12604 N HERRICK AVE 91342

Certificate Information: 12604 N HERRICK AVE 91342

Application / Permit
22010-20000-00563
Plan Check / Job No.
B22VN01889
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD (1930 SQFT), W/FRONT PORCH (42 SQFT), W/ATT. 2-CAR GARAGE (429 SQFT), (41'-6"x37'-0") W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 9/6/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 PETER MOSESIAN
Corrections Issued 3/11/2022 PETER MOSESIAN
Quality Review Completed 3/18/2022 OMID HEDAYAT
Building Plans Picked Up 3/18/2022 APPLICANT
Plan Check Approved 10/25/2022 PETER MOSESIAN
Issued 9/6/2023 APPLICANT
CofO in Progress 2/18/2025 KEVIN BERBERYAN
Permit Finaled 2/27/2025 RUBEN SALAS
CofO Issued 2/27/2025 RUBEN SALAS
Permit Finaled 2/27/2025 RUBEN SALAS

Permit Application Clearance Information

Permit Cleared 4/20/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 4/21/2022 JOSE DUARTE-DIAZ
Hydrant and Access approval Cleared 5/12/2022 LAURINDA MEADE
Trees in Parkway Cleared 7/22/2022 ADALBERTO VERA
Low Impact Development Cleared 10/21/2022 DEBORA LEITE
Roof/Waste drainage to street Cleared 10/21/2022 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 10/24/2022 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 10/24/2022 JOSE DUARTE-DIAZ

Contact Information

Architect Sturgill,, Ben Curtis; Lic. No.: C23174 314 E BROADWAY # E      GLENDALE, CA 91205
Contractor Owner-Builder       ,
Engineer Simonian,, Ara; Lic. No.: C37208 314 E BROADWAY STE A      GLENDALE, CA 91205
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/18/2023 Partial Inspection KEVIN BERBERYAN
Underground Mechanical 11/15/2023 Approved KEVIN BERBERYAN
Footing/Foundation/Slab 11/29/2023 Not Ready for Inspection KEVIN BERBERYAN
Footing/Foundation/Slab 12/4/2023 Approved KEVIN BERBERYAN
Deputy Reinf. Concrete 12/6/2023 Conditional Approval KEVIN BERBERYAN
Deputy Wood Construction 1/9/2024 Conditional Approval KEVIN BERBERYAN
Deputy Wood Construction 1/31/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 2/1/2024 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 2/6/2024 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 2/29/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 3/4/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 3/5/2024 Conditional Approval KEVIN BERBERYAN
PLUMBING-Rough 3/5/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 3/11/2024 Approved KEVIN BERBERYAN
Shower Pan 3/13/2024 Approved CHRISTOPHER ROJAS
Insulation 3/15/2024 Conditional Approval KEVIN BERBERYAN
Interior/Exterior Lathing 3/19/2024 Approved KEVIN BERBERYAN
Drywall Nailing 3/22/2024 Approved KEVIN BERBERYAN
Green Building Rough 3/22/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 3/22/2024 Partial Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 3/27/2024 Approved KEVIN BERBERYAN
Service/Power Release 6/14/2024 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Final 7/8/2024 Approved KEVIN BERBERYAN
Service/Power Release 7/8/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 9/9/2024 Approved KEVIN BERBERYAN
Final 9/9/2024 Corrections Issued KEVIN BERBERYAN
Green Building Final 9/9/2024 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/9/2024 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 9/9/2024 Approved KEVIN BERBERYAN
Verify Sprinkler Sign Off 9/9/2024 Approved KEVIN BERBERYAN
Final 10/16/2024 Partial Approval KEVIN BERBERYAN
Final 2/18/2025 OK to Issue CofO KEVIN BERBERYAN