3521 N GALENA ST 90032
Certificate Information: 3521 N GALENA ST 90032
- Application / Permit
- 22010-20000-00392
- Plan Check / Job No.
- B22VN01247
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 13'-7" x 24' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Valley
- Current Status
- Issued on 1/23/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 2/5/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 2/9/2022 | APPLICANT |
| Applicant returned to address corrections | 1/6/2023 | MADISON ODELL |
| Issued | 1/23/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/14/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 2/14/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 2/24/2022 | CHRISTOPHER ROCHA |
| Grading Pre-Inspection | Cleared | 1/6/2023 | MADISON ODELL |
| "D" conditions | Cleared | 1/11/2023 | DALIA MOKAYED |
| "Q" conditions | Cleared | 1/11/2023 | DALIA MOKAYED |
| ZI | Cleared | 1/11/2023 | DALIA MOKAYED |
Contact Information
| Contractor | Del Builders Inc; Lic. No.: 1060645-B | 15260 VENTURA BLVD STE 1200 SHERMAN OAKS, CA 91403 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/10/2023 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 5/8/2023 | Partial Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 5/26/2023 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/26/2023 | Approved | OSVALDO PARAMO |
| Wood Frame | 5/26/2023 | Partial Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/8/2023 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 6/8/2023 | Approved | OSVALDO PARAMO |
| Wood Frame | 6/8/2023 | Conditional Approval | OSVALDO PARAMO |
| Interior/Exterior Lathing | 6/15/2023 | Partial Approval | OSVALDO PARAMO |
| Shower Pan | 6/15/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| Insulation | 6/22/2023 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 6/22/2023 | Approved | OSVALDO PARAMO |
| Shower Pan | 6/22/2023 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 6/28/2023 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/31/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 7/31/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 7/31/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 7/31/2024 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/31/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Service/Power Release | 7/31/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 7/31/2024 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 7/31/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/19/2024 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 8/19/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 8/19/2024 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 8/19/2024 | Approved | OSVALDO PARAMO |