6506 N WHITE OAK AVE 91406
Certificate Information: 6506 N WHITE OAK AVE 91406
- Application / Permit
- 22010-20000-00391
- Plan Check / Job No.
- B22VN01236
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADU WITH ATT. 2-CAR GARAGE. ADU PER LAMC 12.22 A.33 (c) & (d)
- Permit Issued
- Issued on 3/8/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/1/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | ADRIANA LOPEZ |
| Corrections Issued | 3/3/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 3/3/2022 | SEAN DANG |
| Building Plans Picked Up | 3/8/2022 | APPLICANT |
| Plan Check Approved | 2/27/2023 | ADRIANA LOPEZ |
| No Progress | 2/27/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 2/27/2023 | ADRIANA LOPEZ |
| Issued | 3/8/2023 | APPLICANT |
| CofO in Progress | 12/14/2023 | JON MCHUGH |
| Permit Finaled | 2/1/2024 | JOHN JANSON |
| CofO Issued | 2/1/2024 | JOHN JANSON |
| Permit Finaled | 2/1/2024 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 4/19/2022 | RIDWAN HARDY |
| Address approval | Cleared | 5/5/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 5/9/2022 | MEGAN GODINEZ |
| ZI | Cleared | 1/18/2023 | NELSON RODRIGUEZ |
| Low Impact Development | Cleared | 2/9/2023 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 2/21/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 450 NORTH BRAND BLVD STE 600 GLENDALE, CA 91203 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/1/2023 | Not Ready for Inspection | JON MCHUGH |
| Excavation/Setback/Form/Re-Bar | 5/3/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 5/16/2023 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Partial Approval | JEFFREY BULL |
| Insulation | 5/22/2023 | Partial Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2023 | Partial Approval | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2023 | Corrections Issued | JON MCHUGH |
| BUILDING-Rough-Frame | 8/8/2023 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Rough | 8/8/2023 | Corrections Issued | JON MCHUGH |
| Final | 8/8/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 8/8/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 8/8/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 8/8/2023 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 8/8/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 8/18/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 8/18/2023 | Approved | JON MCHUGH |
| Green Building Rough | 8/18/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 8/18/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 8/18/2023 | Approved | JON MCHUGH |
| Green Building Rough | 8/29/2023 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 8/29/2023 | Partial Approval | JUSTIN HAWLEY |
| Insulation | 9/6/2023 | Corrections Issued | JUSTIN HAWLEY |
| Drywall Nailing | 9/13/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 9/29/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 9/29/2023 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/12/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 10/12/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 10/17/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 12/6/2023 | Corrections Issued | JON MCHUGH |
| Final | 12/6/2023 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 12/6/2023 | Approved | JON MCHUGH |
| Green Building Final | 12/6/2023 | Approved | JON MCHUGH |
| HVAC-Final | 12/6/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 12/6/2023 | Corrections Issued | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 12/6/2023 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 12/6/2023 | Not Ready for Inspection | JON MCHUGH |
| Smoke Detectors | 12/6/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Final | 12/13/2023 | Approved | JON MCHUGH |
| Final | 12/13/2023 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 12/13/2023 | Approved | JON MCHUGH |
| PLUMBING-Final | 12/13/2023 | Approved | JON MCHUGH |
| Service/Power Release | 12/13/2023 | Approved | JON MCHUGH |
| Smoke Detectors | 12/13/2023 | Approved | JON MCHUGH |