21033 W BASSETT ST 91303

Certificate Information: 21033 W BASSETT ST 91303

Application / Permit
22010-20000-00396
Plan Check / Job No.
B22VN01272
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 20 X 25' DETACHED ACCESSORY DWELLIGN UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/11/2022
Issuing Office
Valley
Current Status
CofO Issued on 6/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/26/2022 APPLICANT
Assigned to Plan Check Engineer 2/4/2022 RAPHAEL ROSAS
Corrections Issued 2/5/2022 RAPHAEL ROSAS
Plan Check Approved 6/14/2022 RAPHAEL ROSAS
Building Plans Picked Up 6/15/2022 APPLICANT
Issued 8/11/2022 APPLICANT
CofO in Progress 5/31/2023 ALEXANDER HANDY
Permit Finaled 6/26/2023 JOHN JANSON
CofO Issued 6/26/2023 JOHN JANSON
Permit Finaled 6/26/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/10/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 2/22/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 3/14/2022 JOSE DUARTE-DIAZ
Low Impact Development Cleared 5/6/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 5/9/2022 JOSE DUARTE-DIAZ
ZI Cleared 5/12/2022 MIGUEL GAMBOA

Contact Information

Contractor Ivy Green Construction; Lic. No.: 1014647-B 14537 VENTURA BLVD      SHERMAN OAKS, CA 91403
Engineer Valencia,, Byron Steve; Lic. No.: C87372 16200 VENTURA BLVD   SUITE 227    ENCINO, CA 91436

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/16/2022 Approved STEVEN BACK
Footing/Foundation/Slab 8/16/2022 Corrections Issued STEVEN BACK
PLUMBING-Rough 8/16/2022 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/19/2022 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 9/19/2022 Not Ready for Inspection STEVEN BACK
Rough-Elec/Plmb/HVAC 9/19/2022 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 9/22/2022 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/22/2022 Not Ready for Inspection STEVEN BACK
Green Building Rough 9/22/2022 Not Ready for Inspection STEVEN BACK
Rough-Elec/Plmb/HVAC 9/22/2022 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 10/3/2022 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 10/3/2022 Partial Approval JOHN KIDWELL
Green Building Rough 10/3/2022 Partial Approval JOHN KIDWELL
Rough-Elec/Plmb/HVAC 10/3/2022 Partial Approval JOHN KIDWELL
Interior/Exterior Lathing 10/7/2022 Partial Inspection JUSTIN HAWLEY
BUILDING-Rough-Frame 10/13/2022 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 10/13/2022 Not Ready for Inspection STEVEN BACK
Green Building Rough 10/13/2022 Not Ready for Inspection STEVEN BACK
HVAC-Rough 10/13/2022 Corrections Issued STEVEN BACK
Insulation 10/13/2022 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 10/13/2022 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 10/24/2022 Approved JEFFREY BULL
Green Building Rough 10/24/2022 Approved JEFFREY BULL
Interior/Exterior Lathing 10/24/2022 Partial Approval JEFFREY BULL
Rough-Elec/Plmb/HVAC 10/24/2022 Approved JEFFREY BULL
Insulation 10/31/2022 Corrections Issued STEVEN BACK
Drywall Nailing 11/7/2022 Approved KRISTEN CAUSEY
Insulation 11/7/2022 Approved KRISTEN CAUSEY
Final 5/16/2023 Corrections Issued ALEXANDER HANDY
Footing/Foundation/Slab 5/16/2023 Not Ready for Inspection ALEXANDER HANDY
Green Building Final 5/16/2023 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 5/16/2023 SGSOV Approved ALEXANDER HANDY
Service/Power Release 5/16/2023 Not Ready for Inspection ALEXANDER HANDY
Smoke Detectors 5/16/2023 Approved ALEXANDER HANDY
ELECTRICAL-Final 5/30/2023 Approved ALEXANDER HANDY
Final 5/30/2023 OK to Issue CofO ALEXANDER HANDY
Footing/Foundation/Slab 5/30/2023 Approved ALEXANDER HANDY
Green Building Final 5/30/2023 Approved ALEXANDER HANDY
HVAC-Final 5/30/2023 Approved ALEXANDER HANDY
PLUMBING-Final 5/30/2023 Approved ALEXANDER HANDY
Service/Power Release 5/30/2023 Approved ALEXANDER HANDY