12604 N HERRICK AVE 91342
Certificate Information: 12604 N HERRICK AVE 91342
- Application / Permit
- 22010-20000-00563
- Plan Check / Job No.
- B22VN01889
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD (1930 SQFT), W/FRONT PORCH (42 SQFT), W/ATT. 2-CAR GARAGE (429 SQFT), (41'-6"x37'-0") W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 9/6/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | PETER MOSESIAN |
| Corrections Issued | 3/11/2022 | PETER MOSESIAN |
| Quality Review Completed | 3/18/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| Plan Check Approved | 10/25/2022 | PETER MOSESIAN |
| Issued | 9/6/2023 | APPLICANT |
| CofO in Progress | 2/18/2025 | KEVIN BERBERYAN |
| Permit Finaled | 2/27/2025 | RUBEN SALAS |
| CofO Issued | 2/27/2025 | RUBEN SALAS |
| Permit Finaled | 2/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Permit | Cleared | 4/20/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 4/21/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 5/12/2022 | LAURINDA MEADE |
| Trees in Parkway | Cleared | 7/22/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 10/21/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 10/21/2022 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/24/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 10/24/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Architect | Sturgill,, Ben Curtis; Lic. No.: C23174 | 314 E BROADWAY # E GLENDALE, CA 91205 |
| Contractor | Owner-Builder | , |
| Engineer | Simonian,, Ara; Lic. No.: C37208 | 314 E BROADWAY STE A GLENDALE, CA 91205 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/18/2023 | Partial Inspection | KEVIN BERBERYAN |
| Underground Mechanical | 11/15/2023 | Approved | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 11/29/2023 | Not Ready for Inspection | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 12/4/2023 | Approved | KEVIN BERBERYAN |
| Deputy Reinf. Concrete | 12/6/2023 | Conditional Approval | KEVIN BERBERYAN |
| Deputy Wood Construction | 1/9/2024 | Conditional Approval | KEVIN BERBERYAN |
| Deputy Wood Construction | 1/31/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2024 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 2/6/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 2/29/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 3/4/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/5/2024 | Conditional Approval | KEVIN BERBERYAN |
| PLUMBING-Rough | 3/5/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 3/11/2024 | Approved | KEVIN BERBERYAN |
| Shower Pan | 3/13/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 3/15/2024 | Conditional Approval | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 3/19/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 3/22/2024 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 3/22/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 3/22/2024 | Partial Inspection | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 3/27/2024 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 6/14/2024 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Final | 7/8/2024 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 7/8/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 9/9/2024 | Approved | KEVIN BERBERYAN |
| Final | 9/9/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 9/9/2024 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/9/2024 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 9/9/2024 | Approved | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 9/9/2024 | Approved | KEVIN BERBERYAN |
| Final | 10/16/2024 | Partial Approval | KEVIN BERBERYAN |
| Final | 2/18/2025 | OK to Issue CofO | KEVIN BERBERYAN |