6100 W 75TH PL 90045
Certificate Information: 6100 W 75TH PL 90045
- Application / Permit
- 22010-20000-00361
- Plan Check / Job No.
- B22VN01131
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD WITH ATTACHED 2-CAR GARAGE.
- Permit Issued
- Issued on 10/17/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | ADRIANA LOPEZ |
| Corrections Issued | 3/4/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 3/9/2022 | SEAN DANG |
| Building Plans Picked Up | 3/21/2022 | APPLICANT |
| Applicant returned to address corrections | 6/28/2022 | ADRIANA LOPEZ |
| Plan Check Approved | 9/6/2022 | ADRIANA LOPEZ |
| Issued | 10/17/2022 | APPLICANT |
| CofO in Progress | 3/17/2025 | JESUS PINEDA |
| Permit Finaled | 3/17/2025 | RICHARD STEINBACH |
| CofO Issued | 3/17/2025 | RICHARD STEINBACH |
| Permit Finaled | 3/17/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/18/2022 | PEDRO AYALA |
| Disturb/Remove Protected Trees | Cleared | 6/22/2022 | ADALBERTO VERA |
| Trees in Parkway | Cleared | 6/22/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 6/23/2022 | LAVEON RIDER |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 7/18/2022 | CATHERINE ADROVER |
| Low Impact Development | Cleared | 8/10/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 8/11/2022 | CATHERINE ADROVER |
| GPI Written Notices | Cleared | 8/17/2022 | ADRIANA LOPEZ |
| Grading Pre-Inspection | Cleared | 8/17/2022 | ADRIANA LOPEZ |
Contact Information
| Contractor | Sweiskloss Inc; Lic. No.: 766542-B | 1424 4TH STREET SUITE 501 SANTA MONICA, CA 90401 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/20/2022 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 12/20/2022 | Corrections Issued | BOBBY KEY |
| Deputy Reinf. Concrete | 12/21/2022 | Conditional Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 12/22/2022 | Conditional Approval | DAVID FEILER |
| Footing/Foundation/Slab | 12/22/2022 | Conditional Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 12/23/2022 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 12/23/2022 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2023 | Partial Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 3/28/2023 | Conditional Approval | BOBBY KEY |
| Deputy Wood Construction | 4/7/2023 | Conditional Approval | JESUS PINEDA |
| Deputy Wood Construction | 4/27/2023 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2023 | Partial Approval | BOBBY KEY |
| Deputy Drilled-In Anchors | 6/6/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 6/6/2023 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 7/5/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 7/24/2023 | Partial Approval | BOBBY KEY |
| Insulation | 7/24/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 9/11/2023 | Conditional Approval | RICHARD STEINBACH |
| ELECTRICAL-Rough | 9/22/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 9/22/2023 | Approved | BOBBY KEY |
| Shower Pan | 10/5/2023 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 10/12/2023 | Approved | BOBBY KEY |
| Green Building Rough | 10/12/2023 | Approved | BOBBY KEY |
| Insulation | 10/12/2023 | Partial Approval | BOBBY KEY |
| Verify Sprinkler Sign Off | 10/12/2023 | Approved | BOBBY KEY |
| Insulation | 10/18/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 10/30/2023 | Partial Approval | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 10/30/2023 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 11/27/2023 | Approved | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 12/7/2023 | Approved | BOBBY KEY |
| Gas Test | 3/15/2024 | Partial Approval | BOBBY KEY |
| Sewer | 3/15/2024 | Approved | BOBBY KEY |
| Underground Mechanical | 3/15/2024 | Partial Approval | BOBBY KEY |
| Gas Test | 6/18/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 6/18/2024 | Partial Approval | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/18/2024 | SGSOV Approved | BOBBY KEY |
| HVAC-Final | 6/27/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 6/27/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 7/15/2024 | Partial Approval | BOBBY KEY |
| Green Building Final | 7/15/2024 | Approved | BOBBY KEY |
| Smoke Detectors | 7/15/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 7/29/2024 | Approved | BOBBY KEY |
| Final | 7/31/2024 | Corrections Issued | BOBBY KEY |
| Final | 3/17/2025 | OK to Issue CofO | JESUS PINEDA |
| Service/Power Release | 3/17/2025 | Approved | JESUS PINEDA |