4816 N LA RODA AVE 90041
Certificate Information: 4816 N LA RODA AVE 90041
- Application / Permit
- 22010-20000-00455
- Plan Check / Job No.
- B22VN01513
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW DETACHED 20' X 18'-10" GARAGE PER ENGINEER
- Permit Issued
- Issued on 4/25/2022
- Issuing Office
- Current Status
- CofO Issued on 4/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 2/17/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 3/30/2022 | JEROME MAGAT PALMA |
| No Progress | 3/30/2022 | JEROME MAGAT PALMA |
| Plan Check Approved | 4/5/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/11/2022 | APPLICANT |
| Issued | 4/25/2022 | APPLICANT |
| CofO in Progress | 4/3/2023 | CRAIG VAUGHAN |
| CofO in Progress | 4/3/2023 | CRAIG VAUGHAN |
| Permit Finaled | 4/6/2023 | DEROLD HAUFF |
| CofO Issued | 4/6/2023 | DEROLD HAUFF |
| Permit Finaled | 4/6/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/9/2022 | LANNY MERRICK |
| Roof/Waste drainage to street | Cleared | 3/10/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Phan,, Phillip Trung Tri; Lic. No.: C76425 | 641 S ALMIRANTE DR WEST COVINA, CA 91791 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/21/2022 | Corrections Issued | CRAIG VAUGHAN |
| Pre-Inspection | 6/21/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 7/14/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/12/2022 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 9/12/2022 | Corrections Issued | SCOTT FINNILA |
| Wood Frame | 9/12/2022 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 9/20/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 9/20/2022 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2022 | Approved | CHARLES BOGHOSKHAN |
| Insulation | 11/15/2022 | Approved | CHARLES BOGHOSKHAN |
| Interior/Exterior Lathing | 11/15/2022 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 12/9/2022 | Approved | CHARLES BOGHOSKHAN |
| Final | 12/27/2022 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 12/27/2022 | Approved | CHARLES BOGHOSKHAN |
| SGSOV-Seismic Gas S/O Valve | 12/27/2022 | SGSOV No Gas | CHARLES BOGHOSKHAN |
| Smoke Detectors | 12/27/2022 | Approved | CHARLES BOGHOSKHAN |
| Final | 3/1/2023 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Final | 3/31/2023 | OK to Issue CofO | CRAIG VAUGHAN |
| Service/Power Release | 3/31/2023 | Approved | CRAIG VAUGHAN |