5065 N WOODLEY AVE 91436
Certificate Information: 5065 N WOODLEY AVE 91436
- Application / Permit
- 22010-20000-00345
- Plan Check / Job No.
- B22VN01062
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ONE STORY ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 9/23/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | ERIC WONG |
| Corrections Issued | 2/12/2022 | ERIC WONG |
| Quality Review Completed | 2/16/2022 | KEN GILL |
| Applicant returned to address corrections | 7/12/2022 | ERIC WONG |
| Applicant returned to address corrections | 9/2/2022 | ERIC WONG |
| Plan Check Approved | 9/23/2022 | ERIC WONG |
| Issued | 9/23/2022 | APPLICANT |
| CofO in Progress | 7/21/2024 | THOMAS FINNILA |
| Permit Finaled | 4/15/2025 | JOHN JANSON |
| CofO Issued | 4/15/2025 | JOHN JANSON |
| Permit Finaled | 4/15/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/23/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/23/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/23/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 4/19/2022 | LAURINDA MEADE |
| Low Impact Development | Cleared | 7/22/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 8/5/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/20/2023 | Partial Approval | VINCENT HANLEY |
| Sewer | 4/20/2023 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 5/3/2023 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 5/3/2023 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 5/3/2023 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 5/5/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2023 | Partial Approval | VINCENT HANLEY |
| Deputy Other (see comments) | 6/23/2023 | Conditional Approval | JOHN JANSON |
| HVAC-Rough | 7/31/2023 | Approved | VINCENT HANLEY |
| Shower Pan | 8/3/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 8/9/2023 | Approved | VINCENT HANLEY |
| Wood Frame | 8/9/2023 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 8/10/2023 | Partial Approval | VINCENT HANLEY |
| Insulation | 9/20/2023 | Approved | VINCENT HANLEY |
| Drywall Nailing | 10/6/2023 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 4/18/2024 | Approved | VINCENT HANLEY |
| HVAC-Final | 4/19/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/20/2024 | Approved | THOMAS FINNILA |
| Final | 5/20/2024 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 5/20/2024 | Approved | THOMAS FINNILA |
| Green Building Rough | 5/20/2024 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 5/20/2024 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 5/20/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 5/20/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 5/20/2024 | Approved | THOMAS FINNILA |
| Final | 7/1/2024 | Corrections Issued | THOMAS FINNILA |
| Service/Power Release | 7/1/2024 | Approved | THOMAS FINNILA |
| Smoke Detectors | 7/1/2024 | Approved | THOMAS FINNILA |
| Final | 7/18/2024 | OK to Issue CofO | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Special/Order Compliance | 10/30/2024 | Corrections Issued | THOMAS FINNILA |