15750 W MORRISON ST 91436

Certificate Information: 15750 W MORRISON ST 91436

Application / Permit
22010-20000-00232
Plan Check / Job No.
B22VN00628
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 60'-5" X 38'-0" IRREGULAR SHAPED 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/6/2022
Issuing Office
Current Status
CofO Issued on 7/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 COLIN LOREDO
Corrections Issued 2/23/2022 COLIN LOREDO
Quality Review Completed 2/28/2022 OMID HEDAYAT
Applicant returned to address corrections 4/11/2022 COLIN LOREDO
Plan Check Approved 7/6/2022 COLIN LOREDO
Issued 7/6/2022 APPLICANT
CofO in Progress 7/7/2023 VINCENT HANLEY
Permit Finaled 7/21/2023 DANIEL ORRANTE
CofO Issued 7/21/2023 DANIEL ORRANTE
Permit Finaled 7/21/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/25/2022 CARLOS AGUILERA
Permit Cleared 2/25/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 2/28/2022 CARLOS AGUILERA
Sewer availability Cleared 2/28/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 3/19/2022 DWIGHT SANKEY
Low Impact Development Cleared 4/22/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 5/2/2022 CARLOS AGUILERA
Trees in Parkway Cleared 6/2/2022 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 7/18/2022 Partial Approval JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 8/3/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 8/3/2022 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 8/4/2022 Approved VINCENT HANLEY
PLUMBING-Rough 8/5/2022 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 8/9/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/25/2022 Approved VINCENT HANLEY
Deputy Steel/Welding 9/16/2022 Approved VINCENT HANLEY
PLUMBING-Rough 10/14/2022 No Access for Inspection VINCENT HANLEY
BUILDING-Rough-Frame 10/20/2022 Approved VINCENT HANLEY
Green Building Rough 10/20/2022 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 10/20/2022 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 10/20/2022 Approved VINCENT HANLEY
Shower Pan 11/14/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 11/28/2022 Approved VINCENT HANLEY
Insulation 12/29/2022 Approved VINCENT HANLEY
Drywall Nailing 1/12/2023 Approved VINCENT HANLEY
ELECTRICAL-Final 5/2/2023 Approved VINCENT HANLEY
Final 5/2/2023 Corrections Issued VINCENT HANLEY
Green Building Final 5/2/2023 Approved VINCENT HANLEY
HVAC-Final 5/2/2023 Corrections Issued VINCENT HANLEY
PLUMBING-Final 5/2/2023 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/2/2023 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 5/2/2023 Approved VINCENT HANLEY
Smoke Detectors 5/2/2023 Approved VINCENT HANLEY
Final 6/29/2023 Corrections Issued VINCENT HANLEY
HVAC-Final 6/29/2023 Approved VINCENT HANLEY
PLUMBING-Final 6/29/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 6/29/2023 SGSOV Approved VINCENT HANLEY
Final 7/7/2023 OK to Issue CofO VINCENT HANLEY