618 E 92ND ST 90002

Certificate Information: 618 E 92ND ST 90002

Application / Permit
22010-20000-00264
Plan Check / Job No.
B22VN00791
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan NEW DETACHED ADU AT THE REAR PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g
Permit Issued
Issued on 9/13/2022
Issuing Office
Current Status
CofO Issued on 1/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/19/2022 APPLICANT
Assigned to Plan Check Engineer 1/24/2022 CARLOS MONTES
Corrections Issued 1/24/2022 CARLOS MONTES
Plan Check Approved 5/14/2022 CARLOS MONTES
Issued 9/13/2022 APPLICANT
CofO in Progress 1/13/2023 LILIANA PORTILLO
CofO Issued 1/18/2023 DEROLD HAUFF
Permit Finaled 1/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/9/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 2/9/2022 JEANETTE VONG
Construction near power lines Cleared 4/9/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 4/21/2022 JEANETTE VONG
Sewer availability Cleared 4/21/2022 JEANETTE VONG

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B       ,
Contractor Daniel Pascuale; Lic. No.: 573067-B       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/5/2022 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 10/5/2022 Partial Approval LILIANA PORTILLO
Sewer 10/5/2022 Approved LILIANA PORTILLO
Underground Mechanical 10/5/2022 Approved LILIANA PORTILLO
Footing/Foundation/Slab 10/11/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/26/2022 Approved LILIANA PORTILLO
Gas Test 10/26/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 10/26/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 10/31/2022 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 10/31/2022 Approved LILIANA PORTILLO
Green Building Rough 10/31/2022 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 10/31/2022 Approved LILIANA PORTILLO
Insulation 11/3/2022 Corrections Issued LILIANA PORTILLO
Interior/Exterior Lathing 11/3/2022 Partial Approval LILIANA PORTILLO
Drywall Nailing 11/10/2022 Approved LILIANA PORTILLO
Green Building Rough 11/10/2022 Approved LILIANA PORTILLO
Insulation 11/10/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 11/10/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 1/6/2023 Approved LILIANA PORTILLO
ELECTRICAL-Final 1/6/2023 Approved LILIANA PORTILLO
Final 1/6/2023 Conditional Approval LILIANA PORTILLO
Gas Test 1/6/2023 Approved LILIANA PORTILLO
Green Building Final 1/6/2023 Approved LILIANA PORTILLO
HVAC-Final 1/6/2023 Approved LILIANA PORTILLO
PLUMBING-Final 1/6/2023 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/6/2023 SGSOV Approved LILIANA PORTILLO
Service/Power Release 1/6/2023 Approved LILIANA PORTILLO
Smoke Detectors 1/6/2023 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 1/6/2023 Approved LILIANA PORTILLO
Final 1/12/2023 OK to Issue CofO LILIANA PORTILLO