12606 N HERRICK AVE 91342

Certificate Information: 12606 N HERRICK AVE 91342

Application / Permit
22010-20000-00564
Plan Check / Job No.
B22VN01889
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 2-STORY ADU (34'-5"x27'-9"), 1085 SQFT W/NFPA 13D SPRINKLERS THROUGHOUT PER LAMC 12.22 A.33(c)(d)
Permit Issued
Issued on 2/21/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 PETER MOSESIAN
Corrections Issued 3/11/2022 PETER MOSESIAN
Quality Review Completed 3/18/2022 OMID HEDAYAT
Building Plans Picked Up 3/18/2022 APPLICANT
Plan Check Approved 10/25/2022 PETER MOSESIAN
Issued 2/21/2023 APPLICANT
CofO in Progress 2/21/2025 KEVIN BERBERYAN
Permit Finaled 2/27/2025 RUBEN SALAS
CofO Issued 2/27/2025 RUBEN SALAS
Permit Finaled 2/27/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/20/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 4/21/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 4/21/2022 JOSE DUARTE-DIAZ
Hydrant and Access approval Cleared 5/12/2022 LAURINDA MEADE
Low Impact Development Cleared 9/29/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 9/29/2022 JOSE DUARTE-DIAZ

Contact Information

Architect Sturgill,, Ben Curtis; Lic. No.: C23174 314 E BROADWAY # E      GLENDALE, CA 91205
Contractor Owner-Builder       ,
Engineer Simonian,, Ara; Lic. No.: C37208 314 E BROADWAY STE A      GLENDALE, CA 91205
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/27/2023 Partial Inspection ARAM AVEDISIAN
Pre-Inspection 4/18/2023 Partial Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 4/24/2023 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 4/24/2023 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 4/26/2023 Approved CHRISTOPHER DELLEFIELD
Pre-Inspection 4/26/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Deputy Reinf. Concrete 4/27/2023 Conditional Approval ARAM AVEDISIAN
Underground Mechanical 5/2/2023 Partial Approval ARAM AVEDISIAN
Pre-Inspection 5/23/2023 Partial Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 5/31/2023 Corrections Issued THOMAS FINNILA
HVAC-Rough 5/31/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 6/5/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 6/6/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Wood Frame 6/6/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Rough 6/7/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 6/13/2023 Corrections Issued ROBERT GOLD
HVAC-Rough 6/14/2023 Approved THOMAS FINNILA
BUILDING-Rough-Frame 6/21/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 6/21/2023 Approved RAUL OLAGI
Shower Pan 6/21/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 6/28/2023 Partial Approval ARAM AVEDISIAN
Wood Frame 6/28/2023 Partial Approval ARAM AVEDISIAN
Insulation 7/6/2023 Corrections Issued RAUL OLAGI
Insulation 7/7/2023 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 7/7/2023 Approved MICHEL ABAJAN
Insulation 7/10/2023 Approved MICHEL ABAJAN
Drywall Nailing 7/13/2023 Approved MICHEL ABAJAN
Green Building Rough 7/13/2023 Approved MICHEL ABAJAN
Underground Mechanical 8/21/2023 Partial Approval DAVID ANDERSON
BUILDING-Rough-Frame 9/1/2023 Not Ready for Inspection ROBERT GOLD
ELECTRICAL-Final 9/1/2023 Not Ready for Inspection ROBERT GOLD
Final 9/1/2023 Corrections Issued ROBERT GOLD
Green Building Final 9/1/2023 Not Ready for Inspection ROBERT GOLD
HVAC-Final 9/1/2023 Not Ready for Inspection ROBERT GOLD
PLUMBING-Final 9/1/2023 Not Ready for Inspection ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Not Ready ROBERT GOLD
Service/Power Release 9/1/2023 Not Required ROBERT GOLD
Smoke Detectors 9/1/2023 Not Ready for Inspection ROBERT GOLD
Verify Sprinkler Sign Off 9/1/2023 Not Ready for Inspection ROBERT GOLD
Pre-Inspection 9/28/2023 Partial Inspection ROBERT GOLD
Underground Mechanical 11/15/2023 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 10/17/2024 Approved KEVIN BERBERYAN
Final 10/17/2024 Partial Approval KEVIN BERBERYAN
Green Building Final 10/17/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 10/17/2024 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 10/17/2024 Approved KEVIN BERBERYAN
Verify Sprinkler Sign Off 10/17/2024 Approved KEVIN BERBERYAN
Final 2/21/2025 OK to Issue CofO KEVIN BERBERYAN