14204 W SUNBURST ST 91402
Certificate Information: 14204 W SUNBURST ST 91402
- Application / Permit
- 22010-20000-00579
- Plan Check / Job No.
- B22VN01948
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO DETACHED ADU PER STATE LAW (1-STORY)
- Permit Issued
- Issued on 12/20/2022
- Issuing Office
- Current Status
- CofO Issued on 1/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2022 | CARLOS MONTES |
| Corrections Issued | 2/15/2022 | CARLOS MONTES |
| Plan Check Approved | 5/17/2022 | CARLOS MONTES |
| Issued | 12/20/2022 | APPLICANT |
| CofO in Progress | 1/8/2025 | VINCENT HANLEY |
| Permit Finaled | 1/16/2025 | RUBEN SALAS |
| CofO Issued | 1/16/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/24/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 2/24/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/24/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 4/19/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 4/20/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Eden,, Joseph Taki; Lic. No.: C39955 | 14412 FRIAR ST VAN NUYS, CA 91401 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/19/2023 | Corrections Issued | MATTHEW NELSON |
| Pre-Inspection | 5/19/2023 | Partial Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 1/19/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/19/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 1/19/2024 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 1/19/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 1/19/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 1/19/2024 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 1/26/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 1/26/2024 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 1/26/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Underground Mechanical | 1/26/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 1/31/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 1/31/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 3/26/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 4/10/2024 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 4/10/2024 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 4/15/2024 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Rough | 4/15/2024 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 4/24/2024 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 4/24/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 4/24/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 4/24/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Rough | 5/7/2024 | Partial Approval | KIRK SANDERS |
| HVAC-Rough | 5/7/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 5/7/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Rough | 5/10/2024 | Approved | KIRK SANDERS |
| HVAC-Rough | 5/10/2024 | Corrections Issued | KIRK SANDERS |
| Wood Frame | 5/10/2024 | Not Ready for Inspection | KIRK SANDERS |
| BUILDING-Rough-Frame | 5/14/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/14/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 5/14/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/14/2024 | Partial Approval | VINCENT HANLEY |
| Insulation | 5/16/2024 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 6/3/2024 | Corrections Issued | VINCENT HANLEY |
| Shower Pan | 6/3/2024 | Corrections Issued | VINCENT HANLEY |
| Drywall Nailing | 6/7/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Shower Pan | 6/7/2024 | Corrections Issued | GREGG CUMMINGS |
| Drywall Nailing | 6/11/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 6/11/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/12/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 9/19/2024 | Corrections Issued | VINCENT HANLEY |
| Final | 12/31/2024 | Conditional Approval | MICHEL ABAJAN |
| Green Building Final | 12/31/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 12/31/2024 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 12/31/2024 | Approved | MICHEL ABAJAN |
| Final | 1/3/2025 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Final | 1/7/2025 | Approved | VINCENT HANLEY |
| Final | 1/7/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 1/7/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 1/7/2025 | Approved | VINCENT HANLEY |
| Service/Power Release | 1/13/2025 | Approved | VINCENT HANLEY |