9607 W CRESTA DR 90035
Certificate Information: 9607 W CRESTA DR 90035
- Application / Permit
- 22010-20000-00334
- Plan Check / Job No.
- B22VN01030
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD WITH GARAGE, BASEMENT AND ELEVATOR. ROOF DECK ON TOP
- Permit Issued
- Issued on 6/1/2022
- Issuing Office
- Current Status
- CofO Issued on 7/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/24/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 3/2/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 3/9/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| Plan Check Approved | 5/20/2022 | MAHNAZ NOURHASHEMI |
| Issued | 6/1/2022 | APPLICANT |
| CofO in Progress | 7/13/2023 | CLAYTON GRAHAM |
| Permit Finaled | 7/19/2023 | DANIEL ORRANTE |
| CofO Issued | 7/19/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/19/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 3/24/2022 | JOSE HERNANDEZ |
| Trees in Parkway | Cleared | 4/6/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 4/26/2022 | DWIGHT SANKEY |
| Low Impact Development | Cleared | 5/10/2022 | SARAH YOUSSEF |
| Permit | Cleared | 5/16/2022 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 5/16/2022 | ANTHONY MAINEZ |
| Excavation more than 5-ft deep | Cleared | 5/20/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 5/20/2022 | MAHNAZ NOURHASHEMI |
| Grading Pre-Inspection | Cleared | 5/20/2022 | MAHNAZ NOURHASHEMI |
Contact Information
| Contractor | Di Nalli Construction; Lic. No.: 942979-B | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Engineer | Askarian,, Soroosh; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/20/2022 | Partial Approval | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 7/21/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| METHANE-Rough | 7/22/2022 | Approved | OGANES TARAKHCHYAN |
| Deputy Methane Barrier | 7/27/2022 | Approved | MICHAEL PELHAM |
| METHANE-Barrier | 7/28/2022 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 8/1/2022 | Partial Approval | EVAN COOPER |
| METHANE-Subgrade | 8/1/2022 | Approved | EVAN COOPER |
| Reinforced Concrete Frame | 8/11/2022 | Partial Approval | EVAN COOPER |
| Deputy Shotcrete | 8/22/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Methane Barrier | 10/6/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Methane Barrier | 10/7/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/11/2022 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 12/14/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 12/30/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 12/30/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 1/5/2023 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 1/5/2023 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/9/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/11/2023 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/12/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 1/12/2023 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 1/12/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 1/12/2023 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/19/2023 | Approved | RICHARD STEINBACH |
| HVAC-Rough | 1/19/2023 | Approved | RICHARD STEINBACH |
| Verify Sprinkler Sign Off | 1/19/2023 | Approved | RICHARD STEINBACH |
| Insulation | 1/24/2023 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 1/26/2023 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 1/26/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Drywall Nailing | 2/1/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 2/1/2023 | Approved | JEREMY TODD |
| Shower Pan | 2/1/2023 | Approved | JEREMY TODD |
| Special/Order Compliance | 2/1/2023 | Not Ready for Inspection | JEREMY TODD |
| ELECTRICAL-Final | 5/9/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Final | 5/11/2023 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Final | 5/16/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Final | 5/16/2023 | Approved | CLAYTON GRAHAM |
| Service/Power Release | 5/17/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Final | 6/6/2023 | Approved | JESUS PINEDA |
| Final | 6/27/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Final | 6/27/2023 | Approved | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Approved | CLAYTON GRAHAM |
| Smoke Detectors | 6/27/2023 | Corrections Issued | CLAYTON GRAHAM |
| Final | 7/12/2023 | OK to Issue CofO | CLAYTON GRAHAM |
| Smoke Detectors | 7/12/2023 | Approved | CLAYTON GRAHAM |