8614 N LEHIGH AVE 91352
Certificate Information: 8614 N LEHIGH AVE 91352
- Application / Permit
- 22010-20000-00268
- Plan Check / Job No.
- B22VN00793
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan New Detached ADU 42' by 29'-9" per Ordinance
- Permit Issued
- Issued on 7/20/2022
- Issuing Office
- Current Status
- CofO Issued on 4/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 1/30/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/8/2022 | SAI KHUM |
| Applicant returned to address corrections | 6/21/2022 | ARSALAN SHABESTARI |
| Plan Check Approved | 7/11/2022 | ARSALAN SHABESTARI |
| Issued | 7/20/2022 | APPLICANT |
| CofO in Progress | 3/22/2023 | DAVID ANDERSON |
| Permit Finaled | 4/5/2023 | DANIEL ORRANTE |
| CofO Issued | 4/5/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/5/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/15/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2022 | JOSE DUARTE-DIAZ |
| ZI | Cleared | 3/1/2022 | PABLO ESTRADA |
| Low Impact Development | Cleared | 5/23/2022 | SARAH YOUSSEF |
| Sewer availability | Cleared | 5/24/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 5/31/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/11/2022 | Approved | DAVID ANDERSON |
| Underground Mechanical | 8/22/2022 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 8/31/2022 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/3/2022 | Corrections Issued | DAVID ANDERSON |
| Green Building Rough | 10/3/2022 | Not Ready for Inspection | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 10/3/2022 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 11/21/2022 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Approved | DAVID ANDERSON |
| Green Building Rough | 11/21/2022 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 11/21/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 11/28/2022 | Approved | DAVID ANDERSON |
| Insulation | 12/1/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 12/7/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 12/19/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 12/27/2022 | Approved | DAVID ANDERSON |
| Sewer | 1/20/2023 | Approved | DAVID ANDERSON |
| Underground Mechanical | 1/20/2023 | Partial Approval | DAVID ANDERSON |
| Underground Mechanical | 1/27/2023 | Approved | DAVID ANDERSON |
| Final | 3/13/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 3/13/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 3/13/2023 | SGSOV Approved | DAVID ANDERSON |
| Service/Power Release | 3/13/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 3/13/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 3/21/2023 | Approved | DAVID ANDERSON |
| Final | 3/21/2023 | OK to Issue CofO | DAVID ANDERSON |
| Service/Power Release | 3/21/2023 | Approved | DAVID ANDERSON |