7507 N BALBOA BLVD 91406
Certificate Information: 7507 N BALBOA BLVD 91406
- Application / Permit
- 22010-20000-00267
- Plan Check / Job No.
- B22VN00792
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY ACCESSORY DWELLNG UNIT (20'-0"x25'-0" ) PER LAMC 12.22 A.33 (c)-(d); The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy. "COMPLY WITH DEPARTMENT ORDER effective date 05/21/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 8/10/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/14/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 2/15/2022 | OMID HEDAYAT |
| Applicant returned to address corrections | 3/10/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 3/21/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 8/11/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 1/4/2023 | MOHAMMAD ESMAILI |
| Issued | 8/10/2023 | APPLICANT |
| CofO in Progress | 10/17/2024 | MICKEY YAMASHITA |
| Permit Finaled | 11/18/2024 | DAVID JAMES |
| CofO Issued | 11/18/2024 | DAVID JAMES |
| Permit Finaled | 11/18/2024 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 3/7/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/8/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 3/14/2022 | CARLOS AGUILERA |
| Construction within easement | Cleared | 3/21/2022 | JOHN BACON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/14/2023 | Approved | MICKEY YAMASHITA |
| PLUMBING-Rough | 10/10/2023 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 10/23/2023 | Not Ready for Inspection | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 10/30/2023 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 11/7/2023 | Conditional Approval | MICKEY YAMASHITA |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2023 | Partial Approval | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 11/28/2023 | Approved | MICKEY YAMASHITA |
| Wood Frame | 11/28/2023 | Partial Approval | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 12/19/2023 | Conditional Approval | MICKEY YAMASHITA |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2023 | Conditional Approval | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 1/9/2024 | Corrections Issued | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 1/9/2024 | Corrections Issued | MICKEY YAMASHITA |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2024 | Approved | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 1/18/2024 | Corrections Issued | MICKEY YAMASHITA |
| Interior/Exterior Lathing | 1/18/2024 | Corrections Issued | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 3/11/2024 | Approved | MICKEY YAMASHITA |
| HVAC-Rough | 3/11/2024 | Corrections Issued | MICKEY YAMASHITA |
| PLUMBING-Rough | 3/11/2024 | Partial Approval | MICKEY YAMASHITA |
| Sewer | 3/14/2024 | Conditional Approval | MICKEY YAMASHITA |
| HVAC-Rough | 3/20/2024 | Conditional Approval | MICKEY YAMASHITA |
| Sewer | 3/20/2024 | Not Ready for Inspection | MICKEY YAMASHITA |
| Wood Frame | 3/20/2024 | Approved | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 3/27/2024 | Partial Approval | MICKEY YAMASHITA |
| ELECTRICAL-Rough | 3/27/2024 | Approved | MICKEY YAMASHITA |
| Green Building Rough | 3/27/2024 | Approved | MICKEY YAMASHITA |
| HVAC-Rough | 3/27/2024 | Approved | MICKEY YAMASHITA |
| Insulation | 3/27/2024 | Approved | MICKEY YAMASHITA |
| PLUMBING-Rough | 3/27/2024 | Approved | MICKEY YAMASHITA |
| Sewer | 3/27/2024 | Approved | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 4/4/2024 | Corrections Issued | MICKEY YAMASHITA |
| Drywall Nailing | 4/4/2024 | Approved | MICKEY YAMASHITA |
| BUILDING-Rough-Frame | 6/10/2024 | Approved | MICKEY YAMASHITA |
| Final | 6/10/2024 | Corrections Issued | MICKEY YAMASHITA |
| Green Building Final | 6/10/2024 | Approved | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 6/10/2024 | SGSOV Not Ready | MICKEY YAMASHITA |
| Service/Power Release | 6/10/2024 | Conditional Approval | MICKEY YAMASHITA |
| Smoke Detectors | 6/10/2024 | Corrections Issued | MICKEY YAMASHITA |
| Verify Sprinkler Sign Off | 6/10/2024 | Approved | MICKEY YAMASHITA |
| Final | 6/20/2024 | Corrections Issued | MICKEY YAMASHITA |
| SGSOV-Seismic Gas S/O Valve | 6/20/2024 | SGSOV Approved | MICKEY YAMASHITA |
| Service/Power Release | 6/20/2024 | Approved | MICKEY YAMASHITA |
| Smoke Detectors | 6/20/2024 | Not Ready for Inspection | MICKEY YAMASHITA |
| Final | 6/27/2024 | Corrections Issued | MICKEY YAMASHITA |
| Smoke Detectors | 6/27/2024 | Approved | MICKEY YAMASHITA |
| Final | 7/1/2024 | Partial Approval | MICKEY YAMASHITA |
| Final | 8/5/2024 | Corrections Issued | MICKEY YAMASHITA |
| Final | 10/17/2024 | OK to Issue CofO | MICKEY YAMASHITA |