7208 N FALLBROOK AVE 91307
Certificate Information: 7208 N FALLBROOK AVE 91307
- Application / Permit
- 22010-20000-00199
- Plan Check / Job No.
- B22VN00503
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 26'-6" X 26'-3" IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 9/2/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 2/1/2022 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 6/14/2022 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 7/7/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/13/2022 | APPLICANT |
| Plan Check Approved | 9/2/2022 | HAYATO TSUCHIYA |
| Issued | 9/2/2022 | APPLICANT |
| CofO in Progress | 8/27/2024 | JEFFREY HARTLINE |
| CofO Issued | 9/18/2024 | JOHN JANSON |
| Permit Finaled | 9/18/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 2/15/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 2/17/2022 | AMIR KASHFI |
| Hydrant and Access approval | Cleared | 3/16/2022 | CINDY JOSSELYN |
| Low Impact Development | Cleared | 5/10/2022 | SARAH YOUSSEF |
| Sewer availability | Cleared | 5/11/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 6/24/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/8/2022 | Approved | KRISTEN CAUSEY |
| PLUMBING-Rough | 12/8/2022 | Partial Approval | KRISTEN CAUSEY |
| Special/Order Compliance | 12/8/2022 | Approved | CHRIS CHRISTENSEN |
| Special/Order Compliance | 12/8/2022 | Partial Inspection | JESUS PINEDA |
| Wood Frame | 1/11/2023 | Partial Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 2/6/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| Green Building Rough | 2/6/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| PLUMBING-Rough | 2/6/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| Verify Sprinkler Sign Off | 2/6/2023 | Partial Inspection | KRISTEN CAUSEY |
| Wood Frame | 2/6/2023 | Partial Inspection | KRISTEN CAUSEY |
| Rough-Elec/Plmb/HVAC | 3/23/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| Wood Frame | 3/23/2023 | Not Ready for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 4/11/2023 | Approved | KRISTEN CAUSEY |
| Gas Test | 4/11/2023 | Partial Approval | KRISTEN CAUSEY |
| Green Building Rough | 4/11/2023 | Approved | KRISTEN CAUSEY |
| Rough-Elec/Plmb/HVAC | 4/11/2023 | Approved | KRISTEN CAUSEY |
| Verify Sprinkler Sign Off | 4/11/2023 | Approved | KRISTEN CAUSEY |
| Insulation | 4/21/2023 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 4/28/2023 | Approved | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 6/6/2023 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 11/13/2023 | Partial Approval | JEFFREY HARTLINE |
| HVAC-Rough | 11/20/2023 | Approved | JEFFREY HARTLINE |
| Final | 12/18/2023 | Corrections Issued | JEFFREY HARTLINE |
| Green Building Final | 12/18/2023 | Approved | JEFFREY HARTLINE |
| SGSOV-Seismic Gas S/O Valve | 12/18/2023 | SGSOV Approved | JEFFREY HARTLINE |
| Service/Power Release | 12/18/2023 | Not Ready for Inspection | JEFFREY HARTLINE |
| Smoke Detectors | 12/18/2023 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 2/2/2024 | Approved | JEFFREY HARTLINE |
| Final | 2/2/2024 | Partial Approval | JEFFREY HARTLINE |
| HVAC-Final | 2/2/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 2/2/2024 | Approved | JEFFREY HARTLINE |
| Service/Power Release | 2/2/2024 | Approved | JEFFREY HARTLINE |
| HVAC-Final | 2/6/2024 | Approved | JEFFREY HARTLINE |
| PLUMBING-Final | 2/6/2024 | Approved | JEFFREY HARTLINE |
| Final | 2/9/2024 | Corrections Issued | JEFFREY HARTLINE |
| Final | 7/1/2024 | Not Ready for Inspection | JEFFREY HARTLINE |
| Final | 8/26/2024 | Partial Approval | JEFFREY HARTLINE |
| Final | 8/27/2024 | OK to Issue CofO | JEFFREY HARTLINE |
| Special/Order Compliance | 8/30/2024 | Corrections Issued | HENRY KIM |