12365 W CALIFA ST 91607

Certificate Information: 12365 W CALIFA ST 91607

Application / Permit
22010-20000-00504
Plan Check / Job No.
B22VN01651
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
NEW 7'-0" X 15'-0" DETACHED POOL HOUSE/STORAGE ROOM. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/22/2022
Issuing Office
Current Status
CofO Issued on 3/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/2/2022 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 LUISANGEL VALENZUELA
Corrections Issued 2/3/2022 LUISANGEL VALENZUELA
Applicant returned to address corrections 6/9/2022 LUISANGEL VALENZUELA
Plan Check Approved 6/21/2022 LUISANGEL VALENZUELA
Issued 6/22/2022 APPLICANT
Building Plans Picked Up 6/22/2022 APPLICANT
CofO in Progress 3/13/2023 ROBERT GOLD
Permit Finaled 3/13/2023 DANIEL ORRANTE
CofO Issued 3/13/2023 DANIEL ORRANTE
Permit Finaled 3/13/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/8/2022 AMIR KASHFI
Low Impact Development Cleared 5/3/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 5/3/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/29/2022 Approved RAFAEL CORTES
Footing/Foundation/Slab 6/29/2022 Approved RAFAEL CORTES
Underground Mechanical 6/29/2022 Approved RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 7/6/2022 Approved RAFAEL CORTES
Rough-Elec/Plmb/HVAC 7/6/2022 Approved RAFAEL CORTES
Sewer 7/6/2022 Approved RAFAEL CORTES
Insulation 7/12/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 7/12/2022 Partial Approval ASHLEY THOMPSON
Shower Pan 7/12/2022 Approved ASHLEY THOMPSON
Drywall Nailing 7/18/2022 Approved RAFAEL CORTES
Green Building Rough 7/18/2022 Approved RAFAEL CORTES
Interior/Exterior Lathing 7/18/2022 Approved RAFAEL CORTES
BUILDING-Rough-Frame 8/30/2022 Not Ready for Inspection RAFAEL CORTES
ELECTRICAL-Final 8/30/2022 Not Ready for Inspection RAFAEL CORTES
Final 8/30/2022 Not Ready for Inspection RAFAEL CORTES
Green Building Final 8/30/2022 Not Ready for Inspection RAFAEL CORTES
HVAC-Final 8/30/2022 Not Ready for Inspection RAFAEL CORTES
PLUMBING-Final 8/30/2022 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 8/30/2022 SGSOV Not Ready RAFAEL CORTES
Service/Power Release 8/30/2022 Not Ready for Inspection RAFAEL CORTES
Smoke Detectors 8/30/2022 Not Ready for Inspection RAFAEL CORTES
Verify Sprinkler Sign Off 8/30/2022 Corrections Issued RAFAEL CORTES
BUILDING-Rough-Frame 11/4/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 11/4/2022 Approved CHRISTOPHE COCHRAN
Final 11/4/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 11/4/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 11/4/2022 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 11/4/2022 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 11/4/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 11/4/2022 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 11/4/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 11/14/2022 Approved CHRISTOPHER DELLEFIELD
Final 11/14/2022 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Final 11/14/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Final 11/14/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Service/Power Release 11/14/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 11/23/2022 Approved KIRK SANDERS
Final 11/23/2022 Not Ready for Inspection KIRK SANDERS
PLUMBING-Final 11/23/2022 Not Ready for Inspection KIRK SANDERS
Service/Power Release 11/23/2022 Not Required KIRK SANDERS
Final 12/13/2022 Conditional Approval JORDAN KUTZLY