12606 N HERRICK AVE 91342
Certificate Information: 12606 N HERRICK AVE 91342
- Application / Permit
- 22010-20000-00564
- Plan Check / Job No.
- B22VN01889
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED 2-STORY ADU (34'-5"x27'-9"), 1085 SQFT W/NFPA 13D SPRINKLERS THROUGHOUT PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 2/21/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | PETER MOSESIAN |
| Corrections Issued | 3/11/2022 | PETER MOSESIAN |
| Quality Review Completed | 3/18/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| Plan Check Approved | 10/25/2022 | PETER MOSESIAN |
| Issued | 2/21/2023 | APPLICANT |
| CofO in Progress | 2/21/2025 | KEVIN BERBERYAN |
| Permit Finaled | 2/27/2025 | RUBEN SALAS |
| CofO Issued | 2/27/2025 | RUBEN SALAS |
| Permit Finaled | 2/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/20/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 4/21/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 5/12/2022 | LAURINDA MEADE |
| Low Impact Development | Cleared | 9/29/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 9/29/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Architect | Sturgill,, Ben Curtis; Lic. No.: C23174 | 314 E BROADWAY # E GLENDALE, CA 91205 |
| Contractor | Owner-Builder | , |
| Engineer | Simonian,, Ara; Lic. No.: C37208 | 314 E BROADWAY STE A GLENDALE, CA 91205 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/27/2023 | Partial Inspection | ARAM AVEDISIAN |
| Pre-Inspection | 4/18/2023 | Partial Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 4/24/2023 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 4/24/2023 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 4/26/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 4/26/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Deputy Reinf. Concrete | 4/27/2023 | Conditional Approval | ARAM AVEDISIAN |
| Underground Mechanical | 5/2/2023 | Partial Approval | ARAM AVEDISIAN |
| Pre-Inspection | 5/23/2023 | Partial Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 5/31/2023 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 5/31/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 6/5/2023 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/6/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Wood Frame | 6/6/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 6/7/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/13/2023 | Corrections Issued | ROBERT GOLD |
| HVAC-Rough | 6/14/2023 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/21/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 6/21/2023 | Approved | RAUL OLAGI |
| Shower Pan | 6/21/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 6/28/2023 | Partial Approval | ARAM AVEDISIAN |
| Wood Frame | 6/28/2023 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 7/6/2023 | Corrections Issued | RAUL OLAGI |
| Insulation | 7/7/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 7/7/2023 | Approved | MICHEL ABAJAN |
| Insulation | 7/10/2023 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 7/13/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/13/2023 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 8/21/2023 | Partial Approval | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/1/2023 | Not Ready for Inspection | ROBERT GOLD |
| ELECTRICAL-Final | 9/1/2023 | Not Ready for Inspection | ROBERT GOLD |
| Final | 9/1/2023 | Corrections Issued | ROBERT GOLD |
| Green Building Final | 9/1/2023 | Not Ready for Inspection | ROBERT GOLD |
| HVAC-Final | 9/1/2023 | Not Ready for Inspection | ROBERT GOLD |
| PLUMBING-Final | 9/1/2023 | Not Ready for Inspection | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 9/1/2023 | SGSOV Not Ready | ROBERT GOLD |
| Service/Power Release | 9/1/2023 | Not Required | ROBERT GOLD |
| Smoke Detectors | 9/1/2023 | Not Ready for Inspection | ROBERT GOLD |
| Verify Sprinkler Sign Off | 9/1/2023 | Not Ready for Inspection | ROBERT GOLD |
| Pre-Inspection | 9/28/2023 | Partial Inspection | ROBERT GOLD |
| Underground Mechanical | 11/15/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 10/17/2024 | Approved | KEVIN BERBERYAN |
| Final | 10/17/2024 | Partial Approval | KEVIN BERBERYAN |
| Green Building Final | 10/17/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 10/17/2024 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 10/17/2024 | Approved | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 10/17/2024 | Approved | KEVIN BERBERYAN |
| Final | 2/21/2025 | OK to Issue CofO | KEVIN BERBERYAN |