20746 W BLACKHAWK ST 91311
Certificate Information: 20746 W BLACKHAWK ST 91311
- Application / Permit
- 22010-20000-00265
- Plan Check / Job No.
- B21VN18194
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Current Status
- CofO Issued on 2/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/3/2022 | LAMAR DAVIS |
| Corrections Issued | 3/7/2022 | LAMAR DAVIS |
| Quality Review Completed | 3/11/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 8/9/2022 | LAMAR DAVIS |
| Plan Check Approved | 8/18/2022 | LAMAR DAVIS |
| Issued | 8/29/2022 | APPLICANT |
| CofO in Progress | 2/14/2024 | DAVID SCANTLIN |
| Permit Finaled | 2/27/2024 | JOHN JANSON |
| CofO Issued | 2/27/2024 | JOHN JANSON |
Permit Application Clearance Information
| Low Impact Development | Cleared | 7/26/2022 | JULIAN SUNG |
| Address approval | Cleared | 7/27/2022 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 7/27/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/28/2022 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 8/3/2022 | KIRK LINKLATER |
| GPI Written Notices | Cleared | 8/9/2022 | TIMOTHY POWELL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/13/2022 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 10/25/2022 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2022 | Partial Approval | DAVID SCANTLIN |
| ELECTRICAL-Rough | 1/17/2023 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 1/23/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 1/23/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Rough | 1/23/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 1/23/2023 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 1/23/2023 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 2/7/2023 | Approved | MORRIS JACKSON |
| Green Building Rough | 2/7/2023 | Approved | MORRIS JACKSON |
| Insulation | 2/7/2023 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 2/7/2023 | Partial Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 2/15/2023 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 3/24/2023 | Approved | DAVID SCANTLIN |
| Shower Pan | 3/24/2023 | Approved | DAVID SCANTLIN |
| Special/Order Compliance | 3/24/2023 | Partial Inspection | JUSTIN HAWLEY |
| Final | 9/22/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 9/22/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 9/22/2023 | SGSOV Approved | DAVID SCANTLIN |
| Service/Power Release | 9/22/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 9/22/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 10/13/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 10/13/2023 | Approved | DAVID SCANTLIN |
| Service/Power Release | 10/13/2023 | Approved | DAVID SCANTLIN |
| Smoke Detectors | 10/13/2023 | Approved | DAVID SCANTLIN |
| Final | 1/10/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 2/14/2024 | OK to Issue CofO | DAVID SCANTLIN |