1609 W 64TH ST 90047
Certificate Information: 1609 W 64TH ST 90047
- Application / Permit
- 22010-20000-00276
- Plan Check / Job No.
- B22VN00822
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW TWO STORY ACCESSORY DWELLING UNIT WITH ATTACHED GARAGE PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g)
- Permit Issued
- Issued on 1/26/2024
- Issuing Office
- Valley
- Current Status
- Issued on 1/26/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | SELLA BENYAMIN |
| Corrections Issued | 2/24/2022 | SELLA BENYAMIN |
| Quality Review Completed | 3/1/2022 | STEVEN KIM |
| Building Plans Picked Up | 3/2/2022 | APPLICANT |
| Applicant returned to address corrections | 11/2/2023 | SELLA BENYAMIN |
| Applicant returned to address corrections | 1/11/2024 | SELLA BENYAMIN |
| Plan Check Approved | 1/26/2024 | SELLA BENYAMIN |
| Issued | 1/26/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/21/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 3/22/2022 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 7/24/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/27/2023 | NEIL TUANO |
| Construction near power lines | Cleared | 9/27/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng D; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/11/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 4/15/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 4/15/2024 | Corrections Issued | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 4/17/2024 | Approved | CRAIG DAVIS |
| PLUMBING-Rough | 4/17/2024 | Partial Approval | CRAIG DAVIS |
| BUILDING-Rough-Frame | 6/10/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Green Building Rough | 6/10/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 6/10/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 7/9/2024 | Corrections Issued | CRAIG DAVIS |
| ELECTRICAL-Rough | 7/9/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 7/9/2024 | Not Ready for Inspection | CRAIG DAVIS |
| HVAC-Rough | 7/9/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 7/9/2024 | Corrections Issued | CRAIG DAVIS |
| Verify Sprinkler Sign Off | 7/9/2024 | Not Ready for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 7/26/2024 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 7/26/2024 | Approved | DAVID FEILER |
| Green Building Rough | 7/26/2024 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 7/26/2024 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 7/26/2024 | Not Ready for Inspection | DAVID FEILER |
| Verify Sprinkler Sign Off | 7/26/2024 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 8/8/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 8/8/2024 | Corrections Issued | CRAIG DAVIS |
| HVAC-Rough | 8/8/2024 | Corrections Issued | CRAIG DAVIS |
| Interior/Exterior Lathing | 8/8/2024 | Corrections Issued | CRAIG DAVIS |
| PLUMBING-Rough | 8/8/2024 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 8/12/2024 | Corrections Issued | CRAIG DAVIS |
| Green Building Rough | 8/12/2024 | Corrections Issued | CRAIG DAVIS |
| Interior/Exterior Lathing | 8/12/2024 | Corrections Issued | CRAIG DAVIS |
| Deputy Wood Construction | 8/13/2024 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 8/23/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 8/23/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 8/23/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/27/2024 | Approved | CRAIG DAVIS |
| Insulation | 8/27/2024 | Approved | CRAIG DAVIS |
| Drywall Nailing | 9/16/2024 | Partial Approval | CRAIG DAVIS |
| Shower Pan | 9/16/2024 | Corrections Issued | CRAIG DAVIS |
| Shower Pan | 9/23/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 10/4/2024 | Approved | CRAIG DAVIS |
| Service/Power Release | 2/14/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 2/21/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Final | 2/21/2025 | Corrections Issued | LUIS CASTRO |
| Service/Power Release | 3/4/2025 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 3/12/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Final | 3/12/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 3/20/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Final | 3/20/2025 | Not Ready for Inspection | BARRY HACHE |