11002 N BABBITT AVE 91344
Certificate Information: 11002 N BABBITT AVE 91344
- Application / Permit
- 22010-20000-00231
- Plan Check / Job No.
- B22VN00622
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 42'-6" X 20' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED GARAGE “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy."
- Permit Issued
- Issued on 4/5/2022
- Issuing Office
- Current Status
- CofO Issued on 5/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | SELLA BENYAMIN |
| Corrections Issued | 2/22/2022 | SELLA BENYAMIN |
| Quality Review Completed | 2/24/2022 | STEVEN KIM |
| Plan Check Approved | 4/5/2022 | SELLA BENYAMIN |
| Issued | 4/5/2022 | APPLICANT |
| CofO in Progress | 6/13/2023 | DAVID SCANTLIN |
| Permit Finaled | 5/10/2024 | DANIEL ORRANTE |
| CofO Issued | 5/10/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/10/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/9/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 3/22/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 4/5/2022 | WALTER RAMIREZ |
| Hold | Cleared | 4/28/2022 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/9/2022 | Approved | DAVID SCANTLIN |
| Deputy Reinf. Concrete | 5/18/2022 | Conditional Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 5/18/2022 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Partial Approval | SEAN WIRCH |
| Special/Order Compliance | 6/23/2022 | Corrections Issued | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 7/13/2022 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 7/25/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 8/16/2022 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 8/18/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 8/23/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 8/23/2022 | Approved | DAVID SCANTLIN |
| Green Building Rough | 8/23/2022 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 8/23/2022 | Approved | DAVID SCANTLIN |
| Insulation | 8/30/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Insulation | 9/8/2022 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 9/13/2022 | Approved | KRISTEN CAUSEY |
| Insulation | 9/13/2022 | Approved | KRISTEN CAUSEY |
| Underground Mechanical | 9/13/2022 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 9/26/2022 | Approved | DAVID SCANTLIN |
| Shower Pan | 9/26/2022 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 10/21/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Underground Mechanical | 12/7/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 12/12/2022 | No Access for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2022 | No Access for Inspection | DAVID SCANTLIN |
| Pre-Inspection | 12/12/2022 | No Access for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 5/2/2023 | Approved | DAVID SCANTLIN |
| Final | 5/2/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 5/2/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/2/2023 | SGSOV Not Ready | DAVID SCANTLIN |
| Smoke Detectors | 5/2/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/26/2023 | SGSOV Not Ready | STEVEN BACK |
| Final | 6/1/2023 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 6/1/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Approved | DAVID SCANTLIN |
| Final | 6/12/2023 | OK to Issue CofO | DAVID SCANTLIN |