Permit
- 22010-20000-00580
- Plan Check / Job No.
- B22VN01949
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan PROPOSED DETACHED ADU PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g). ATTACHED GARAGE ON 1ST STORY. The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
- Permit Issued
- Issued on 1/18/2023
- Issuing Office
- Current Status
- CofO Issued on 4/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | MARCELA FRANQUEZ |
| Corrections Issued | 3/4/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 3/7/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 7/26/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 9/22/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 11/4/2022 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 12/7/2022 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 12/16/2022 | MARCELA FRANQUEZ |
| Plan Check Approved | 1/18/2023 | MARCELA FRANQUEZ |
| Issued | 1/18/2023 | APPLICANT |
| CofO in Progress | 2/13/2024 | ARTHUR NEGRETE |
| Permit Finaled | 4/2/2024 | DEROLD HAUFF |
| CofO Issued | 4/2/2024 | DEROLD HAUFF |
| Permit Finaled | 4/2/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Miscellaneous | Cleared | 3/8/2022 | DANIEL MATA |
| Miscellaneous | Cleared | 3/8/2022 | DANIEL MATA |
| Miscellaneous | Cleared | 3/8/2022 | DANIEL MATA |
| Specific Plan | Cleared | 3/8/2022 | DANIEL MATA |
| Address approval | Cleared | 3/9/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2022 | WALLIE JONG |
| Sewer availability | Cleared | 3/10/2022 | WALLIE JONG |
| ZA Case | Cleared | 3/25/2022 | MAXFIELD VERMY |
| ZA Case | Cleared | 3/25/2022 | MAXFIELD VERMY |
| Hydrant and Access approval | Cleared | 3/28/2022 | LAURINDA MEADE |
| Frnt yard landscape/Water mgmt | Cleared | 4/28/2022 | MAXFIELD VERMY |
| Highway dedication | Cleared | 6/30/2022 | THAN WIN |
| Roof/Waste drainage to street | Cleared | 7/11/2022 | WALLIE JONG |
Contact Information
| Architect | Zbikowski,, Jeffrey; Lic. No.: C35389 | 4043 IRVING PL SUITE B CULVER CITY, CA 90232 |
| Contractor | Owner-Builder | , |
| Engineer | Lotfi,, Fariborz Frank; Lic. No.: C49359 | 1328 DUENDE LANE PACIFIC PALISADES, CA 90272 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/2/2023 | Partial Approval | JOSE AVILA |
| METHANE-Barrier | 5/2/2023 | Partial Approval | JOSE AVILA |
| METHANE-Subgrade | 5/2/2023 | Approved | JOSE AVILA |
| Sewer | 5/2/2023 | Partial Approval | JOSE AVILA |
| Deputy Reinf. Concrete | 5/5/2023 | Conditional Approval | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 5/5/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 5/5/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Deputy Reinf. Concrete | 5/9/2023 | Conditional Approval | KATHRYN BUTTERWORTH |
| Deputy Steel/Welding | 5/9/2023 | Conditional Approval | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 5/10/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 5/10/2023 | Approved | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 5/11/2023 | Conditional Approval | SCOTT FINNILA |
| Deputy Reinf. Concrete | 5/12/2023 | Conditional Approval | FREDDIE RIVERA |
| Deputy Steel/Welding | 5/12/2023 | Conditional Approval | FREDDIE RIVERA |
| Deputy Steel/Welding | 5/25/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2023 | Partial Approval | SCOTT FINNILA |
| Deputy Wood Construction | 6/28/2023 | Conditional Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 7/5/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 7/5/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 7/5/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/21/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 7/21/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Rough | 7/21/2023 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Rough | 7/21/2023 | Approved | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 7/21/2023 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/9/2023 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 8/9/2023 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 8/9/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 8/14/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Drywall Nailing | 8/21/2023 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 8/21/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Gas Test | 10/3/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Sewer | 10/3/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Underground Mechanical | 10/3/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 10/24/2023 | Approved | KATHRYN BUTTERWORTH |
| Sewer | 10/24/2023 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 11/15/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Final | 11/15/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 11/15/2023 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 2/12/2024 | Approved | ARTHUR NEGRETE |
| Final | 2/12/2024 | OK to Issue CofO | ARTHUR NEGRETE |
| Footing/Foundation/Slab | 2/12/2024 | Approved | ARTHUR NEGRETE |
| Green Building Final | 2/12/2024 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 2/12/2024 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 2/12/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 2/12/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 2/12/2024 | Approved | ARTHUR NEGRETE |
| Smoke Detectors | 2/12/2024 | Approved | ARTHUR NEGRETE |