5603 N KELVIN AVE 91367
Certificate Information: 5603 N KELVIN AVE 91367
- Application / Permit
- 22010-20000-00457
- Plan Check / Job No.
- B22VN01521
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED (34'-1"x27'-0"), 918 SQFT ADU USING WFPP PER LAMC 12.22 A.33(c)(d)
- Permit Issued
- Issued on 7/15/2022
- Issuing Office
- Current Status
- CofO Issued on 11/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | PETER MOSESIAN |
| Corrections Issued | 3/2/2022 | PETER MOSESIAN |
| Quality Review Completed | 3/7/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/8/2022 | APPLICANT |
| Plan Check Approved | 7/15/2022 | PETER MOSESIAN |
| Issued | 7/15/2022 | APPLICANT |
| CofO in Progress | 11/23/2022 | STEVEN BACK |
| CofO Issued | 11/29/2022 | JOHN JANSON |
| Permit Finaled | 11/29/2022 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/19/2022 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 5/6/2022 | DWAYNE LAURENT |
| Address approval | Cleared | 5/27/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 5/27/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 5/27/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/27/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/10/2022 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 8/10/2022 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 8/15/2022 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 8/15/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 9/19/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 9/19/2022 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 9/19/2022 | Approved | STEVEN BACK |
| Shower Pan | 9/19/2022 | Approved | STEVEN BACK |
| Underground Mechanical | 9/19/2022 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 9/22/2022 | Approved | STEVEN BACK |
| Green Building Rough | 9/22/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 9/22/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 9/22/2022 | Approved | STEVEN BACK |
| Insulation | 9/26/2022 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 9/29/2022 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 11/23/2022 | Approved | STEVEN BACK |
| Final | 11/23/2022 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 11/23/2022 | Approved | STEVEN BACK |
| PLUMBING-Final | 11/23/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 11/23/2022 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 11/23/2022 | Approved | STEVEN BACK |