505 W 31ST ST #207 90007

Certificate Information: 505 W 31ST ST #207 90007

Application / Permit
22010-20000-00528
Plan Check / Job No.
B22VN01748
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
ePlan. Convert existing Recreation Room (B occupancy) to Accessory Dwelling Unit at 2nd floor of existing 7-story Affordable Housing/Apartment building.
Permit Issued
Issued on 5/26/2022
Issuing Office
Current Status
CofO Issued on 8/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/3/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 PRANITA SHAH
Corrections Issued 3/11/2022 PRANITA SHAH
Disabled Access Plans Picked Up 3/21/2022 APPLICANT
Quality Review Completed 3/24/2022 HERNAN ARREOLA
Applicant returned to address corrections 5/4/2022 PRANITA SHAH
Plan Check Approved 5/24/2022 PRANITA SHAH
Issued 5/26/2022 APPLICANT
CofO in Progress 8/30/2022 JAMES POWERS
CofO Issued 8/30/2022 ERNESTO CORRAL
Permit Finaled 8/30/2022 ERNESTO CORRAL

Permit Application Clearance Information

Tenant Habitability Plan Cleared 3/15/2022 ISMAEL HERNANDEZ
ZI Cleared 3/18/2022 YINGSHI HUANG
Address approval Cleared 3/19/2022 CINDY QI
Sewer availability Cleared 3/19/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 3/22/2022 CINDY QI
Fire Marshal Fire Life Safety Cleared 4/8/2022 MENOA AGHAJANI
Redevelopment Project Area Cleared 4/26/2022 SUSAN WONG
DAS Clearance Cleared 5/17/2022 PRANITA SHAH

Contact Information

Architect Blatter,, Jay Irwin; Lic. No.: NA22984       ,
Contractor Owner-Builder       ,

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 6/29/2022 Approved MARK FERRARI
Drywall Nailing 7/11/2022 Partial Approval DAVID BURKHEAD
Final 8/8/2022 OK for TCO JAMES POWERS
METHANE-Final 8/8/2022 Approved JAMES POWERS
METHANE-Rough 8/8/2022 Approved JAMES POWERS
Reinforced Concrete Frame 8/8/2022 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 8/8/2022 SGSOV Approved JAMES POWERS
Smoke Detectors 8/8/2022 Approved JAMES POWERS
Final 8/30/2022 OK to Issue CofO JAMES POWERS