10030 N OAKDALE AVE 91311

Certificate Information: 10030 N OAKDALE AVE 91311

Application / Permit
22010-20000-00468
Plan Check / Job No.
B22VN01555
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) IRR. SHAPED 26'-8" x 59'-7" DET. ACCESSORY DWELLING UNIT W/ ATT. PATIO COVER PER LAMC 12.22 A.33 (c)-(d); ALL WORK PER WFPP AND LADBS PATIO COVER STANDARD DETAIL
Permit Issued
Issued on 5/19/2022
Issuing Office
Current Status
CofO Issued on 2/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/1/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 SEAN SHAHMIRI
Corrections Issued 3/3/2022 SEAN SHAHMIRI
Quality Review Completed 3/7/2022 OMID HEDAYAT
Building Plans Picked Up 3/8/2022 APPLICANT
Applicant returned to address corrections 5/2/2022 SEAN SHAHMIRI
Plan Check Approved 5/18/2022 SEAN SHAHMIRI
Issued 5/19/2022 APPLICANT
CofO in Progress 2/15/2023 DAVID SCANTLIN
Permit Finaled 2/15/2023 JOHN JANSON
CofO Issued 2/15/2023 JOHN JANSON
Permit Finaled 2/15/2023 JOHN JANSON

Permit Application Clearance Information

Hydrant and Access approval Cleared 4/22/2022 DWIGHT SANKEY
Low Impact Development Cleared 4/25/2022 CHRIS VONG
Address approval Cleared 4/26/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 4/26/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 4/26/2022 MEGAN GODINEZ
Sewer availability Cleared 4/26/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/18/2022 Partial Approval JEFFREY PARD
PLUMBING-Rough 8/2/2022 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 8/11/2022 Approved JEFFREY PARD
PLUMBING-Rough 8/23/2022 Partial Approval JEFFREY PARD
Sewer 8/23/2022 Approved JEFFREY PARD
Wood Frame 9/13/2022 Partial Approval JEFFREY PARD
BUILDING-Rough-Frame 9/22/2022 Corrections Issued DAVID SANDOVAL
ELECTRICAL-Rough 9/22/2022 Approved DAVID SANDOVAL
PLUMBING-Rough 9/22/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 9/30/2022 Not Ready for Inspection DAVID SCANTLIN
Green Building Rough 9/30/2022 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 9/30/2022 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 9/30/2022 Not Ready for Inspection DAVID SCANTLIN
Wood Frame 9/30/2022 Approved DAVID SCANTLIN
Insulation 10/17/2022 Not Ready for Inspection JOHN KIDWELL
Interior/Exterior Lathing 10/17/2022 Partial Approval JOHN KIDWELL
Drywall Nailing 10/31/2022 Approved JOHN KIDWELL
Green Building Rough 10/31/2022 Approved JOHN KIDWELL
Interior/Exterior Lathing 10/31/2022 Partial Approval JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 12/21/2022 SGSOV Not Ready JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 1/4/2023 SGSOV Not Ready JOHN KIDWELL
BUILDING-Rough-Frame 1/19/2023 Approved JOHN KIDWELL
Final 1/19/2023 Corrections Issued DAVID SCANTLIN
Final 1/19/2023 Corrections Issued JOHN KIDWELL
Green Building Final 1/19/2023 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 1/19/2023 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 1/19/2023 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 1/19/2023 Approved JOHN KIDWELL
Final 2/14/2023 OK to Issue CofO DAVID SCANTLIN
Green Building Final 2/14/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 2/14/2023 SGSOV Approved DAVID SCANTLIN
Service/Power Release 2/14/2023 Approved DAVID SCANTLIN