11002 N BABBITT AVE 91344

Certificate Information: 11002 N BABBITT AVE 91344

Application / Permit
22010-20000-00231
Plan Check / Job No.
B22VN00622
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 42'-6" X 20' TWO STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) WITH ATTACHED GARAGE “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy."
Permit Issued
Issued on 4/5/2022
Issuing Office
Current Status
CofO Issued on 5/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 SELLA BENYAMIN
Corrections Issued 2/22/2022 SELLA BENYAMIN
Quality Review Completed 2/24/2022 STEVEN KIM
Plan Check Approved 4/5/2022 SELLA BENYAMIN
Issued 4/5/2022 APPLICANT
CofO in Progress 6/13/2023 DAVID SCANTLIN
Permit Finaled 5/10/2024 DANIEL ORRANTE
CofO Issued 5/10/2024 DANIEL ORRANTE
Permit Finaled 5/10/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 2/25/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/9/2022 CARLOS AGUILERA
Sewer availability Cleared 3/9/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/22/2022 CARLOS AGUILERA
Construction near power lines Cleared 4/5/2022 WALTER RAMIREZ
Hold Cleared 4/28/2022 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/9/2022 Approved DAVID SCANTLIN
Deputy Reinf. Concrete 5/18/2022 Conditional Approval DAVID SCANTLIN
Footing/Foundation/Slab 5/18/2022 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 5/31/2022 Partial Approval SEAN WIRCH
Special/Order Compliance 6/23/2022 Corrections Issued DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 6/29/2022 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 7/13/2022 Approved DAVID SCANTLIN
HVAC-Rough 7/25/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 8/2/2022 Approved SEAN HAUPT
Interior/Exterior Lathing 8/16/2022 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 8/18/2022 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 8/23/2022 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 8/23/2022 Approved DAVID SCANTLIN
Green Building Rough 8/23/2022 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 8/23/2022 Approved DAVID SCANTLIN
Insulation 8/30/2022 Not Ready for Inspection DAVID SCANTLIN
Insulation 9/8/2022 Approved KRISTEN CAUSEY
Drywall Nailing 9/13/2022 Approved KRISTEN CAUSEY
Insulation 9/13/2022 Approved KRISTEN CAUSEY
Underground Mechanical 9/13/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 9/26/2022 Approved DAVID SCANTLIN
Shower Pan 9/26/2022 Approved DAVID SCANTLIN
ELECTRICAL-Rough 10/21/2022 Not Ready for Inspection DAVID SCANTLIN
Underground Mechanical 12/7/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 12/12/2022 No Access for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 12/12/2022 No Access for Inspection DAVID SCANTLIN
Pre-Inspection 12/12/2022 No Access for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 5/2/2023 Approved DAVID SCANTLIN
Final 5/2/2023 Corrections Issued DAVID SCANTLIN
Green Building Final 5/2/2023 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 5/2/2023 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 5/2/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 5/26/2023 SGSOV Not Ready STEVEN BACK
Final 6/1/2023 Corrections Issued DAVID SCANTLIN
Green Building Final 6/1/2023 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Approved DAVID SCANTLIN
Final 6/12/2023 OK to Issue CofO DAVID SCANTLIN