14204 W SUNBURST ST 91402

Certificate Information: 14204 W SUNBURST ST 91402

Application / Permit
22010-20000-00579
Plan Check / Job No.
B22VN01948
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO DETACHED ADU PER STATE LAW (1-STORY)
Permit Issued
Issued on 12/20/2022
Issuing Office
Current Status
CofO Issued on 1/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/14/2022 APPLICANT
Assigned to Plan Check Engineer 2/14/2022 CARLOS MONTES
Corrections Issued 2/15/2022 CARLOS MONTES
Plan Check Approved 5/17/2022 CARLOS MONTES
Issued 12/20/2022 APPLICANT
CofO in Progress 1/8/2025 VINCENT HANLEY
Permit Finaled 1/16/2025 RUBEN SALAS
CofO Issued 1/16/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/24/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 2/24/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 2/24/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 4/19/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 4/20/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Eden,, Joseph Taki; Lic. No.: C39955 14412 FRIAR ST      VAN NUYS, CA 91401

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/19/2023 Corrections Issued MATTHEW NELSON
Pre-Inspection 5/19/2023 Partial Inspection MATTHEW NELSON
BUILDING-Rough-Frame 1/19/2024 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 1/19/2024 Not Ready for Inspection GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 1/19/2024 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 1/19/2024 Not Ready for Inspection GREGG CUMMINGS
Green Building Rough 1/19/2024 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 1/19/2024 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 1/26/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 1/26/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 1/26/2024 Corrections Issued CHRISTOPHER ROJAS
Underground Mechanical 1/26/2024 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 1/31/2024 Not Ready for Inspection GREGG CUMMINGS
Underground Mechanical 1/31/2024 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 3/26/2024 Corrections Issued KIRK SANDERS
PLUMBING-Rough 4/10/2024 Corrections Issued KIRK SANDERS
Underground Mechanical 4/10/2024 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 4/15/2024 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 4/15/2024 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 4/24/2024 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 4/24/2024 Corrections Issued KIRK SANDERS
HVAC-Rough 4/24/2024 Corrections Issued KIRK SANDERS
PLUMBING-Rough 4/24/2024 Approved KIRK SANDERS
ELECTRICAL-Rough 5/7/2024 Partial Approval KIRK SANDERS
HVAC-Rough 5/7/2024 Corrections Issued KIRK SANDERS
PLUMBING-Rough 5/7/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 5/10/2024 Approved KIRK SANDERS
HVAC-Rough 5/10/2024 Corrections Issued KIRK SANDERS
Wood Frame 5/10/2024 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 5/14/2024 Approved VINCENT HANLEY
Green Building Rough 5/14/2024 Approved VINCENT HANLEY
HVAC-Rough 5/14/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/14/2024 Partial Approval VINCENT HANLEY
Insulation 5/16/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/20/2024 Approved VINCENT HANLEY
Drywall Nailing 6/3/2024 Corrections Issued VINCENT HANLEY
Shower Pan 6/3/2024 Corrections Issued VINCENT HANLEY
Drywall Nailing 6/7/2024 Not Ready for Inspection GREGG CUMMINGS
Shower Pan 6/7/2024 Corrections Issued GREGG CUMMINGS
Drywall Nailing 6/11/2024 Approved VINCENT HANLEY
Shower Pan 6/11/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/12/2024 Approved VINCENT HANLEY
ELECTRICAL-Final 9/19/2024 Corrections Issued VINCENT HANLEY
Final 12/31/2024 Conditional Approval MICHEL ABAJAN
Green Building Final 12/31/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/31/2024 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 12/31/2024 Approved MICHEL ABAJAN
Final 1/3/2025 Corrections Issued VINCENT HANLEY
ELECTRICAL-Final 1/7/2025 Approved VINCENT HANLEY
Final 1/7/2025 OK to Issue CofO VINCENT HANLEY
HVAC-Final 1/7/2025 Approved VINCENT HANLEY
PLUMBING-Final 1/7/2025 Approved VINCENT HANLEY
Service/Power Release 1/13/2025 Approved VINCENT HANLEY