20746 W BLACKHAWK ST 91311

Certificate Information: 20746 W BLACKHAWK ST 91311

Application / Permit
22010-20000-00265
Plan Check / Job No.
B21VN18194
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 8/29/2022
Issuing Office
Current Status
CofO Issued on 2/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/23/2022 APPLICANT
Assigned to Plan Check Engineer 3/3/2022 LAMAR DAVIS
Corrections Issued 3/7/2022 LAMAR DAVIS
Quality Review Completed 3/11/2022 HERNAN ARREOLA
Applicant returned to address corrections 8/9/2022 LAMAR DAVIS
Plan Check Approved 8/18/2022 LAMAR DAVIS
Issued 8/29/2022 APPLICANT
CofO in Progress 2/14/2024 DAVID SCANTLIN
Permit Finaled 2/27/2024 JOHN JANSON
CofO Issued 2/27/2024 JOHN JANSON

Permit Application Clearance Information

Low Impact Development Cleared 7/26/2022 JULIAN SUNG
Address approval Cleared 7/27/2022 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 7/27/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/28/2022 LEE GUILBEAUX
Sewer availability Cleared 7/28/2022 LEE GUILBEAUX
Grading Pre-Inspection Cleared 8/3/2022 KIRK LINKLATER
GPI Written Notices Cleared 8/9/2022 TIMOTHY POWELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/13/2022 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 10/25/2022 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 11/18/2022 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 1/17/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 1/23/2023 Approved DAVID SCANTLIN
Green Building Rough 1/23/2023 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 1/23/2023 Approved DAVID SCANTLIN
PLUMBING-Rough 1/23/2023 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 1/23/2023 Approved DAVID SCANTLIN
Drywall Nailing 2/7/2023 Approved MORRIS JACKSON
Green Building Rough 2/7/2023 Approved MORRIS JACKSON
Insulation 2/7/2023 Approved MORRIS JACKSON
Interior/Exterior Lathing 2/7/2023 Partial Approval MORRIS JACKSON
BUILDING-Rough-Frame 2/15/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 3/24/2023 Approved DAVID SCANTLIN
Shower Pan 3/24/2023 Approved DAVID SCANTLIN
Special/Order Compliance 3/24/2023 Partial Inspection JUSTIN HAWLEY
Final 9/22/2023 Corrections Issued DAVID SCANTLIN
Green Building Final 9/22/2023 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 9/22/2023 SGSOV Approved DAVID SCANTLIN
Service/Power Release 9/22/2023 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 9/22/2023 Not Ready for Inspection DAVID SCANTLIN
Final 10/13/2023 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 10/13/2023 Approved DAVID SCANTLIN
Service/Power Release 10/13/2023 Approved DAVID SCANTLIN
Smoke Detectors 10/13/2023 Approved DAVID SCANTLIN
Final 1/10/2024 Not Ready for Inspection DAVID SCANTLIN
Final 2/14/2024 OK to Issue CofO DAVID SCANTLIN