22922 W OXNARD ST 91367
Certificate Information: 22922 W OXNARD ST 91367
- Application / Permit
- 22010-20000-00202
- Plan Check / Job No.
- B22VN00511
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 1-STORY 70'-0" X 91'-11" SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE AND TRELLIS. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/28/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/17/2022 | COLIN LOREDO |
| Corrections Issued | 2/24/2022 | COLIN LOREDO |
| Building Plans Picked Up | 3/1/2022 | APPLICANT |
| Quality Review Completed | 3/2/2022 | OMID HEDAYAT |
| Plan Check Approved | 7/28/2022 | COLIN LOREDO |
| Issued | 7/28/2022 | APPLICANT |
| CofO in Progress | 11/7/2023 | TROY SANDERS |
| Permit Finaled | 12/18/2023 | JOHN JANSON |
| CofO Issued | 12/18/2023 | JOHN JANSON |
| Permit Finaled | 12/18/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2022 | DAGOVERTO GUERRERO |
| Permit | Cleared | 3/3/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 3/15/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 4/5/2022 | LAURINDA MEADE |
| Trees in Parkway | Cleared | 6/1/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 7/12/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 7/13/2022 | DAGOVERTO GUERRERO |
| GPI Written Notices | Cleared | 7/28/2022 | COLIN LOREDO |
| Grading Pre-Inspection | Cleared | 7/28/2022 | COLIN LOREDO |
| Miscellaneous | Cleared | 7/28/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khansa,, Eyass Wafik; Lic. No.: C91758 | 2252 JOSIE AVE LONG BEACH, CA 90815 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/16/2022 | Approved | TROY SANDERS |
| Underground Mechanical | 10/6/2022 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 10/21/2022 | Conditional Approval | TROY SANDERS |
| Deputy Reinf. Concrete | 10/28/2022 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Partial Approval | TROY SANDERS |
| Pre-Inspection | 11/17/2022 | Partial Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 12/6/2022 | Partial Approval | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2022 | Partial Approval | TROY SANDERS |
| Green Building Rough | 12/6/2022 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Rough | 12/6/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 12/6/2022 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 12/6/2022 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 12/15/2022 | Partial Approval | TROY SANDERS |
| Green Building Rough | 12/15/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 12/15/2022 | Partial Approval | TROY SANDERS |
| Verify Sprinkler Sign Off | 12/15/2022 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 12/23/2022 | Approved | TROY SANDERS |
| Insulation | 12/23/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 12/23/2022 | Approved | TROY SANDERS |
| Shower Pan | 12/23/2022 | Approved | TROY SANDERS |
| Verify Sprinkler Sign Off | 12/23/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 1/4/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 5/5/2023 | Approved | TROY SANDERS |
| Service/Power Release | 5/5/2023 | Approved | TROY SANDERS |
| Final | 11/3/2023 | OK to Issue CofO | TROY SANDERS |
| Footing/Foundation/Slab | 11/3/2023 | Approved | TROY SANDERS |
| Green Building Final | 11/3/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/3/2023 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 11/3/2023 | Approved | TROY SANDERS |