2109 S WEST VIEW ST 90016

Certificate Information: 2109 S WEST VIEW ST 90016

Application / Permit
22010-20000-00418
Plan Check / Job No.
B22VN01349
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 2-STORY ADU W/ROOFTOP DECK
Permit Issued
Issued on 12/5/2022
Issuing Office
Current Status
CofO Issued on 2/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2022 APPLICANT
Disabled Access Plans Picked Up 2/8/2022 APPLICANT
Green Plans Picked Up 2/8/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 ALBERT SERVIN
Corrections Issued 2/23/2022 ALBERT SERVIN
Quality Review Completed 2/23/2022 PETER KIM
Plan Check Approved 12/5/2022 ALBERT SERVIN
Issued 12/5/2022 APPLICANT
CofO in Progress 1/28/2025 JUSTIN HAWLEY
Permit Finaled 2/2/2025 DEROLD HAUFF
Permit Finaled 2/2/2025 DEROLD HAUFF
CofO Issued 2/2/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/29/2022 CELINA MORENO
Hydrant and Access approval Cleared 5/11/2022 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 5/12/2022 CELINA MORENO
Low Impact Development Cleared 6/20/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/23/2022 CELINA MORENO
Sewer availability Cleared 6/23/2022 CELINA MORENO
Green Code Cleared 6/28/2022 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 4/10/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 9/25/2023 Approved DEROLD HAUFF
Floor/Roof Diaphrgm/Shear Wall 9/25/2023 Partial Approval DEROLD HAUFF
Footing/Foundation/Slab 9/25/2023 Approved DEROLD HAUFF
Insulation 9/25/2023 Partial Approval DEROLD HAUFF
Interior/Exterior Lathing 9/25/2023 Approved DEROLD HAUFF
Special/Order Compliance 9/25/2023 Approved DEROLD HAUFF
Green Building Rough 9/27/2023 Partial Inspection CALEB MEISTER
Verify Sprinkler Sign Off 9/27/2023 Partial Inspection CALEB MEISTER
Wood Frame 9/27/2023 Partial Inspection CALEB MEISTER
Insulation 10/20/2023 Approved CALEB MEISTER
Drywall Nailing 10/31/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 12/8/2023 Approved LILIANA PORTILLO
Final 9/16/2024 Corrections Issued JOSE MACIAS
Final 9/30/2024 Not Ready for Inspection JUSTIN HAWLEY
Green Building Rough 9/30/2024 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 9/30/2024 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 9/30/2024 Not Ready for Inspection JUSTIN HAWLEY
Special/Order Compliance 9/30/2024 Corrections Issued JUSTIN HAWLEY
Verify Sprinkler Sign Off 9/30/2024 Not Ready for Inspection JUSTIN HAWLEY
Wood Frame 9/30/2024 Not Ready for Inspection JUSTIN HAWLEY
Green Building Final 10/9/2024 Not Ready for Inspection JUSTIN HAWLEY
Green Building Rough 10/9/2024 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 10/9/2024 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 10/9/2024 Not Ready for Inspection JUSTIN HAWLEY
Special/Order Compliance 10/9/2024 Not Ready for Inspection JUSTIN HAWLEY
Verify Sprinkler Sign Off 10/9/2024 Not Ready for Inspection JUSTIN HAWLEY
Wood Frame 10/9/2024 Not Ready for Inspection JUSTIN HAWLEY
Final 11/27/2024 Not Ready for Inspection JUSTIN HAWLEY
Green Building Final 11/27/2024 Not Ready for Inspection JUSTIN HAWLEY
Green Building Rough 11/27/2024 Not Ready for Inspection JUSTIN HAWLEY
Pre-Inspection 11/27/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 11/27/2024 SGSOV Not Ready JUSTIN HAWLEY
Smoke Detectors 11/27/2024 Not Ready for Inspection JUSTIN HAWLEY
Verify Sprinkler Sign Off 11/27/2024 Not Ready for Inspection JUSTIN HAWLEY
Final 12/3/2024 Corrections Issued JUSTIN HAWLEY
Green Building Final 12/3/2024 Not Ready for Inspection JUSTIN HAWLEY
Green Building Rough 12/3/2024 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 12/3/2024 SGSOV Approved JUSTIN HAWLEY
Smoke Detectors 12/3/2024 Approved JUSTIN HAWLEY
Verify Sprinkler Sign Off 12/3/2024 Approved JUSTIN HAWLEY
Wood Frame 12/3/2024 Approved JUSTIN HAWLEY
Final 12/19/2024 No Access for Inspection JUSTIN HAWLEY
Green Building Final 12/19/2024 No Access for Inspection JUSTIN HAWLEY
Order to Comply 12/19/2024 Not Required JUSTIN HAWLEY
Final 12/27/2024 Corrections Issued JUSTIN HAWLEY
Green Building Final 12/27/2024 Not Ready for Inspection JUSTIN HAWLEY
Final 1/13/2025 Corrections Issued JUSTIN HAWLEY
Green Building Final 1/13/2025 Approved JUSTIN HAWLEY
Final 1/22/2025 Corrections Issued JUSTIN HAWLEY
Final 1/28/2025 OK to Issue CofO JUSTIN HAWLEY