9621 N HAYVENHURST AVE 91343
Certificate Information: 9621 N HAYVENHURST AVE 91343
- Application / Permit
- 22010-20000-00407
- Plan Check / Job No.
- B22VN01286
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DETACHED GARAGE CONVERSION TO ADU.
- Permit Issued
- Issued on 3/6/2022
- Issuing Office
- Current Status
- CofO Issued on 7/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2022 | JOE VO |
| Corrections Issued | 1/30/2022 | JOE VO |
| Plan Check Approved | 2/21/2022 | JOE VO |
| Issued | 3/6/2022 | APPLICANT |
| CofO in Progress | 6/29/2022 | ALAN MORELOS |
| CofO Issued | 7/22/2022 | MICHAEL SMITH |
| Permit Finaled | 7/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/1/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 2/1/2022 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 2/17/2022 | SERGIO VALENZUELA |
Contact Information
| No Data Available. |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/31/2022 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 4/6/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 4/6/2022 | Approved | RAUL OLAGI |
| Sewer | 4/6/2022 | Approved | RAUL OLAGI |
| Underground Mechanical | 4/6/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/19/2022 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 4/19/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 4/19/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 4/19/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 4/19/2022 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 4/19/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/27/2022 | Approved | RAUL OLAGI |
| Insulation | 4/27/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 5/10/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 5/10/2022 | Approved | RAUL OLAGI |
| Shower Pan | 5/10/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 6/14/2022 | Approved | ALAN MORELOS |
| Final | 6/14/2022 | Corrections Issued | ALAN MORELOS |
| Green Building Final | 6/14/2022 | Approved | ALAN MORELOS |
| HVAC-Final | 6/14/2022 | Approved | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 6/14/2022 | SGSOV Approved | ALAN MORELOS |
| Smoke Detectors | 6/14/2022 | Approved | ALAN MORELOS |
| Final | 6/29/2022 | OK to Issue CofO | ALAN MORELOS |
| PLUMBING-Final | 6/29/2022 | Approved | ALAN MORELOS |