5067 N WOODLEY AVE 91436

Certificate Information: 5067 N WOODLEY AVE 91436

Application / Permit
22010-20000-00344
Plan Check / Job No.
B22VN01062
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SINGLE FAMILY DWELLING WITH BASEMENT. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 9/23/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/24/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 ERIC WONG
Corrections Issued 2/12/2022 ERIC WONG
Quality Review Completed 2/16/2022 KEN GILL
Applicant returned to address corrections 7/12/2022 ERIC WONG
Applicant returned to address corrections 9/2/2022 ERIC WONG
Plan Check Approved 9/23/2022 ERIC WONG
Issued 9/23/2022 APPLICANT
CofO in Progress 7/2/2024 THOMAS FINNILA
CofO in Progress 8/5/2024 SEAN WIRCH
CofO Issued 9/30/2024 JOHN JANSON
Permit Finaled 9/30/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/23/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/23/2022 CARLOS AGUILERA
Sewer availability Cleared 3/23/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 4/19/2022 LAURINDA MEADE
Low Impact Development Cleared 7/22/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/5/2022 CARLOS AGUILERA
Permit Cleared 9/6/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/28/2022 Approved VINCENT HANLEY
PLUMBING-Rough 10/18/2022 Partial Approval VINCENT HANLEY
Underground Mechanical 10/18/2022 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 10/25/2022 Not Ready for Inspection DAVID SANDOVAL
Pre-Inspection 10/25/2022 Approved DAVID SANDOVAL
Special/Order Compliance 10/26/2022 Corrections Issued SEAN WIRCH
Deputy Other (see comments) 11/7/2022 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 11/9/2022 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 11/9/2022 Partial Approval VINCENT HANLEY
Deputy Reinf. Concrete 11/10/2022 Approved VINCENT HANLEY
Deputy Other (see comments) 11/22/2022 Approved VINCENT HANLEY
Reinforced Concrete Frame 11/22/2022 Partial Approval VINCENT HANLEY
Reinforced Concrete Frame 12/5/2022 Approved VINCENT HANLEY
Deputy Reinf. Concrete 12/6/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/17/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/17/2023 Partial Approval VINCENT HANLEY
Green Building Rough 4/17/2023 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 4/17/2023 Not Ready for Inspection VINCENT HANLEY
Deputy Steel/Welding 4/26/2023 Approved VINCENT HANLEY
Deputy Reinf. Concrete 5/3/2023 Approved VINCENT HANLEY
Deputy Reinf. Concrete 5/5/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/9/2023 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/9/2023 Partial Approval VINCENT HANLEY
Green Building Rough 5/9/2023 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 5/9/2023 Not Ready for Inspection VINCENT HANLEY
Wood Frame 5/9/2023 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 6/6/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Approved VINCENT HANLEY
PLUMBING-Rough 7/14/2023 Approved VINCENT HANLEY
Sewer 7/14/2023 Approved VINCENT HANLEY
HVAC-Rough 7/31/2023 Approved VINCENT HANLEY
Shower Pan 8/3/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 8/9/2023 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 8/9/2023 Approved VINCENT HANLEY
Green Building Rough 8/9/2023 Not Ready for Inspection VINCENT HANLEY
Verify Sprinkler Sign Off 8/9/2023 Approved VINCENT HANLEY
Wood Frame 8/9/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/10/2023 Partial Approval VINCENT HANLEY
HVAC-Rough 8/16/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 8/16/2023 Approved VINCENT HANLEY
Insulation 9/20/2023 Approved VINCENT HANLEY
Drywall Nailing 10/6/2023 Approved JOHN KIDWELL
ELECTRICAL-Final 4/18/2024 Approved VINCENT HANLEY
PLUMBING-Final 4/18/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/19/2024 Approved VINCENT HANLEY
Final 4/19/2024 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 4/19/2024 Approved VINCENT HANLEY
Green Building Final 4/19/2024 Approved VINCENT HANLEY
Green Building Rough 4/19/2024 Approved VINCENT HANLEY
HVAC-Final 4/19/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 4/19/2024 SGSOV Approved VINCENT HANLEY
Service/Power Release 4/19/2024 Approved VINCENT HANLEY
Smoke Detectors 4/19/2024 Approved VINCENT HANLEY
Final 5/20/2024 Corrections Issued THOMAS FINNILA
Final 6/18/2024 Corrections Issued MORRIS JACKSON
Final 7/1/2024 OK to Issue CofO THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 7/9/2024 Not Ready for Inspection THOMAS FINNILA