13475 N BRADLEY AVE 91342

Certificate Information: 13475 N BRADLEY AVE 91342

Application / Permit
22010-20000-00541
Plan Check / Job No.
B22VN01800
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 12/2/2022
Issuing Office
Current Status
CofO Issued on 2/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/9/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 LAMAR DAVIS
Corrections Issued 3/1/2022 LAMAR DAVIS
Quality Review Completed 3/9/2022 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 11/22/2022 LAMAR DAVIS
Issued 12/2/2022 APPLICANT
CofO in Progress 2/21/2025 KEVIN BERBERYAN
Permit Finaled 2/27/2025 RUBEN SALAS
CofO Issued 2/27/2025 RUBEN SALAS
Permit Finaled 2/27/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/20/2022 ROMAN GUTIERREZ
Low Impact Development Cleared 4/20/2022 KHAING AYE
Roof/Waste drainage to street Cleared 4/21/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 4/25/2022 ROMAN GUTIERREZ
Sewer availability Cleared 4/25/2022 ROMAN GUTIERREZ
Hydrant and Access approval Cleared 5/20/2022 MICHAEL GILLISSIE
GPI Written Notices Cleared 11/14/2022 BRIAN MILLER
Grading Pre-Inspection Cleared 11/14/2022 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/26/2023 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 7/31/2023 Partial Approval RAUL OLAGI
Sewer 7/31/2023 Approved RAUL OLAGI
Footing/Foundation/Slab 9/7/2023 Corrections Issued ROBERT GOLD
BUILDING-Rough-Frame 11/9/2023 Conditional Approval KEVIN BERBERYAN
Green Building Rough 11/9/2023 Not Ready for Inspection KEVIN BERBERYAN
Verify Sprinkler Sign Off 11/9/2023 Not Ready for Inspection KEVIN BERBERYAN
BUILDING-Rough-Frame 2/16/2024 Partial Approval CRAIG DAVIS
ELECTRICAL-Rough 2/16/2024 Corrections Issued CRAIG DAVIS
Green Building Rough 2/16/2024 Not Ready for Inspection CRAIG DAVIS
HVAC-Rough 2/16/2024 Approved CRAIG DAVIS
PLUMBING-Rough 2/16/2024 Corrections Issued CRAIG DAVIS
Verify Sprinkler Sign Off 2/16/2024 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 3/12/2024 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 3/12/2024 Conditional Approval KEVIN BERBERYAN
Green Building Rough 3/12/2024 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 3/12/2024 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 3/12/2024 Approved KEVIN BERBERYAN
Verify Sprinkler Sign Off 3/12/2024 Approved KEVIN BERBERYAN
Wood Frame 3/12/2024 Partial Approval KEVIN BERBERYAN
Interior/Exterior Lathing 3/15/2024 Approved KEVIN BERBERYAN
Insulation 3/22/2024 Conditional Approval KEVIN BERBERYAN
Interior/Exterior Lathing 3/29/2024 Approved KEVIN BERBERYAN
Drywall Nailing 4/5/2024 Approved KEVIN BERBERYAN
PLUMBING-Final 12/20/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 1/9/2025 Approved KEVIN BERBERYAN
Final 1/9/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 1/9/2025 Approved KEVIN BERBERYAN
Green Building Final 1/9/2025 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Final 1/9/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 1/9/2025 SGSOV Approved KEVIN BERBERYAN
Service/Power Release 1/9/2025 Approved KEVIN BERBERYAN
Smoke Detectors 1/9/2025 Approved KEVIN BERBERYAN
Final 2/21/2025 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 2/21/2025 Approved KEVIN BERBERYAN