20639 W CANTARA ST 91306

Certificate Information: 20639 W CANTARA ST 91306

Application / Permit
22010-20000-00254
Plan Check / Job No.
B22VN00776
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 37'9" x 29'2" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 4/5/2022
Issuing Office
Current Status
CofO Issued on 7/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/19/2022 APPLICANT
Assigned to Plan Check Engineer 1/28/2022 JEFFREY TANGONAN
Corrections Issued 1/29/2022 JEFFREY TANGONAN
Applicant returned to address corrections 3/31/2022 JEFFREY TANGONAN
Issued 4/5/2022 APPLICANT
Building Plans Picked Up 4/6/2022 APPLICANT
CofO in Progress 10/17/2023 ALEXANDER HANDY
Permit Finaled 7/24/2024 JOHN JANSON
CofO Issued 7/24/2024 JOHN JANSON
Permit Finaled 7/24/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/14/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/14/2022 CARLOS AGUILERA
Sewer availability Cleared 2/14/2022 CARLOS AGUILERA
ZA Case Cleared 3/21/2022 MIGUEL GAMBOA
Roof/Waste drainage to street Cleared 4/2/2022 CARLOS AGUILERA

Contact Information

Contractor Garage To Apartment Inc General Construction; Lic. No.: 1041564-B 1102 SAN FERNANDO RD SUITE 206      SAN FERNANDO, CA 91340
Engineer Barragan,, Pedro; Lic. No.: C90531 329 N HUBBARD AVE      SAN FERNANDO, CA 91340

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/12/2022 Approved DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 4/27/2022 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 4/27/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/16/2022 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Approved STEVEN BACK
Interior/Exterior Lathing 6/27/2022 Partial Approval STEVEN BACK
Sewer 6/27/2022 Partial Approval STEVEN BACK
ELECTRICAL-Rough 7/5/2022 Approved STEVEN BACK
HVAC-Rough 7/5/2022 Approved STEVEN BACK
PLUMBING-Rough 7/5/2022 Approved STEVEN BACK
Sewer 7/5/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 7/11/2022 Approved STEVEN BACK
Green Building Rough 7/11/2022 Approved STEVEN BACK
Verify Sprinkler Sign Off 7/11/2022 Approved STEVEN BACK
Insulation 7/19/2022 Corrections Issued STEVEN BACK
Insulation 7/25/2022 Not Ready for Inspection STEVEN BACK
Drywall Nailing 8/4/2022 Corrections Issued STEVEN BACK
Underground Mechanical 11/3/2022 Approved STEVEN BACK
Final 12/7/2022 Corrections Issued STEVEN BACK
Green Building Final 12/7/2022 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 12/7/2022 SGSOV Not Ready STEVEN BACK
Service/Power Release 12/7/2022 Not Ready for Inspection STEVEN BACK
Smoke Detectors 12/7/2022 Not Ready for Inspection STEVEN BACK
Final 2/23/2023 Corrections Issued ALEXANDER HANDY
Green Building Final 2/23/2023 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 2/23/2023 SGSOV Approved ALEXANDER HANDY
Service/Power Release 2/23/2023 Not Ready for Inspection ALEXANDER HANDY
Smoke Detectors 2/23/2023 Approved ALEXANDER HANDY
ELECTRICAL-Final 10/16/2023 Approved ALEXANDER HANDY
Final 10/16/2023 OK to Issue CofO ALEXANDER HANDY
Green Building Final 10/16/2023 Approved ALEXANDER HANDY
HVAC-Final 10/16/2023 Approved ALEXANDER HANDY
PLUMBING-Final 10/16/2023 Approved ALEXANDER HANDY
Service/Power Release 10/16/2023 Approved ALEXANDER HANDY