5823 N IRVINE AVE 91601
Certificate Information: 5823 N IRVINE AVE 91601
- Application / Permit
- 22010-20000-00522
- Plan Check / Job No.
- B22VN01726
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 27' X 15' ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 5/25/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/11/2022 | SERGIO MUNIZ |
| Corrections Issued | 2/13/2022 | SERGIO MUNIZ |
| Plan Check Approved | 5/9/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 5/11/2022 | APPLICANT |
| Issued | 5/25/2022 | APPLICANT |
| CofO in Progress | 5/16/2023 | JACK KARGODORIAN |
| Permit Finaled | 7/13/2023 | DANIEL ORRANTE |
| CofO Issued | 7/13/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/13/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 2/25/2022 | CARLOS AGUILERA |
| ZA Case | Cleared | 2/25/2022 | DANG NGUYEN |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/28/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 4/25/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Dwell Llc; Lic. No.: 1030158-B | 5315 LAUREL CANYON BLVD #102 VALLEY VILLAGE, CA 91607 |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 21126 MERRIDY STREET CHATSWORTH, CA 91311 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/24/2022 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 7/5/2022 | Partial Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/13/2022 | Corrections Issued | THOMAS FINNILA |
| Pre-Inspection | 7/19/2022 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2022 | Corrections Issued | DEANDRE HOFFMAN |
| Gas Test | 8/2/2022 | Approved | DEANDRE HOFFMAN |
| PLUMBING-Rough | 8/2/2022 | Approved | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 8/3/2022 | Conditional Approval | DAVID MATSON |
| Deputy Wood Construction | 8/3/2022 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 8/23/2022 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 8/23/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Rough | 8/23/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 8/23/2022 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/3/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 10/3/2022 | Approved | THOMAS FINNILA |
| Green Building Rough | 10/3/2022 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 10/3/2022 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 10/3/2022 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 10/20/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 10/20/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 10/20/2022 | Partial Approval | JACK KARGODORIAN |
| Insulation | 11/7/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 11/7/2022 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 11/7/2022 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 11/16/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 11/16/2022 | Partial Approval | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 3/29/2023 | Approved | JACK KARGODORIAN |
| Final | 3/29/2023 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 3/29/2023 | Approved | JACK KARGODORIAN |
| Green Building Final | 3/29/2023 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 3/29/2023 | SGSOV Not Ready | JACK KARGODORIAN |
| Service/Power Release | 3/29/2023 | Corrections Issued | JACK KARGODORIAN |
| Smoke Detectors | 3/29/2023 | Approved | JACK KARGODORIAN |
| Final | 4/25/2023 | Corrections Issued | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2023 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 4/25/2023 | Approved | JACK KARGODORIAN |
| Final | 5/15/2023 | OK to Issue CofO | JACK KARGODORIAN |
| Service/Power Release | 5/15/2023 | Approved | JACK KARGODORIAN |