12041 W RIALTO ST 91352

Certificate Information: 12041 W RIALTO ST 91352

Application / Permit
22010-20000-00405
Plan Check / Job No.
B22VN01285
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. New 2nd dwelling 2-story unit per SB9 GC Section 65852.21(b)(2)(A) at rear of lot.
Permit Issued
Issued on 1/10/2023
Issuing Office
Current Status
CofO Issued on 1/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2022 APPLICANT
Assigned to Plan Check Engineer 2/24/2022 TU HUA
Corrections Issued 3/8/2022 TU HUA
Quality Review Completed 3/11/2022 SAI KHUM
Applicant returned to address corrections 12/7/2022 TU HUA
Applicant returned to address corrections 12/23/2022 TU HUA
Plan Check Approved 1/6/2023 TU HUA
No Progress 1/10/2023 INTERNET PERMIT
Plan Check Approved 1/10/2023 INTERNET PERMIT
Issued 1/10/2023 APPLICANT
CofO in Progress 1/19/2024 MATTHEW NELSON
Permit Finaled 1/24/2024 RUBEN SALAS
CofO Issued 1/24/2024 RUBEN SALAS
Permit Finaled 1/24/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/19/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/31/2022 CARLOS AGUILERA
Sewer availability Cleared 3/31/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/23/2022 JOSE DUARTE-DIAZ
Clean Up Green Up Cleared 7/25/2022 BRENNEN OBETO
ZI Cleared 7/25/2022 BRENNEN OBETO
ZI Cleared 7/25/2022 BRENNEN OBETO
Low Impact Development Cleared 9/12/2022 MARCO SANCHEZ
Construction near power lines Cleared 10/3/2022 RIDWAN HARDY
Construction within easement Cleared 10/3/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/1/2023 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 2/1/2023 Not Ready for Inspection MATTHEW NELSON
Footing/Foundation/Slab 2/2/2023 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 2/6/2023 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 2/7/2023 Approved MATTHEW NELSON
PLUMBING-Rough 2/7/2023 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 3/16/2023 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 4/20/2023 Not Ready for Inspection MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 4/20/2023 Partial Approval MATTHEW NELSON
HVAC-Rough 4/20/2023 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 4/20/2023 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 4/20/2023 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 4/28/2023 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 4/28/2023 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 4/28/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 5/5/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 5/5/2023 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Rough 5/5/2023 Approved CHRISTOPHER DELLEFIELD
Verify Sprinkler Sign Off 5/5/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 5/11/2023 Approved MATTHEW NELSON
ELECTRICAL-Rough 5/11/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 5/11/2023 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 5/11/2023 Approved MATTHEW NELSON
Insulation 5/17/2023 Approved MATTHEW NELSON
Drywall Nailing 5/26/2023 Approved MATTHEW NELSON
Shower Pan 6/26/2023 Not Ready for Inspection WILLIAM WREN
Shower Pan 6/30/2023 Approved MATTHEW NELSON
ELECTRICAL-Final 11/8/2023 Corrections Issued CHRISTOPHER ROJAS
Final 11/8/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 11/8/2023 Approved CHRISTOPHER ROJAS
HVAC-Final 11/8/2023 Approved CHRISTOPHER ROJAS
PLUMBING-Final 11/8/2023 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 11/8/2023 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 11/8/2023 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 11/8/2023 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 11/14/2023 Approved ROBERT GOLD
Final 11/14/2023 Corrections Issued ROBERT GOLD
PLUMBING-Final 11/14/2023 Not Ready for Inspection ROBERT GOLD
Final 11/29/2023 Not Ready for Inspection MATTHEW NELSON
Gas Test 11/29/2023 Approved MATTHEW NELSON
PLUMBING-Final 11/29/2023 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 11/29/2023 SGSOV Approved MATTHEW NELSON
Service/Power Release 11/29/2023 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 1/8/2024 Approved MATTHEW NELSON
Final 1/8/2024 Corrections Issued MATTHEW NELSON
HVAC-Final 1/8/2024 Approved MATTHEW NELSON
PLUMBING-Final 1/8/2024 Approved MATTHEW NELSON
Service/Power Release 1/8/2024 Not Ready for Inspection MATTHEW NELSON
Final 1/18/2024 OK to Issue CofO MATTHEW NELSON
Service/Power Release 1/18/2024 Approved MATTHEW NELSON