10262 W KURT ST 91342
Certificate Information: 10262 W KURT ST 91342
- Application / Permit
- 22010-20000-00252
- Plan Check / Job No.
- B22VN00737
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 1-STORY 2-UNIT ACCESSORY DWELLING UNIT CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 10/8/2022
- Issuing Office
- Current Status
- CofO Issued on 10/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/15/2022 | DANIEL YIP |
| Corrections Issued | 2/16/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 9/8/2022 | DANIEL YIP |
| Plan Check Approved | 9/21/2022 | DANIEL YIP |
| Issued | 10/8/2022 | APPLICANT |
| CofO in Progress | 10/2/2023 | WILLIAM WREN |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
| CofO Issued | 10/13/2023 | RUBEN SALAS |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2022 | DAGOVERTO GUERRERO |
| Street Frontage | Cleared | 3/3/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/8/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 4/5/2022 | LAURINDA MEADE |
| Miscellaneous | Cleared | 4/6/2022 | YINGSHI HUANG |
| Construction near power lines | Cleared | 4/14/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 6/22/2022 | ANTHONY VARGAS |
| Specific Plan | Cleared | 8/23/2022 | CECILIA CASTILLO |
| Roof/Waste drainage to street | Cleared | 9/1/2022 | MEGAN GODINEZ |
| GPI Written Notices | Cleared | 9/6/2022 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 9/6/2022 | CARLOS MONTES |
| Miscellaneous | Cleared | 9/9/2022 | DANIEL SCHNEIDEREIT |
Contact Information
| Contractor | Next Generation Builders; Lic. No.: 1069728-B | , |
| Contractor | Polymath Development Group Inc; Lic. No.: 1069728-B | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/3/2022 | Corrections Issued | MATTHEW NELSON |
| Sewer | 11/3/2022 | Partial Approval | MATTHEW NELSON |
| Underground Mechanical | 11/3/2022 | Partial Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 11/15/2022 | Corrections Issued | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 11/22/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 12/16/2022 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 12/27/2022 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 12/27/2022 | Corrections Issued | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2022 | Partial Approval | WILLIAM WREN |
| Green Building Rough | 12/27/2022 | Not Ready for Inspection | WILLIAM WREN |
| HVAC-Rough | 12/27/2022 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 12/27/2022 | Corrections Issued | WILLIAM WREN |
| Rough-Elec/Plmb/HVAC | 12/27/2022 | Not Ready for Inspection | WILLIAM WREN |
| Verify Sprinkler Sign Off | 12/27/2022 | Not Ready for Inspection | WILLIAM WREN |
| ELECTRICAL-Rough | 2/3/2023 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2023 | Approved | WILLIAM WREN |
| Green Building Rough | 2/3/2023 | Approved | WILLIAM WREN |
| Verify Sprinkler Sign Off | 2/3/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 2/23/2023 | No Access for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 3/6/2023 | Not Ready for Inspection | WILLIAM WREN |
| Interior/Exterior Lathing | 3/6/2023 | Approved | WILLIAM WREN |
| Wood Frame | 3/6/2023 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 3/9/2023 | Approved | WILLIAM WREN |
| HVAC-Rough | 3/9/2023 | Approved | WILLIAM WREN |
| Insulation | 3/9/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 3/14/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 3/16/2023 | Approved | WILLIAM WREN |
| Shower Pan | 3/16/2023 | Approved | WILLIAM WREN |
| Final | 8/30/2023 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 8/30/2023 | Approved | WILLIAM WREN |
| Green Building Final | 8/30/2023 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 8/30/2023 | SGSOV Approved | WILLIAM WREN |
| Service/Power Release | 8/30/2023 | Not Ready for Inspection | WILLIAM WREN |
| Smoke Detectors | 8/30/2023 | Approved | WILLIAM WREN |
| Final | 9/5/2023 | Corrections Issued | WILLIAM WREN |
| Service/Power Release | 9/5/2023 | Not Ready for Inspection | WILLIAM WREN |
| Final | 9/12/2023 | OK to Issue CofO | WILLIAM WREN |
| Service/Power Release | 9/12/2023 | Approved | WILLIAM WREN |