5316 N LENNOX AVE 91401

Certificate Information: 5316 N LENNOX AVE 91401

Application / Permit
22010-20000-00554
Plan Check / Job No.
B22VN01848
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW 13' X 17'-8" CABANA. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/19/2022
Issuing Office
Current Status
CofO Issued on 2/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 RAPHAEL ROSAS
Corrections Issued 2/21/2022 RAPHAEL ROSAS
Applicant returned to address corrections 3/28/2022 RAPHAEL ROSAS
Plan Check Approved 4/18/2022 RAPHAEL ROSAS
Issued 4/19/2022 APPLICANT
Building Plans Picked Up 4/22/2022 APPLICANT
CofO in Progress 2/8/2023 JOHN COLEMAN
Permit Finaled 2/17/2023 MICHAEL SMITH
CofO Issued 2/17/2023 MICHAEL SMITH
Permit Finaled 2/17/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/15/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 4/15/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 4/18/2022 JOHN BACON

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/26/2022 Corrections Issued RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 9/15/2022 Approved RICHARD DOCKUS
Footing/Foundation/Slab 9/15/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 9/15/2022 Partial Approval RICHARD DOCKUS
Deputy Wood Construction 10/21/2022 Partial Approval ROBERT GOLD
BUILDING-Rough-Frame 10/28/2022 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Rough 10/28/2022 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 10/28/2022 Approved RICHARD DOCKUS
HVAC-Rough 10/28/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 10/28/2022 Approved RICHARD DOCKUS
Verify Sprinkler Sign Off 10/28/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 11/4/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 11/4/2022 Approved RICHARD DOCKUS
Insulation 11/8/2022 Conditional Approval THOMAS FINNILA
Underground Mechanical 11/8/2022 Partial Approval THOMAS FINNILA
Drywall Nailing 11/14/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 11/14/2022 Not Ready for Inspection THOMAS FINNILA
Shower Pan 11/14/2022 Approved THOMAS FINNILA
Interior/Exterior Lathing 11/23/2022 Approved RYAN SALAZAR
ELECTRICAL-Final 12/22/2022 Approved JOHN COLEMAN
Final 12/22/2022 Corrections Issued JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 12/22/2022 SGSOV Approved JOHN COLEMAN
Smoke Detectors 12/22/2022 Approved JOHN COLEMAN
Final 1/17/2023 Corrections Issued JOHN COLEMAN
Service/Power Release 1/17/2023 Approved JOHN COLEMAN
Final 2/8/2023 OK to Issue CofO JOHN COLEMAN