10975 N CARTWRIGHT DR 91311
Certificate Information: 10975 N CARTWRIGHT DR 91311
- Application / Permit
- 22010-20000-00466
- Plan Check / Job No.
- B22VN01549
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW IRREGULAR SHAPED 23'-4" X 18'-0", 357 SF RECREATION ROOM W/ FULL BATHROOM (EXTERIOR ACCESS ONLY). NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/21/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/10/2022 | COLIN LOREDO |
| Corrections Issued | 3/14/2022 | COLIN LOREDO |
| Quality Review Completed | 3/25/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/30/2022 | APPLICANT |
| Applicant returned to address corrections | 12/15/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/3/2023 | RAPHAEL ROSAS |
| Plan Check Approved | 2/21/2023 | RAPHAEL ROSAS |
| Issued | 2/21/2023 | APPLICANT |
| CofO in Progress | 7/12/2023 | DAVID SCANTLIN |
| Permit Finaled | 4/26/2024 | DANIEL ORRANTE |
| CofO Issued | 4/26/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/26/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/10/2022 | COLIN LOREDO |
| "Q" conditions | Cleared | 8/16/2022 | NELSON RODRIGUEZ |
| Miscellaneous | Cleared | 8/16/2022 | NELSON RODRIGUEZ |
| Miscellaneous | Cleared | 8/16/2022 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 8/16/2022 | NELSON RODRIGUEZ |
| ZA Case | Cleared | 8/16/2022 | NELSON RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 9/14/2022 | ROMAN GUTIERREZ |
| Watercourse | Cleared | 9/15/2022 | ROMAN GUTIERREZ |
| Hydrant and Access approval | Cleared | 9/23/2022 | LAVEON RIDER |
| Distance to fire station | Cleared | 9/27/2022 | LAVEON RIDER |
| Grading Pre-Inspection | Cleared | 1/25/2023 | KIRK LINKLATER |
| GPI Written Notices | Cleared | 2/21/2023 | COLIN LOREDO |
Contact Information
| Contractor | Hays Hal Construction Inc; Lic. No.: 667560-B | 4181 LATHAM ST RIVERSIDE, CA 92501 |
| Engineer | Miller,, Karen Lynn; Lic. No.: GE2257 | 6634 VALJEAN AVENUE VAN NUYS, CA 91406 |
| Engineer | Rahman,, Moksudur; Lic. No.: C69263 | 14616 MCKENDREE AVE CHINO, CA 91708 |
| Geologist | Putnam,, Lance Richard; Lic. No.: EG2469 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/27/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 3/1/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 3/2/2023 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 3/6/2023 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 3/6/2023 | Partial Inspection | MORRIS JACKSON |
| Special/Order Compliance | 3/6/2023 | Partial Inspection | SEAN WIRCH |
| BUILDING-Rough-Frame | 3/22/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 3/22/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| MERV13>=Rough | 3/22/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 3/22/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 4/3/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 4/3/2023 | Approved | DAVID SCANTLIN |
| Insulation | 4/13/2023 | Corrections Issued | SEAN HAUPT |
| BUILDING-Rough-Frame | 5/10/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 5/10/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| MERV13>=Rough | 5/10/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 5/10/2023 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 5/25/2023 | Approved | DAVID SCANTLIN |
| Insulation | 6/1/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 6/7/2023 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 6/22/2023 | Approved | DAVID SCANTLIN |
| Final | 6/22/2023 | Corrections Issued | DAVID SCANTLIN |
| Footing/Foundation/Slab | 6/22/2023 | Approved | DAVID SCANTLIN |
| Green Building Final | 6/22/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 6/22/2023 | Approved | DAVID SCANTLIN |
| MERV13>=Final | 6/22/2023 | Approved | DAVID SCANTLIN |
| MERV13>=Rough | 6/22/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 6/22/2023 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 6/22/2023 | Approved | DAVID SCANTLIN |
| Smoke Detectors | 6/22/2023 | Approved | DAVID SCANTLIN |
| Final | 6/30/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 7/11/2023 | OK to Issue CofO | DAVID SCANTLIN |